ABSTRACT

MW deals with instructions in clause 3.4. Variations and the valuation of such instructions is covered in clause 3.6. Clause 3.6.2 states that the architect and the contractor must endeavour to agree a price before the contractor carries out an instruction, but clause 3.6.3 sets out the architect’s power to determine the value of work if no agreement can be reached.