Walls; thickness ne 150mm 0.21 20.32 6.36 86.91 m3 113.59 150-300mm 0.15 14.51 4.54 86.91 m3 105.96 300-500mm 0.13 12.58 3.94 86.91 m3 103.43 exceeding 500mm 0.12 11.61 3.64 86.91 m3 102.16

Suspended slabs; thickness ne 150mm 0.27 26.12 8.18 86.91 m3 121.21 150-300mm 0.21 20.32 6.36 86.91 m3 113.59 300-500mm 0.19 18.38 5.76 86.91 m3 111.05 exceeding 500mm 0.19 18.38 5.76 86.91 m3 111.05

Labour Total hours £ £ £ rate £

IN SITU CONCRETE – cont

In situ concrete Grade C20/20 – cont Columns, piers and beams; cross-sectional area

ne 0.03m2 0.50 48.38 15.13 86.91 m3 150.42 0.03-0.10m2 0.40 38.70 12.11 86.91 m3 137.72 0.10-0.25m2 0.35 33.87 10.60 86.91 m3 131.38 0.25-1.00m2 0.35 33.87 10.60 86.91 m3 131.38 exceeding 1m2 0.28 27.09 8.48 86.91 m3 122.48

ADD to the above prices for sulphate-resisting cement – – – 10.50 m3 10.50 air entrained concrete – – – 5.78 m3 5.78 water repellant concrete – – – 5.51 m3 5.51

In situ concrete Grade C30/20 Bases, footings, pile caps and ground beams; thickness

ne 150mm 0.21 20.32 6.36 91.56 m3 118.24 150-300mm 0.18 17.42 5.45 91.56 m3 114.43 300-500mm 0.15 14.51 4.54 91.56 m3 110.61 exceeding 500mm 0.14 13.55 4.24 91.56 m3 109.35

Walls; thickness ne 150mm 0.22 21.29 6.66 91.56 m3 119.51 150-300mm 0.16 15.48 6.65 91.56 m3 113.69 300-500mm 0.13 12.58 5.41 91.56 m3 109.55 exceeding 500mm 0.12 11.61 4.99 91.56 m3 108.16

Suspended slabs; thickness ne 150mm 0.28 27.09 11.63 91.56 m3 130.28 150-300mm 0.22 21.29 9.15 91.56 m3 122.00 300-500mm 0.19 18.38 7.90 91.56 m3 117.84 exceeding 500mm 0.18 17.42 7.48 91.56 m3 116.46

Columns, piers and beams; cross-sectional area ne 0.03m2 0.53 51.28 22.03 91.56 m3 164.87 0.03-0.10m2 0.42 40.64 17.46 91.56 m3 149.66 0.10-0.25m2 0.36 34.83 14.96 91.56 m3 141.35 0.25-1.00m2 0.35 33.87 14.55 91.56 m3 139.98 exceeding 1m2 0.28 27.09 11.63 91.56 m3 130.28

ADD to the above prices for sulphate-resisting cement – – – 10.50 m3 10.50 air entrained concrete – – – 5.78 m3 5.78 water-repellant concrete – – – 5.51 m3 5.51

Labour Total hours £ £ £ rate £

PRECAST CONCRETE The cost of precast concrete item is very much dependent on the complexity of the moulds, the number of units to be cast from each mould and the size and the weight of the unit to be handled. The unit rates below are for standard precast items that are often to be found on a Civil Engineering project. It would be misleading to quote for indicative costs for tailor-made precast concrete units and it is advisable to contact specialist maunfacturers for guide prices.