ABSTRACT

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

ACCESS PLATFORMS

Access platform, scissor type, towed; height of platform 5 m 4.80 hour 4.80 - - - 4.80 1(8)

Access platform, scissor type, electric; height of platform 5 m 6.00 hour 6.00 - - - 6.00 1(1)

Access platform, scissor type, rough terrain, petrol driven;

height of platform 8 m 9.00 hour 9.00 50 1.5 2.0 9.90 1(6) Access platform, telescopic,

towed; height of platform 12 m 7.08 hour 7.08 - - - 7.08 1(13) Access platform telescopic,

petrol; height of platform 14 m 9.95 hour 9.95 50 2.0 3.0 11.17 1(11)

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

ACCESS PLATFORMS - continued

Access platform, telescopic, vehicle mounted (DERV)

height of platform 12 m 18.88 hour 18.88 50 2.0 3.0 20.22 1(16)

height of platform 15 m 19.74 hour 19.74 50 3.0 3.0 21.75 1(*) Access platform underbridge type (Simon UB40) 31.50 hour 31.50 - - - 31.50 1(13)

AGRICULTURAL TYPE TRACTORS

Tractor 4.82 t, 4WD (74 kW) 12.52 hour 12.52 75 9.0 2.0 16.65 32(63) Tractor (68 HP) c/w 1T Hiab lift 14.47 hour 14.47 75 9.0 2.0 18.60 32(62) Tractor (68 HP) with front end loading bucket (0.33 m³) 13.74 hour 13.74 75 9.0 2.0 17.87 37(51) Tractor (68 HP) with Hydro seeding equipment 14.63 hour 14.63 75 9.0 2.0 18.76 37(*) Tractor (68 HP) includes 2 tool compressor and front end loading bucket 15.03 hour 15.03 75 10.5 3.5 19.92 - Tractor (68HP) with Fencing Auger 13.66 hour 13.66 75 9.0 3.5 17.85 -

ASPHALT/ROAD CONSTRUCTION

Asphalt pavers maximum paving width 3.60 m, 24kW engine 24.41 hour 24.41 80 6.2 4.0 27.51 2(1) extending up to 4 m, 35 kW engine 43.90 hour 43.90 80 8.2 5.0 48.04 2(1) maximum paving width 9 m, 80kW

engine 79.58 hour 79.58 80 17.0 3.0 87.98 2(3) Associated equipment

tar sprayer (100 litre) 1.66 hour 1.66 80 9.0 3.0 6.11 29(6) self propelled chip spreader 6.45 hour 6.45 80 9.0 3.0 10.90 2(9) heating iron 1.19 hour 1.19 - - - 1.19 - insulated (20 tonne) tipper (DERV) 21.60 hour 21.60 80 14.0 7.0 37.18 14(18) 3 point roller 8.06 hour 8.06 80 6.0 7.5 11.16 23(4)

Surface planers, cold plane planing width 0.5 m, 72 kW 12.10 hour 12.10 80 6.0 5.0 15.12 2(12) planing width 2.1 m, 390 kW 50.43 hour 50.43 80 12.0 5.0 56.48 2(14)

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

Surface planers, heat plane planing width up to 1.0 m re-mixer 24.21 hour 24.21 80 8.0 3.0 28.17 2(11) planing width up to 4.5 m remixer 74.64 hour 74.64 80 13.0 5.0 81.19 2(-)

Concrete pavers maximum paving width 6.00 m, depth 300 mm, 123 kW 70.61 hour 70.61 80 17.0 3.0 79.01 - maximum paving width 12.8 m depth 500 mm 340 kW 102.89 hour 102.89 80 72.0 3.0 138.49 -

Concrete Slipform paver/trimmer maximum paving width 5 m 84.72 hour 84.72 80 24.0 3.0 96.59 -

Slipformed Concrete joint and bar inserter 10.08 hour 10.08 80 4.0 3.0 12.06 - Concrete Slipform finisher 15.22 hour 15.22 80 9.0 3.0 19.67 -

COMPACTION

Plate compactors Vibrating compaction plate 64 kg unit weight 360 mm wide (petrol) 47.71 week 1.19 85 0.8 3.0 2.02 22(6) Vibrating compaction plate 140 kg unit weight 400 mm wide (petrol) 51.57 week 1.29 85 1.2 3.0 2.53 22(8) Vibrating compaction plate 180 kg unit weight 600 mm wide 52.30 week 1.31 85 0.9 3.0 1.78 22(10) Vibrating compaction plate 345 kg unit weight 600 mm wide 55.15 week 1.38 85 1.2 3.0 2.01 22(12) Vibrating compaction trench plate 300 mm wide 41.84 week 1.05 85 0.8 3.0 1.47 22(*) Tamper BT60 61 kg (petrol) 47.71 week 1.19 85 0.8 3.0 2.02 22(1)

CLEANERS/SWEEPERS

Front Tractor or Truck mounted 2 m wide (excluding vehicle) 71.89 week 1.80 - - - 1.80 14(36) Towed sweeper diesel engined 107.44 week 2.69 75 4.0 4.0 6.75 - Glutton type mobile gully sucker 13.90 hour 13.90 75 12.0 3.0 25.95 -

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

MOBILE COMPRESSORS (SILENCED OR SUPER SILENCED)

Compressors, single tool 1.80 m³/min, 13 kW 119.05 week 2.98 85 3.2 4.0 4.68 4(1)

Compressors, two tool 2.80 m³/min, 23 kW, two tool 135.26 week 3.38 85 4.5 3.0 5.74 4(2) 3.70 m³/min, 28 kW, two tool 159.83 week 4.00 85 5.9 3.0 7.10 4(3) 4.80 m³/min, 34 kW, two tool 184.94 week 4.62 85 6.8 3.0 8.19 4(4) 7.30 m³/min, 53 kW, two tool 240.70 week 6.02 85 10.2 3.0 11.38 4(6)

Compressors, four tool 11.30 m³/min, 95 kW, four tool 390.56 week 9.76 85 19.0 3.0 19.74 4(8) 15.50 m³/min, 160 kW, four tool 433.96 week 10.85 85 32.0 3.0 27.66 4(9) 16.00 m³/min, 160 kW, four tool 491.81 week 12.30 85 32.0 3.0 29.11 4(9) 18.40 m³/min, 235 kW, four tool 423.63 week 10.59 85 47.0 3.0 35.28 4(10) 22.10 m³/min, 216 kW, four tool 516.62 week 12.92 85 43.0 3.0 35.51 4(11) 25.30 m³/min, 216 kW 619.94 week 15.50 85 43.0 3.0 38.09 4(11)

Reciprocating compressors up to 4 cfm for small air tools 240v 44.14 week 1.10 85 3.0 3.0 2.68 4(16) up to 9 cfm for small air tools 240v 79.04 week 1.98 85 3.0 3.0 3.56 4(16) up to 13 cfm for small air tools 240v 87.15 week 2.18 85 4.0 3.0 4.28 4(16)

Petrol driven hydraulic power unit c/w breaker (63 kg) 73.52 week 1.84 85 1.5 3.0 2.63 -

Tractair, wheeled loader mounted compressor, c/w hoses, 4 steels and 2 tarmac cutters 19.53 hour 19.53 85 12.0 0.0 25.65 4(12)

