ABSTRACT

Clause 17 of the Institution of Civil Engineers' Conditions of Contract states:

The Contractor shall be responsible for the true and proper setting out of the Works and for the correctness of the position, levels, dimensions and alignment of all parts of the Works and for the provision of all necessary instruments, appliances and labour in connection therewith. If at any time during the progress of the works any error shall appear or arise in the position, levels, dimensions or alignment of any part of the Works the Contractor, on being required so to do by the Engineer, shall, at his own expense, rectify such error to the satisfaction of the Engineer, unless such error is based on incorrect data supplied in writing by the Engineer or Engineer's representative, in which case the expense of rectifying same shall be borne by the Employer. The checking of any se~tting out or of any line or level by the Engineer or the Engineer's representative shall not in any way relieve the Contractor of his responsibility for the correctness thereof and the Contractor shall carefully protect and preserve all bench marks, sight rails, pegs and other things used in setting out works.