ABSTRACT

General characteristics of Herrenknecht TBM used in tunnel drivage are given in Table 2.

TBM came to the field in 31 May 2000 and machine assemblage time took 30 days. Table 3 summaries machine assemblage time for different jobs. A typical view of TBM is given in Figure 3.