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

COMPRESSOR TOOLS (cw 50 ft/15 m HOSE)

chipping hammer, 0.7 m³/min 35.30 week 0.88 - - - 0.88 30(4) brick hammer/demolition pick,1.4 m³/ min 13.12 week 0.33 - - - 0.33 - clay spade,1.6 m³/min 17.15 week 0.43 - - - 0.43 30(3) road breaker, 2.4 m³/min 32.58 week 0.81 - - - 0.81 30(1) hand hammer drill, 0.9 m³/min 37.38 week 0.93 - - - 0.93 30(*) light rock drill 28, 1.2 m³/min 44.76 week 1.12 - - - 1.12 30(5) medium rock drill 30, 1.5 m³/min 61.67 week 1.54 - - - 1.54 30(6) heavy rock drill 33, 2.4 m³/min 82.08 week 2.05 - - - 2.05 30(7) scabbler 1 head hand, 0.3 m³/min 74.96 week 1.87 - - - 1.87 - scabbler 3 head hand, 0.7 m³/min 89.95 week 2.25 - - - 2.25 - scabbler 5 head trolley, 3.1 m³/min 198.39 week 4.96 - - - 4.96 - scabbler 7 head trolley, 4.5 m³/min 232.83 week 5.82 - - - 5.82 - needle gun/descaler, 0.3 m³/min 47.79 week 1.19 - - - 1.19 30(4) concrete crack cutter, 0.7 m³/min 106.07 week 2.65 - - - 2.65 - rammer, 1.5 m³/min 17.45 week 0.44 - - - 0.44 22(1) air lance, variable valve, 0.3 m³/min 16.84 week 0.42 - - - 0.42 - impact wrench 12 mm drive, 0.4m³/min 39.38 week 0.98 - - - 0.98 - impact wrench 25 mm drive, 0.4m³/min 66.62 week 1.67 - - - 1.67 - trench sheet driver, 2.4 m³/min 85.87 week 2.15 - - - 2.15 - steel post driver (crash barrier), 2.4 m³/min 86.03 week 2.15 - - - 2.15 - angle grinder 9", 0.8 m³/min 45.14 week 1.13 - - - 1.13 - disc cutter 12", 1.4 m³/min 56.30 week 1.41 - - - 1.41 - poker vibrator P35 (35 mm), 2.4 m³/min 41.43 week 1.04 - - - 1.04 6(24) poker vibrator P54 (54 mm), 2.4 m³/min 52.36 week 1.31 - - - 1.31 6(24) poker vibrator P70 (70 mm), 2.4 m³/min 60.96 week 1.52 - - - 1.52 6(24) rotary drill, 0.3 m³/min 41.43 week 1.04 - - - 1.04 - extra air hose, 25mm x 15 m hose 9.10 week 0.23 - - - 0.23 -

extra air hose, 38mm x 15 m hose 25.45 week 0.64 - - - 0.64 -

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

CONCRETE EQUIPMENT

Poker vibrators air pokers (see compressor tables) 6(24) 50 mm, petrol 48.53 week 1.21 75 2.0 2.0 3.12 6(21) 50 mm, electric 48.53 week 1.21 - - - 1.21 6(23) 75 mm, diesel 48.53 week 1.21 75 1.5 2.0 1.90 6(22) 75 mm, electric 49.45 week 1.24 - - - 1.24 6(23)

Tampers and screeders vibrating tamper and handles (petrol) 69.05 week 1.73 75 2.0 2.0 3.64 6(32) razor-back screeder (per metre) 43.16 week 1.08 75 1.5 2.0 1.77 - double beam screeder (7.6 m wide) 95.82 week 2.40 75 1.5 2.0 3.09 6(34)

Rotary power float (petrol), 687 mm diameter 49.45 week 1.24 75 2.0 2.0 3.15 6(36) 865 mm diameter 59.66 week 1.49 75 2.0 2.0 3.40 6(36)

Reinforcement power bar cropper (electric) 78.51 week 1.96 - - - 1.96 3(6)

Reinforcement power bar bender (electric) 97.14 week 2.43 - - - 2.43 3(3)

Compaction stud roller 16.66 week 0.42 75 1.5 2.0 1.11 -

MIXERS

Concrete mixer 3/2 tip up, 240 v 36.25 week 0.91 - - - 0.91 5(1) 4/3, petrol 40.23 week 1.01 75 1.5 2.0 2.44 5(1) 5/3½, diesel 60.95 week 1.52 75 1.2 2.0 2.07 5(2) 8½/6, diesel, skip fed 77.15 week 1.93 75 1.3 2.0 2.53 5(6)

Paddle screed mixer 5/3½ diesel 44.32 week 1.11 75 1.2 2.0 1.66 5(13) Truck mixer 6 m³ 31.34 hour 31.34 75 14.0 3.0 37.83 5(40)

CONCRETE PUMPS

Air operated 'SEM' pump 7.50 hour 7.50 - - - 7.50 6(1) Truck mounted 45 cm/hr (air pump) 32.86 hour 32.86 75 8.0 3.0 36.57 6(6) Schwing slurry pump 12.07 hour 12.07 75 1.5 3.0 12.77 6(1)

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

CONCRETE SKIPS

Rollover type 0.5 yd³ (0.38 m³) 26.75 week 0.67 - - - 0.67 8(22)

Dual flow type 0.5 yd³ (0.38 m³) 29.61 week 0.74 - - - 0.74 8(22) 0.75 yd³ (0.57 m³) 34.98 week 0.87 - - - 0.87 8(23) 1.00 yd³ (0.76 m³) 39.79 week 0.99 - - - 0.99 8(24)

CRANES

7 t mobile (site use) 18.23 hour 18.23 60 3.4 10.0 19.58 7(2) Truck mounted mobile (wheeled) cranes

15 t SWL 30.37 hour 30.37 60 5.1 10.0 32.39 7(20) 20 t SWL 36.49 hour 36.49 60 5.5 10.0 38.67 7(20) 25 t SWL 46.11 hour 46.11 60 5.8 10.0 48.41 7(21) 40 t SWL 65.89 hour 65.89 60 6.3 10.0 68.38 7(23) 50 t SWL 88.07 hour 88.07 60 8.5 10.0 91.44 7(24) 70 t SWL 124.18 hour 124.18 60 10.0 10.0 128.14 7(25) 90 t SWL 131.47 hour 131.47 60 12.0 10.0 136.22 7(25)

Crawler cranes 10 t 25.64 hour 25.64 60 3.0 10.0 26.83 7(12) 20 t 27.83 hour 27.83 60 3.5 10.0 29.22 7(12) 30 t 30.50 hour 30.50 60 3.5 10.0 31.89 7(13)

DIESEL GENERATORS

500 w Petrol 110 or 240 V 50.72 week 1.27 85 0.8 3.0 2.15 11(1) 1.5 kVA Petrol 110 or 240 V 63.36 week 1.58 85 1.1 3.0 2.78 11(1) 2.5 kVA Petrol 110 or 240 V 75.46 week 1.89 85 1.7 3.0 3.75 11(2) 4 kVA diesel dual voltage 90.10 week 2.25 85 1.6 3.0 3.09 11(2) 7 kVA diesel dual voltage 119.45 week 2.99 85 1.8 3.0 3.94 11(3) 7.5 kVA diesel dual voltage 132.91 week 3.32 85 1.8 3.0 4.27 11(3) 7.5 kVA diesel (super silenced) 136.50 week 3.41 85 1.8 3.0 4.36 11(3) 10 kVA diesel dual voltage 167.22 week 4.18 85 2.1 4.0 5.29 11(3) 15 kVA diesel dual voltage 209.03 week 5.23 85 3.0 4.0 6.82 11(4) 25 kVA diesel 3 phase 440 V 262.77 week 6.57 85 4.9 5.0 9.19 11(5) 55 kVA diesel 3 phase 440 V 316.54 week 7.91 85 10.9 5.0 13.75 11(7) 75 kVA diesel 3 phase 440 V 369.54 week 9.24 85 17.0 5.0 18.34 11(8)

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

DIESEL GENERATORS - continued

125 kVA diesel 3 phase 440 V 491.93 week 12.30 85 21.8 5.0 23.97 11(11) 200 kVA diesel 3 phase 440 V 668.30 week 16.71 85 40.0 5.0 38.13 11(12) 250 kVA diesel 3 phase 440 V 861.74 week 21.54 85 48.0 5.0 47.24 11(13)

