ABSTRACT

The process of creating a project schedule follows directly from the scope definition process and builds from the WBS. The interface point for this is at the WP level in that the goal is to create a WP sequence and cycle time (duration) for each of the activities in the project, then meld these together to create a schedule. The sections that follow will construct the schedule in the following steps (PMI, 2013, p. 143): 1. Plan schedule management: As in all the KAs a management plan signifies how

that area will be processed. In this case, the plan focuses on the necessary processes to plan, execute, and control the project schedule.