chapter  24
17 Pages

Prospective analysis: Methodology and worked example

This chapter describes in detail, as a worked example, the ‘time impact’ method of analysis, as used to demonstrate a contractor’s extension of time entitlement.

This technique is applied to the construction of a new science block on a university campus. The contract value was £32 million, the contract start date was 6 August 2002 and the contract period was 87 weeks.