EXCAVATORS

(Bucket capacity refers to SAE heaped) Mini Excavators (tracked)

Kubota KX36, 1435 kg (0.04 m³) 362.29 week 9.06 85 4.0 5.0 11.20 10(15) Kubota KX41, 1565 kg (0.045 m³) 362.29 week 9.06 85 4.0 5.0 11.20 10(15) Kubota KX71, 2835 kg (0.075 m³) 489.59 week 12.24 85 5.0 5.0 14.92 10(16) Kubota U45, 4500 kg (0.12m3) 489.59 week 12.24 85 5.0 5.0 14.92 10(16) Hitachi ZX16, 1660 kg (0.05 m³) 342.71 week 8.57 85 4.0 5.0 10.71 10(15)

Mini Excavators (wheeled) Komatsu PW30, 3000 kg 407.28 week 10.18 85 5.0 5.0 12.86 10(15)

Hydraulic crawler mounted backacter approximate data: weight up to SAE bucket kW

3.5 tonne 0.10 m³ 25 16.17 hour 16.17 80 4.0 7.5 18.23 10(17) 6.5 tonne 0.25 m³ 40 17.14 hour 17.14 80 5.0 7.5 19.72 10(19) 8.5 tonne 0.30 m³ 50 18.03 hour 18.03 80 8.0 7.5 22.16 10(19)

11.5 tonne 0.40 m³ 63 19.81 hour 19.81 80 9.5 7.5 24.71 10(20) 14.5 tonne 0.45 m³ 70 22.85 hour 22.85 80 10.5 7.5 28.27 10(21)

16 tonne 0.55 m³ 80 25.96 hour 25.96 80 12.0 7.5 32.15 10(21) 19 tonne 0.70 m³ 90 31.72 hour 31.72 80 14.0 7.5 38.94 10(22) 21 tonne 1.00 m³ 100 34.83 hour 34.83 80 16.0 7.5 43.09 10(22) 23.5 tonne 1.00 m³ 115 40.20 hour 40.20 80 19.0 7.5 50.00 10(23)

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

Hydraulic crawler mounted backacter; approximate data:

weight up to SAE bucket kW 28.5 tonne 1.20 m³ 130 46.47 hour 46.47 75 24.0 7.5 58.08 10(24) 35.5 tonne 1.20 m³ 160 87.90 hour 87.90 75 31.0 7.5 102.90 10(25) 40 tonne 1.60 m³ 180 89.15 hour 89.15 75 36.0 7.5 106.57 10(26) 50 tonne 2.00 m³ 205 96.69 hour 96.69 75 45.0 7.5 118.46 10(26) 60 tonne 2.50 m³ 235 116.39 hour 116.39 75 52.0 7.5 141.55 10(27)

20 tonne (0.6 m³), 15 m reach cable operated boom 43.25 hour 43.25 80 16.0 7.5 51.51 10(22)

30 tonne (0.8 m³), 20 m reach cable operated boom 75.35 hour 75.35 75 24.0 7.5 86.96 10(24)

Hydraulic wheeled backacter weight up to SAE bucket 3.5 tonne 0.10 m³ 13.36 hour 13.36 80 4.0 7.5 15.42 10(17) 6.5 tonne 0.27 m³ 15.69 hour 15.69 80 5.0 7.5 18.27 10(19) 8 tonne 0.34 m³ 17.50 hour 17.50 80 8.0 7.5 21.63 10(19) 11 tonne 0.43 m³ 16.07 hour 16.07 80 9.5 7.5 20.97 10(19) 15 tonne 0.47 m³ 22.82 hour 22.82 80 10.5 7.5 28.24 10(21) 19 tonne 1.00 m³ 27.61 hour 27.61 80 14.0 7.5 34.83 10(22)

Backhoe loader, wheeled

JCB 3CX, 1.1 m³ 15.18 hour 15.18 75 7.5 6.0 18.76 10(36) Volvo BL61, 1.0 m³ 15.53 hour 15.53 75 7.5 6.0 19.11 10(36) JCB 2CX, 0.6 m³ 12.68 hour 12.68 75 7.5 6.0 16.26 10(34) Hymac 180C, 0.95 m³ 15.16 hour 15.16 75 7.5 6.0 18.74 10(36)

Percussion breaker attachments Montabert 140 (380 kg) with steels 155.10 week 3.88 - - - 3.88 10(30) Montabert 300 (606 kg) with steels 218.88 week 5.47 - - - 5.47 10(30) Montabert 900 (1133 kg) with steels 327.45 week 8.19 - - - 8.19 10(31) Montabert V 1200 (1570 kg) with steels 437.75 week 10.94 - - - 10.94 10(34)

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

EXCAVATORS - continued

Other hydraulic attachments Rock backacter bucket (ripper teeth) 120.64 week 3.02 - - - 3.02 - Ditch bucket (c/w side cutters) 81.00 week 2.03 - - - 2.03 - Trapezoidal bucket 89.61 week 2.24 - - - 2.24 - Clamshell Grab (1.0 m³) 161.99 week 4.05 - - - 4.05 - Rock handling Grab (up to 3 t) 151.66 week 3.79 - - - 3.79 - Scrap handling Grab (up to 1 t) 151.66 week 3.79 - - - 3.79 - Scrap shears 201.64 week 5.04 - - - 5.04 - Grab bucket 89.61 week 2.24 - - - 2.24 - Demolition ball 29.31 week 0.73 - - - 0.73 - Large scoop bucket 1.40 m³ 72.38 week 1.81 - - - 1.81 - Single shank ripper 37.92 week 0.95 - - - 0.95 - Flat track shoes (highway use) 20.68 week 0.52 - - - 0.52 -

HOISTS, LIFTING AND HANDLING

Telescopic handler 4WD lifting up to 2.50 tonnes 11.63 hour 11.63 25 75.0 4.0 23.33 15(12) Electric forklift 2.5 tonnes 4.90 hour 4.90 - - - 4.90 Rough terrain forklift (Manitou M50) 5.0 tonnes 14.67 hour 14.67 75 7.5 4.0 18.18 15(20) Lorry (8T) with 1T Hiab 21.01 hour 21.01 75 7.5 4.0 24.52 14(10) Mast section per 1.5 m (max x 91m) 9.81 week 0.25 - - - 0.25 - Tirfor winch TU 32 (3T SWL) 44.69 week 1.12 - - - 1.12 36(14) Tirfor winch TU 16 32.17 week 0.80 - - - 0.80 36(12) Chain hoist up to 2000 kg capacity 30.21 week 0.76 - - - 0.76 - Chain hoist up to 3000 kg capacity 32.17 week 0.80 - - - 0.80 - Electric cable hoist 200 kg SWL with gantry 69.28 week 1.73 - - - 1.73 36(6) Engine crane up to 10 CWT 31.38 week 0.78 75 2.0 3.0 1.71 36(1) (500 kg SWL)

