ABSTRACT

You have now finished all eight steps of the Process and you have a decision to make: how should I schedule the project? You either can manually establish a calendar date for each activity or you can use PC software for your project. The answer is simple if you wish to provide closure to your project team. Your team has worked hard and long developing the project plan. By rough calculations, your endpoint date is within your team’s capability. You could either “turn them loose” now or get back with them later on the specific dates for their activities. In terms of member morale, you could provide closure on their need for knowing these dates now and before they exit the Session. There is a simple answer: do it now, manually!