ABSTRACT

The ‘windows’ method of analysis is considered to be the most reliable of the various retrospective analysis techniques. Therefore, this chapter uses a worked example of the ‘windows’ method to demonstrate a contractor’s extension of time entitlement and his subsequent entitlement to timerelated costs.