Cost per working hour Hire Hire DSR

Rate Period Plant Usage Fuel Oil etc. Total £ £ % l/hr % fuel £

PILING PLANT

(weight = piston weight) Piling hammer, double acting (air) weight up to 3,000 kg 856.18 week 21.40 - - - 21.40 17(5) weight up to 4,000 kg 1,083.72 week 27.09 - - - 27.09 17(6) weight up to 6,000 kg 1,210.97 week 30.27 - - - 30.27 17(7) Piling hammer, double acting hydraulic weight up to 5,000 kg 416.43 week 10.41 - - - 10.41 - weight up to 10,000 kg 449.74 week 11.24 - - - 11.24 - weight up to 50,000 kg 624.64 week 15.62 - - - 15.62 - weight up to 100,000 kg 1,299.26 week 32.48 - - - 32.48 - Piling hammer, single acting diesel weight up to 1,500 kg 674.33 week 16.86 75 6.0 5.0 19.70 17(30) weight up to 2,500 kg 1,084.86 week 27.12 75 11.0 5.0 32.32 17(32) weight up to 3,500 kg 1,640.05 week 41.00 75 14.0 5.0 47.62 17(34) weight up to 5,000 kg 1,782.87 week 44.57 75 16.0 5.0 52.13 - weight up to 5,700 kg 1,894.25 week 47.36 75 18.0 5.0 55.87 17(35) weight up to 6,200 kg 2,576.57 week 64.41 75 26.0 5.0 76.70 17(36) weight up to 8,000 kg 2,998.29 week 74.96 75 30.0 5.0 89.14 17(37) weight up to 10,000 kg 3,290.62 week 82.27 75 35.0 5.0 98.81 17(38) Hanging leaders for use with diesel hammers length 8.5 m 274.81 week 6.87 - - - 6.87 17(*) length 15.5 m 470.38 week 11.76 - - - 11.76 17(53) length 22.5 m 540.00 week 13.50 - - - 13.50 17(54) Flexible hose for compressed air (per 30 ft length) 38 mm diameter 24.99 week 0.62 - - - 0.62 17(24) 50 mm diameter 31.65 week 0.79 - - - 0.79 17(25) Piling extractors (including compressor) BSP HD10 unit weight 3,000 kg 1,382.49 week 34.56 75 20.0 4.0 43.92 17(20) BSP HD15 unit weight 4,580 kg 1,613.12 week 40.33 75 30.0 4.0 54.37 17(21) Vibratory hammer/extractor, hydraulic cent. force - 16 tonne, pulling force -12.5 tonne 1,631.25 week 40.78 75 30.0 7.5 55.29 17(39) cent. force - 59 tonne, pulling force -36 tonne 3,677.51 week 91.94 75 30.0 7.5 106.45 17(41) cent. force - 200 tonne, pulling

force -80 tonne 11,783.09 week 294.58 75 30.0 7.5 309.09 17(43)

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

ROLLERS

Pedestrian rollers 475 kg trench compactor 2.49 hour 2.49 80 0.9 7.5 2.95 23(11) 600 kg double drum vibratory 3.60 hour 3.60 80 1.0 7.5 4.11 23(11) 928 kg double drum vibratory 4.03 hour 4.03 80 1.6 7.5 4.85 23(12) 1300 kg double drum vibratory 4.43 hour 4.43 80 2.3 7.5 5.62 23(13) 159 kg single drum vibratory 2.39 hour 2.39 80 0.8 7.5 2.80 23(9) 466 kg single drum vibratory 2.49 hour 2.49 80 0.9 7.5 2.96 23(9)

Self propelled rollers 2½ tonne double vibratory 7.58 hour 7.58 80 3.6 7.5 9.45 23(21) 5 tonne double vibratory 10.24 hour 10.24 80 3.8 7.5 12.22 23(22)

Self propelled rollers 9 tonne single drum vibratory 15.57 hour 15.57 80 10.0 7.5 20.73 23(23) Bomag BW55E single drum vibratory 16.47 hour 16.47 80 11.0 7.5 22.15 23(25) Bomag BW71E single drum vibratory 17.61 hour 17.61 80 16.3 7.5 26.02 23(26) Bomag BW217D single drum vibratory 25.40 hour 25.40 80 23.8 7.5 37.67 23(*) Bomag BC672 RB Refuse

compactor 21.48 hour 21.48 80 42.0 7.5 43.15 23(*)

3 wheel dead weight 10 tonne 10.85 hour 10.85 80 16.0 7.5 19.11 23(3) 10 tonne 10.03 hour 10.03 80 15.0 7.5 17.77 23(3) 12 tonne 10.85 hour 10.85 80 17.0 7.5 19.62 23(4)

Rubber tyred rollers 10 tonne 14.32 hour 14.32 80 17.0 7.5 23.09 23(7) 6 tonne 13.86 hour 13.86 80 12.0 7.5 20.05 23(6)

Towed vibratory rollers Bomag BW6 (6 tonne) 7.95 hour 7.95 80 7.5 7.5 11.82 23(17) Bomag BW6S Sheepsfoot 8.36 hour 8.36 80 4.0 7.5 10.42 23(30)

Dual Purpose Rollers Benford MBR71B with breaker 3.66 hour 3.66 80 4.0 7.5 5.72 - Bomag BW138 with breaker 4.16 hour 4.16 80 4.0 7.5 6.22 -

Cost per working week

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

SCAFFOLDING AND ACCESSORIES

Tube alloy per metre 0.78 4 week 0.20 - - - 0.20 25(2) Tube galvanised per metre 0.44 4 week 0.11 - - - 0.11 25(1) Boards - per 4 metre length 0.55 4 week 0.14 - - - 0.14 25(19) Base plates adjustable each 0.48 4 week 0.12 - - - 0.12 25(8) Base plates fixed each 0.25 4 week 0.06 - - - 0.06 25(7) Clips each (all types) 0.25 4 week 0.06 - - - 0.06 25(7) Couplers each (all types) 0.80 4 week 0.20 - - - 0.20 25(7) Spigots each ledgers and braces/m 0.50 4 week 0.12 - - - 0.12 25(7) Putlog 1.5 m blade end each steel 0.70 4 week 0.17 - - - 0.17 25(3) Putlog 1.8 m blade end each steel 0.70 4 week 0.17 - - - 0.17 25(5) Reveal screws each 0.17 4 week 0.04 - - - 0.04 25(7) Castor wheel rubber tyred w/brake 5.97 4 week 1.49 - - - 1.49 25(16)

ACCESS STAGING AND TOWERS

Alloy towers base size 1.8 x 0.80 height to platform 2.6 m 47.38 week 47.38 - - - 47.38 - Extra sections per 2 m rise (max 3) 28.16 week 28.16 - - - 28.16 - Alloy towers base size 1.8 x 1.80 height to platform 2.6 m 52.38 week 52.38 - - - 52.38 - Extra sections per 2 m rise (max 7) 32.13 week 32.13 - - - 32.13 - Alloy stairwell tower per 2 m rise 38.70 week 38.70 - - - 38.70 - Steel towers base size 1.80 x 1.80 height to platform 1.80 m 23.74 week 23.74 - - - 23.74 - Extra sections per 0.60 m rise 6.32 week 6.32 - - - 6.32 - Steel towers base size 3.80 x 3.80 height to platform 1.80 m 41.66 week 41.66 - - - 41.66 - Extra sections per 1.20 m rise 14.18 week 14.18 - - - 14.18 - Castor wheels 5.97 4 week 1.49 - - - 1.49 25(14) Toe boards per 4 metre length 0.75 4 week 0.19 - - - 0.19 25(19) Toe boards hinged per 4 metre length 0.38 4 week 0.10 - - - 0.10 - Handrail (included with towers) 0.24 4 week 0.06 - - - 0.06 - Stair tread complete 0.40 4 week 0.10 - - - 0.10 - Brick guard 3.47 4 week 0.87 - - - 0.87 - Bridging Unit per 1.00 m 4.52 week 4.52 - - - 4.52 -

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

TRACTORS

Tractor dozers with single equipment 50 kW 14.48 hour 14.48 80 11.0 7.5 20.16 32(1) 74 kW 19.94 hour 19.94 80 14.5 7.5 27.42 32(2) 104 kW 34.73 hour 34.73 80 21.0 6.0 45.41 32(4) 212 kW 82.34 hour 82.34 80 38.0 6.0 101.67 32(7) 276 kW 95.35 hour 95.35 80 53.0 7.5 122.70 32(9) 67 kW 20.22 hour 20.22 80 14.5 7.5 27.70 32(1) 123 kW 39.30 hour 39.30 80 25.0 7.5 52.20 32(5)

