ABSTRACT

In an effort to start the job and, having started it, to maintain reasonable progress, the contractor sometimes assumes more than its fair share of responsibility. An example of this may be observed in the contractor’s attitude to setting-out when faced with wholly or partially inadequate drawings. Very often, it does its best on the information available when it should be seeking to protect its own position.