Dozer attachments single shank ripper 3.66 hour 3.66 - - - 3.66 - triple shank ripper 6.66 hour 6.66 - - - 6.66 - 'U' dozer blade 2.00 hour 2.00 - - - 2.00 - angle dozer blade 2.08 hour 2.08 - - - 2.08 - skeleton blade 2.08 hour 2.08 - - - 2.08 -

Tractor loaders 0.8 m³ 17.83 hour 17.83 75 11.0 7.5 23.15 32(11) 1.5 m³ 27.65 hour 27.65 75 19.0 7.5 36.84 32(15) 2.0 m³ 47.13 hour 47.13 75 25.0 7.5 59.22 32(16) 3.0 m³ 60.34 hour 60.34 75 34.0 7.5 76.79 32(18) 3.0 m³ 60.65 hour 60.65 75 34.0 7.5 77.10 32(18)

Wheeled loaders 0.55 m³ 33 kW 11.55 hour 11.55 75 8.0 7.5 15.42 32(28) 0.75 m³ 41 kW 13.66 hour 13.66 75 9.5 7.5 18.26 32(28) 1.60 m³ 83 kW 27.84 hour 27.84 75 11.0 7.5 33.16 32(32) 2.70 m³ 115 kW 33.05 hour 33.05 75 19.0 7.5 42.24 32(36) 3.10 m³ 135 kW 49.06 hour 49.06 75 23.0 7.5 60.19 32(37) 3.85 m³ 194 kW 65.31 hour 65.31 80 30.0 7.5 80.79 32(39) 6.00 m³ 310 kW 138.29 hour 138.29 80 53.0 7.5 165.64 32(41)

Wheeled loaders 10.50 m³ 588 kW 94.25 hour 94.25 80 90.0 7.5 140.69 32(*) Long reach loader; 1.00 m³,

54 kW 25.71 hour 25.71 75 11.0 7.5 31.03 -

Wheel dozer, blade capacity 7.5 m³ 338 kW 52.13 hour 52.13 80 68.0 7.5 87.22 32(9)

Loader Attachments 4 in 1 bucket 2.97 hour 2.97 - - - 2.97 - side dumping bucket 2.62 hour 2.62 - - - 2.62 - rock bucket 2.27 hour 2.27 - - - 2.27 - skeleton bucket 2.35 hour 2.35 - - - 2.35 -

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

single shank ripper (D6) 3.83 hour 3.83 - - - 3.83 - multi shank ripper (D8) 6.98 hour 6.98 - - - 6.98 - rear mounted backacter 9.95 hour 9.95 - - - 9.95 -

Hydraulic face shovels 32 tonne, 1.50 m³ 58.55 hour 58.55 80 34.0 7.5 76.09 10(25) 42 tonne, 2.60 m³ 79.63 hour 79.63 80 44.0 7.5 102.33 10(26) 62 tonne, 1.30 - 3.40 m³ 94.02 hour 94.02 80 64.0 7.5 127.04 10(27)

Skid Steer Loaders Bobcat 463 or similar 7.06 hour 7.06 75 3.5 5.0 8.71 32(48) Bobcat 553 or similar 8.03 hour 8.03 75 4.5 5.0 10.16 32(49) Case 85 XT or similar 9.25 hour 9.25 75 8.3 5.0 13.17 32(49)

Motor Scraper - single engine 15.30 m³ 77.71 hour 77.71 80 44.0 3.0 99.46 32(69) 33.60 m³ 177.03 hour 177.03 80 20.0 3.0 186.92 32(*)

Motor Scraper - twin engine 16.00 m³ 91.70 hour 91.70 80 70.0 3.0 126.31 32(71) 33.60 m³ 202.02 hour 202.02 80 125.5 6.0 265.87 32(73)

Motor scraper - elevating 8.40 m³ 56.02 hour 56.02 80 25.0 3.0 68.38 32(74) 13.00 m³ 66.46 hour 66.46 80 36.0 3.0 84.26 32(75) 16.80 m³ 75.49 hour 75.49 80 46.0 3.0 98.23 32(76)

Tractor (tracked) pipe layer complete with counterweight and boom

up to 145 kW lifting max 28 t (Komatsu/CAT or similar) 44.63 hour 44.63 80 17.0 4.0 53.12 -

Tractor (tracked) pipe layer complete with counterweight and boom

up to 149 kW lifting max 41 t (CAT or similar) 52.46 hour 52.46 80 17.0 4.0 60.95 - up to 224 kW, lifting max 70 t (CAT or similar) 64.09 hour 64.09 80 26.0 4.0 77.07 -

Tractor (tracked) no equipment, for Agro/towing use

75 kW 13.97 hour 13.97 75 10.0 5.0 18.70 - 90 kW 17.79 hour 17.79 75 12.0 5.0 23.46 - 125 kW 23.57 hour 23.57 75 18.0 5.0 32.08 -

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

TRACTORS - continued

Motor Grader (6 wheel) up to 93kW blade 3.66m (Cat or similar) 20.76 hour 20.76 80 17.0 7.5 29.53 32(55) up to 113kW blade 3.66m (Cat or similar) 43.55 hour 43.55 80 23.0 7.5 55.42 32(56) up to 158kW blade 3.96m 33.81 hour 33.81 80 27.0 7.5 47.74 32(57) up to 205kW blade 4.88m (Cat or similar) 44.86 hour 44.86 80 32.0 7.5 61.37 33(*)

Trench excavator (Trencher) up to 100kW max width 0.60m maxdepth 2.40m (Vermeer or similar) 58.62 hour 58.62 75 22.0 3.0 68.82 33(5) up to 300kW max width 1.07m maxdepth 3.66m (Vermeer or similar) 89.49 hour 89.49 75 40.0 3.0 108.03 33(7) towed type from Agro Tractor maxwidth 0.13m max depth 0.55m 9.50 hour 9.50 75 3.0 3.0 10.89 33(*)

TRANSPORT (TIPPERS AND DUMPERS)

Tipping lorries 4 x 2 wheel tippers

gross weight up to 11.0 tonnes payloadup to 5.5 tonnes - side tipping 12.60 hour 12.60 80 30.0 4.0 27.58 14(15/ gross weight up to 11 tonnes 19 payloadup to 8 tonnes 15.38 hour 15.38 80 25.0 4.0 27.86 14(15) gross weight up to 14 tonnes payloadup to 10 tonnes 16.01 hour 16.01 80 30.0 4.0 30.99 14(16) gross weight up to 17 tonnes payloadup to 12 tonnes 17.00 hour 17.00 80 33.0 4.0 33.47 14(16)

6 x 4 wheel tippers gross weight up to 25 tonnes payload up to 18 tonnes 27.36 hour 27.36 80 35.0 4.0 44.83 14(17) gross weight up to 31 tonnes payload up to 20 tonnes 30.40 hour 30.40 80 40.0 4.0 50.37 14(18)

8 x 4 wheel tippers gross weight up to 31 tonnes payload up to 20 tonnes 33.31 hour 33.31 80 40.0 4.0 53.28 14(18) gross weight up to 31 tonnes payload up to 22 tonnes 35.62 hour 35.62 80 42.0 4.0 56.59 14(18) gross weight up to 33 tonnes payload up to 24 tonnes 38.65 hour 38.65 80 44.0 4.0 60.61 14(*)

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

Articulated tipper trailers (Highway type excluding tractor)

twin axle (Bogie) payload up to 20 tonnes (40' length) 21.15 hour 21.15 80 40.0 4.0 41.12 - triple axle (Bogie) payload up to 25 tonnes (50' length) 30.40 hour 30.40 80 44.0 4.0 52.36 -

Dump truck (on site use only) 10.5 m³ heaped capacity, 15.5 tonne payload 15.56 hour 15.56 80 15.0 5.0 23.12 9(12) 14 m³ heaped capacity, 18 tonne payload 22.34 hour 22.34 80 31.0 5.0 37.96 9(14)

Dump truck (on site use only) 19 m³ heaped capacity, 31 tonne payload 40.60 hour 40.60 80 37.5 5.0 59.50 9(17) 24 m³ heaped capacity, 36 tonne payload 61.52 hour 61.52 80 37.9 5.0 80.62 9(18) 57 m³ heaped capacity, 88 tonne payload 80.75 hour 80.75 80 112.0 5.0 137.20 9(*) 78 m³ heaped capacity, 136 tonne payload 94.83 hour 94.83 80 122.0 5.0 156.32 9(*)

Dump truck (articulated type ADT's) Volvo 6 x 6, 18.5 tonne or similar, payload11 m³ heaped capacity 23.19 hour 23.19 80 21.4 3.0 33.77 9(22) Volvo 6 x 6, 22.5 tonne or similar, payload12 m³ heaped capacity 36.70 hour 36.70 80 29.2 3.0 51.14 9(23)

Dump truck (articulated type ADT's) 23 tonne payload, 13 m³ heaped capacity 37.09 hour 37.09 80 26.9 3.0 50.39 9(23) 25 tonne payload, 13.6 m³ heaped capacity 37.09 hour 37.09 80 29.5 3.0 51.67 9(24) 25 tonne payload, 14.2 m³ heaped capacity 37.09 hour 37.09 80 25.0 3.0 49.45 9(24) 32 tonne payload, 19 m³ heaped capacity 51.54 hour 51.54 80 36.5 3.0 69.59 9(25)

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

TRANSPORT (TIPPERS AND DUMPERS) - continued

Small dumpers 750kg payload, heaped capacity 0.55 m³ 5.38 hour 5.38 80 1.5 3.0 6.12 9(3) 1000kg payload, heaped capacity 0.75 m³ 5.38 hour 5.38 80 2.0 3.0 6.37 9(3) 2000kg payload, heaped capacity 1.55 m³ (Thwaites 4000 L, 4 x 4) 5.38 hour 5.38 80 3.0 3.0 6.86 9(5) 2500kg payload, heaped capacity 1.80 m³ (Thwaites 3 Tonne, 4 x 4) 5.38 hour 5.38 80 4.0 3.0 7.36 9(6) 3000kg payload, heaped capacity 2.00 m³ (Thwaites 3.5 Tonne, 4 x 4) 7.06 hour 7.06 80 5.0 3.0 9.53 9(7) 4000kg payload, heaped capacity 2.50 m³ (Thwaites 4.5 Tonne, 4 x 4) 7.06 hour 7.06 80 7.0 3.0 10.52 9(8)

Power barrow 3.83 hour 3.83 80 0.8 2.0 4.22 6(49)

Transport (trucks and vans) Truck, 5t chassis 7.49 hour 7.49 80 7.0 3.0 10.95 Truck, 8t chassis 9.18 hour 9.18 80 8.0 3.0 13.14 Truck, 10t chassis 11.61 hour 11.61 80 10.0 3.0 16.55 Truck, 16t chassis 13.66 hour 13.66 80 15.0 3.0 21.08 Skip Loader, 17t chassis 20.42 hour 20.42 80 15.0 3.0 27.84 Small van (petrol) 6.84 hour 6.84 80 8.0 3.0 10.80 14(20) Pick up (DERV) (1.10 tonnes) 7.51 hour 7.51 80 8.0 3.0 11.47 14(21) Personnel carrier (12 seat transit) 7.61 hour 7.61 80 10.0 3.0 12.55 14(30) SWB utility (DERV) 9.18 hour 9.18 80 7.0 3.0 12.64 14(26) LWB utility (DERV) 11.67 hour 11.67 80 7.0 3.0 15.13 14(27)

Trailers Flat trailer (2 axles) 44.69 4 week 0.28 - - - 0.28 - Drop side trailer (2 axles) 53.62 4 week 0.34 - - - 0.34 - Plant Trailer up to 10 ton 85.10 4 week 0.53 - - - 0.53 - Plant Trailer up to 20 ton 121.57 4 week 0.76 - - - 0.76 -

Cost per working week

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

TRENCH SHEETS ETC. (MINIMUM 50)

Trench struts (each) Nr 0; range 0.30 m - 0.40 m 0.76 week 0.76 - - - 0.76 - Nr 1; range 0.46 m - 0.71 m 0.84 week 0.84 - - - 0.84 26(3) Nr 2; range 0.70 m - 1.10 m 0.88 week 0.88 - - - 0.88 26(4) Nr 3; range 1.04 m - 1.70 m 0.92 week 0.92 - - - 0.92 26(5)

Standard props (each) Nr 0 3ft 6in - 6ft 0in 0.87 week 0.87 - - - 0.87 - Nr 1 5ft 9in - 10ft 3in 0.90 week 0.90 - - - 0.90 - Nr 2 6ft 6in - 11ft 0in 0.93 week 0.93 - - - 0.93 - Nr 3 8ft 6in - 13ft 0in 0.96 week 0.96 - - - 0.96 - Nr 4 10ft 6in - 16ft 0in 1.06 week 1.06 - - - 1.06 - Nr 5 16ft 0in - 21ft 0in 1.17 week 1.17 - - - 1.17 -

Beam heads (each) Nr 1 0.53 week 0.53 - - - 0.53 - Nr 2 0.62 week 0.62 - - - 0.62 - Nr 3 0.80 week 0.80 - - - 0.80 - Nr 4 0.90 week 0.90 - - - 0.90 -

Split heads (each) Nr 1 1ft 9in - 2ft 9in 0.70 week 0.70 - - - 0.70 - Nr 2 3ft 9in - 4ft 6in 0.80 week 0.80 - - - 0.80 - Nr 3 4ft 6in - 6ft 3in 0.99 week 0.99 - - - 0.99 -

Trench Sheets 6'0" 1.26 week 1.26 - - - 1.26 - 8'0" 1.44 week 1.44 - - - 1.44 - 10'0" 1.78 week 1.78 - - - 1.78 - 12'0" 2.23 week 2.23 - - - 2.23 - 14'0" 2.50 week 2.50 - - - 2.50 - 16'0" 2.87 week 2.87 - - - 2.87 -

Trench boxes (approximate cost per m²) - refer to Approximate Estimates

PUMPING AND DEWATERING

Self priming centrifugal diesel pumps (inc. 8 m suction and delivery pipes)

50 mm 550 l/min 62.82 week 1.57 80 0.8 2.0 1.96 20(10) 75 mm Flygt submersible 1050 l/min (4 kW) 60.13 week 1.50 80 - - 1.50 20(24) 75 mm 750 l/min 83.00 week 2.08 80 1.0 2.0 2.57 20(11)

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

PUMPING AND DEWATERING - continued

100 mm 1500 l/min 114.00 week 2.85 80 2.8 2.0 4.22 20(12) 150 mm Sykes UV0 head pump / high capacity 197.92 week 4.95 80 6.8 2.0 8.28 20(13) 76 mm Sykes VCD3 jetting pump 235.48 week 5.89 80 2.0 2.0 6.87 - 100 mm Sykes WP100/60 wellpointing pump 217.15 week 5.43 80 4.5 2.0 7.63 - 150 mm Sykes WP150/60 wellpointing pump 268.19 week 6.70 80 6.8 2.0 10.03 -

Extra hose (per metre) 50 mm Suction 1.62 week 0.04 - - - 0.04 21(2) 50 mm Delivery 1.17 week 0.03 - - - 0.03 21(8) 75 mm Suction 1.78 week 0.04 - - - 0.04 21(3) 75 mm Delivery 1.22 week 0.03 - - - 0.03 21(9) 100 mm Suction 2.21 week 0.06 - - - 0.06 21(4) 100 mm Delivery 1.70 week 0.04 - - - 0.04 21(10) 150 mm Suction 3.38 week 0.08 - - - 0.08 21(5) 150 mm Delivery 3.30 week 0.08 - - - 0.08 21(11) 150 mm Duraline (lay flat fine hose) - week (included with - - - - 150 mm Jetting tube - week Jetting Pump) - - - - 150 mm PVC header pipe and attachments at 1.50m centres including jet wells for wellpointing to 6.5 m deep (per well-point) 4.28 week 0.11 - - - 0.11 -

MISCELLANEOUS

Road form 10m long (each) 50 mm Suction 4.32 week 0.11 - - - 0.11 27(2) 125 mm high 4.60 week 0.12 - - - 0.12 - 150 mm high 4.61 week 0.12 - - - 0.12 27(3) 200 mm high 4.92 week 0.12 - - - 0.12 27(4) 225 mm high 5.21 week 0.13 - - - 0.13 27(7)

Flexible road form 3m long (each) 150 mm high 1.99 week 0.05 - - - 0.05 - 200 mm high 2.08 week 0.05 - - - 0.05 - 225 mm high 2.16 week 0.05 - - - 0.05 -

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

Road signs on stands (each) 600mm diameter 8.58 week 0.21 - - - 0.21 37(43) 750mm diameter 8.58 week 0.21 - - - 0.21 37(44) 900mm diameter 10.73 week 0.27 - - - 0.27 37(45) 1200mm diameter 12.52 week 0.31 - - - 0.31 37(46)

Road safety flashing hazard lamps (Batteries inc.) 1.97 week 0.05 - - - 0.05 37(22) traffic lamps static 1.51 week 0.04 - - - 0.04 37(10) standard cone 1.51 week 0.04 - - - 0.04 37(39) road pins 0.75 week 0.02 - - - 0.02 - PVC-U barrier 5.27 week 0.13 - - - 0.13 37(6) cone converter 1.87 week 0.05 - - - 0.05 - railway sleepers - baulks - each 2.83 week 0.07 - - - 0.07 - traffic light systems two way radar, 110V 143.89 week 3.60 - - - 3.60 - two way, mains, timer operated 123.35 week 3.08 - - - 3.08 37(9)

Transformers/cables 2kVA 18.51 week 0.46 - - - 0.46 11(16) 4kVA 22.61 week 0.57 - - - 0.57 11(17) 6kVA 35.99 week 0.90 - - - 0.90 11(18)

Extension cable 240V/110V 15 m plug and socket 6.29 week 0.16 - - - 0.16 - 30 m plug and socket 7.87 week 0.20 - - - 0.20 - 15 m 4 mm 10.86 week 0.27 - - - 0.27 -

Transformers/cables 240V junction box 11.35 week 0.28 - - - 0.28 - 110V junction box 11.35 week 0.28 - - - 0.28 -

Welding & cutting sets ARC Mains 150 amps portable 28.78 week 0.72 - - - 0.72 35(5) ARC Petrol 200 amps mobile 95.36 week 2.38 80 1.8 - 4.18 - ARC Diesel 300 amps trailer mounted 123.35 week 3.08 80 2.3 - 4.18 35(3) Oxy acetylene set portable (cutting) 56.30 week 1.41 75 650/325 - 4.14 35(1) Oxy acetylene set portable (welding) 63.63 week 1.59 75 500/325 - 4.32 35(1) MIG welder 120 amp 34.74 week 0.87 - - - 0.87 -

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

MISCELLANEOUS - continued

Lighting 0.70 floodlight 6' stand 1000 watt 35.73 week 0.89 - - - 0.89 -

17' floodlight tower (cw 2kVA generator) 68.74 week 1.72 - - - 1.72 -

40' floodlight tower (cw 6kVA generator) 150.16 week 3.75 - - - 3.75 -

Festoon lighting set (34m) 24.40 week 0.61 - - - 0.61 -

Tripod floodlight 1.8m stand 500 watt 24.03 week 0.60 - - - 0.60 -

Drain tools drain rods (10m set) including equipment 12.66 week 0.32 - - - 0.32 37(24) drain plug (rubber diaphragm) 100 4.51 week 0.11 - - - 0.11 37(26) drain plug (rubber diaphragm) 150 5.63 week 0.14 - - - 0.14 37(27) drain plug (rubber diaphragm) 300 6.00 week 0.15 - - - 0.15 37(28) mains powered drain cleaner 67.57 week 1.69 - - - 1.69 - drain tester - smoke 9.01 week 0.23 - - - 0.23 - drain tester - U gauge 10.13 week 0.25 - - - 0.25 - drain tester - pressure pump 30.03 week 0.75 - - - 0.75 - drain tester - mandrel 5.63 week 0.14 - - - 0.14 - stilson wrench 24" 7.81 week 0.20 - - - 0.20 - stilson wrench 36" 12.01 week 0.30 - - - 0.30 - clay pipe cutter to 9" 22.52 week 0.56 - - - 0.56 - steel pipe cutter to 6" 17.07 week 0.43 - - - 0.43 - drain bag 4" or 6" 7.51 week 0.19 - - - 0.19 -

Tar boilers lorry mounted 400 litres 16.46 hour 16.46 - - - 16.46 29(1) power operated 1200 litres 268.20 week 6.71 - - - 6.71 29(2)

Shot blasting equipment 150 lb 129.79 week 3.24 - - - 3.24 - 350 lb 179.42 week 4.49 - - - 4.49 -

Grit blaster ICE160, 72kg 144.72 week 3.62 - - - 3.62 -

Stone splitter 25" x 4" 56.87 week 1.42 - - - 1.42 -

Block splitter 30.03 week 0.75 - - - 0.75 -

Slab splitter 37.54 week 0.94 - - - 0.94 -

Slab lifter 7.89 week 0.20 - - - 0.20 -

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

Cartridge guns Hilti DX76 32.17 week 0.80 - - - 0.80 - Hilti DX460 28.61 week 0.72 - - - 0.72 -

Heating/Drying Propane radiant heater (12,500 BTU) 17.41 week 0.44 80 0.3 - 0.70 37(11) forced air heater (60,000 BTU) 55.33 week 1.38 80 1.2 - 2.62 37(12) forced air heater (150,000 BTU) 76.61 week 1.92 80 3.0 - 5.01 37(14) forced air heater (325,000 BTU) 110.61 week 2.77 80 6.5 - 9.47 37(16) dehumidifier (40 litres/day) 68.11 week 1.70 - - - 1.70 37(34) fume extractor (6" diameter) 74.48 week 1.86 - - - 1.86 -

Drills/Saws/Tools diamond drill, 6" max. diameter 93.66 week 2.34 - - - 2.34 - masonry drill & core bits, 10mm 30.04 week 0.75 - - - 0.75 - masonry drill & core bits, 32mm 57.56 week 1.44 - - - 1.44 31(1) angle head drill 17.87 week 0.45 - - - 0.45 31(4) Roto broach, milling to 34mm 64.65 week 1.62 - - - 1.62 - rotary hammer drill, light weight 30.04 week 0.75 - - - 0.75 31(15) rotary hammer drill, heavy weight 26.46 week 0.66 - - - 0.66 31(16) demolition hammer, heavy duty 28.61 week 0.72 - - - 0.72 - grinder, 225mm, electric 21.45 week 0.54 - - - 0.54 - grinder, 114mm, electric 15.74 week 0.39 - - - 0.39 31(11) saw bench, 410mm diameter, petrol 50.06 week 1.25 75 1.0 2.0 2.21 24(10) saw bench, 610mm diameter, diesel 53.62 week 1.34 75 1.0 2.0 1.80 24(13) chain saw, up to 410mm 42.90 week 1.07 75 0.4 2.0 1.25 24(2) 225mm electric grinder (angle) 27.16 week 0.68 - - - 0.68 31(10) 450mm conc saw 25hp diesel 125.13 week 3.13 75 0.3 2.0 3.27 6(41) 600mm conc saw 40hp diesel 148.55 week 3.71 75 0.3 2.0 3.85 6(42) Stihl saw disc 305mm petrol 39.33 week 0.98 75 0.2 2.0 1.17 37(18) Drills/Saws/Tools Stihl saw disc 12" air 34.91 week 0.87 - - - 0.87 37(18) 8" floor sander (electric) 47.00 week 1.18 - - - 1.18 31(13) Water/Fuel Supply towed (trailer) water/diesel bowser, 275 gallon 55.24 week 1.38 - - - 1.38 34(8) bowser, 500 gallon 82.53 week 2.06 - - - 2.06 34(9) lorry-mounted tanker, 1000 gallon (DERV) 8.5t chassis 14.89 hour 14.89 75 9.0 2.0 23.84 34(10)

PLANT COSTS - continued

Cost per working hour

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

MISCELLANEOUS - continued

lorry-mounted tanker,1500 gallon (DERV) 12t chassis 16.80 hour 16.80 75 13.0 2.0 29.73 34(11) storage tanks, up to 250 gallon 43.08 4 week 0.27 - - - 0.27 34(1) storage tanks, up to 500 gallon 54.31 4 week 0.34 - - - 0.34 34(2) up to 1000 gallon 67.42 4 week 0.42 - - - 0.42 34(3) up to 2000 gallon 74.90 4 week 0.47 - - - 0.47 34(4)

Landscaping Items and Tools post hole auger 6"/9" hand 10.90 week 0.27 - - - 0.27 - powered auger petrol 71.51 week 1.79 75 2.0 2.0 3.70 - post driver for 4" post 8.94 week 0.22 - - - 0.22 - post driver for 6" posts 9.84 week 0.25 - - - 0.25 - linemarker 2", 3" or 4" wide 20.02 week 0.50 - - - 0.50 bolt croppers 24" or 36" 12.51 week 0.31 - - - 0.31 tipping and loading skip 6 tonne 42.90 week 1.07 - - - 1.07 8(28) cultivator self propelled 157.30 week 3.93 75 1.0 2.0 4.39 -

Boilers and Sprays bitumen boiler 10 gallon (45 litres) 28.61 week 0.72 75 1.0 2.0 1.68 29(*) bitumen boiler 15 gallon (68 litres) 50.92 week 1.27 75 1.0 2.0 2.23 29(*) cold tar spray 50.92 week 1.27 - - - 1.27 29(5)

Flame gun propane (road burner) 15.74 week 0.39 75 N/a N/a 0.39 2(*)

Air tool bits-landscaping (see also compressor tools)

shove holer 10.28 week 0.26 - - - 0.26 - points and chisels 1.70 week 0.04 - - - 0.04 - clayspade 2.32 week 0.06 - - - 0.06 30(3) tarmac cutter 4.01 week 0.10 - - - 0.10 - comb holder 1.79 week 0.04 - - - 0.04 - self-drill anchor holder 2.32 week 0.06 - - - 0.06 - rammer foot 3.41 week 0.09 - - - 0.09 -

Floor sander (belt) 30.40 week 0.76 - - - 0.76 31(13)

Pinking roller 17.87 week 0.45 - - - 0.45 -

Floor grinder/scarifier, electric 67.93 week 1.70 - - - 1.70 -

Floor saw, 450mm petrol 89.38 week 2.23 75 1.0 2.0 3.19 6(38)

Floor plane, petrol 80.44 week 2.01 75 1.0 2.0 2.97 -

Floor scaler, petrol 98.32 week 2.46 75 1.0 2.0 3.42 -

Rubbish chute (sections) 5.71 week 0.14 - - - 0.14 -

Diesel elevators up to 15 m 74.90 week 1.87 75 3.0 2.0 3.25 - up to 30 m 103.01 week 2.58 75 5.0 2.0 4.88 -

Cost per working week

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

FORMWORK EQUIPMENT

Adjustable props Nr 0 1.07 - 1.82 3.47 week 3.47 - - - 3.47 Nr 1 1.75 - 3.12 3.47 week 3.47 - - - 3.47 Nr 2 1.98 - 3.35 4.04 week 4.04 - - - 4.04 Nr 3 2.59 - 3.95 4.04 week 4.04 - - - 4.04 Nr 4 3.20 - 4.88 4.04 week 4.04 - - - 4.04

MISCELLANEOUS

Decking per SM (Kwikform) (excluding props) 9.24 week 9.24 - - - 9.24

Column clamps (set) Nr 1 0.3 - 0.53 1.86 week 1.86 - - - 1.86 27(17) Nr 2 0.46 - 0.84 2.29 week 2.29 - - - 2.29 27(18) Nr 3 0.66 - 1.222 3.15 week 3.15 - - - 3.15 27(19)

Beam Clamps 300mm arms 1.55 week 1.55 - - - 1.55 27(20) 450mm arms 1.70 week 1.70 - - - 1.70 27(21) 600mm arms 1.93 week 1.93 - - - 1.93 27(22)

Manhole shutters - 1800mm high 675 mm internal diameter 38.35 week 38.35 - - - 38.35 900 mm internal diameter 46.03 week 46.03 - - - 46.03 1050 mm internal diameter 49.60 week 49.60 - - - 49.60 1200 mm internal diameter 53.69 week 53.69 - - - 53.69 1500 mm internal diameter 61.37 week 61.37 - - - 61.37 1800 mm internal diameter 64.94 week 64.94 - - - 64.94 2100 mm internal diameter 76.70 week 76.70 - - - 76.70 2400 mm internal diameter 84.37 week 84.37 - - - 84.37 2700 mm internal diameter 87.96 week 87.96 - - - 87.96

Portable Accommodation

(including electrical fittings but excluding additional security items, shutters, grilles etc. per unit delivered and set up on site) Offices

Jack Leg hutment 12'2" x 8'8" 45.00 week 45.00 - - - 45.00 16(1) Jack Leg hutment 16'2" x 8'8" 45.00 week 45.00 - - - 45.00 16(1) Jack Leg hutment 24'2" x 10'2" 70.00 week 70.00 - - - 70.00 16(1) Jack Leg hutment 32'2" x 10'2" 125.00 week 125.00 - - - 125.00 16(1)

PLANT COSTS - continued

Cost per working week

Hire Hire DSR Rate Period Plant Usage Fuel Oil etc. Total

£ £ % l/hr % fuel £

MISCELLANEOUS - continued

Portable Accommodation - continued

Jack Leg hutment 48'2" x 12'2" 250.00 week 250.00 - - - 250.00 16(1) Wheeled cabin 12'1" x 7'6" 42.50 week 42.50 - - - 42.50 16(6) Wheeled cabin 22'1" x 7'6" 55.00 week 55.00 - - - 55.00 16(7)

Stores Jack Leg hutment 12'2" x 8'8" 42.00 week 42.00 - - - 42.00 16(1) Jack Leg hutment 16'2" x 8'8" 42.00 week 42.00 - - - 42.00 16(1) Jack Leg hutment 24'2" x 10'2" 60.00 week 60.00 - - - 60.00 16(1) Jack Leg hutment 32'2" x 10'2" 80.00 week 80.00 - - - 80.00 16(1)

Sundries Toilet, chemical 35.00 week 35.00 - - - 35.00 16(5) Toilet unit, water flushing 40.00 week 40.00 - - - 40.00 16(5) Toilet unit, VIP, water flushing 65.00 week 65.00 - - - 65.00 16(5) Pollution Decontamination unit 22'1" X 7'6" 250.00 week 250.00 - - - 250.00 16(5) Canteen Unit 32'4" x 8'8" 150.00 week 150.00 - - - 150.00 16(2)