ABSTRACT

EXCAVATION BY DREDGING –cont’d For use in lakes, canals, rivers, industrial lagoons and from silted locations in dock systems Floating craft using diesel driven suction method with a 200 mm diameter flexible pipe maximum distance from point of suction to point of discharge 1500 m. Maximum dredge depth 5 m. Average pumping output 30 m3 per hour and approximate average costs (excluding mobilisation and demobilisation costs ranging between £3,000and £6,000 apiece) - - - - m3 6.04 EXCAVATION FOR CUTTINGS The following unit costs are based on backacter and tractor loader machines Excavate topsoil maximum depth ne 0.25 m 0.03 0.95 1.03 - m3 1.98 Excavate material other than topsoil, rock or artificial hard material ne 0.25 m maximum depth 0.03 0.95 1.03 - m3 1.98 0.25 - 0.5 m maximum depth 0.03 0.95 1.03 - m3 1.98 0.5 - 1.0 m maximum depth 0.04 1.26 1.34 - m3 2.60 1.0 - 2.0 m maximum depth 0.06 1.89 2.03 - m3 3.92 2.0 - 5.0 m maximum depth 0.10 3.16 3.37 - m3 6.53 5.0 - 10.0 m maximum depth 0.20 6.31 6.78 - m3 13.09 10.0 - 15.0 m maximum depth 0.29 9.15 9.81 - m3 18.96 The following unit costs are based on backacter machines fitted with hydraulic breakers and tractor loader machines Excavate rock (medium hard) ne 0.25 m maximum depth 0.31 9.78 10.49 - m3 20.27 0.25 - 0.5 m maximum depth 0.43 13.57 14.55 - m3 28.12 0.5 - 1.0 m maximum depth 0.58 18.30 19.61 - m3 37.92 1.0 - 2.0 m maximum depth 0.80 25.25 27.11 - m3 52.36 Excavate unreinforced concrete exposed at the commencing surface ne 0.25 m maximum depth 0.57 17.99 19.30 - m3 37.29 0.25 - 0.5 m maximum depth 0.60 18.94 20.30 - m3 39.24 0.5 -1.0 m maximum depth 0.67 21.14 22.67 - m3 43.82 1.0 - 2.0 m maximum depth 0.70 22.09 23.67 - m3 45.76 Excavate reinforced concrete exposed at the commencing surface ne 0.25 m maximum depth 0.90 28.40 30.45 - m3 58.86 0.25 - 0.5 m maximum depth 0.90 28.40 30.45 - m3 58.86 0.5 - 1.0 m maximum depth 0.95 29.98 32.14 - m3 62.12 1.0 - 2.0 m maximum depth 1.08 34.08 36.54 - m3 70.63 Excavate unreinforced concrete not exposed at the commencing surface ne 0.25 m maximum depth 0.65 20.51 21.99 - m3 42.50 0.25 - 0.5 m maximum depth 0.67 21.14 22.67 - m3 43.82 0.5 -1.0 m maximum depth 0.69 21.78 23.36 - m3 45.14 1.0 - 2.0 m maximum depth 0.72 22.72 24.36 - m3 47.08

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

EXCAVATION FOR FOUNDATIONS The following unit costs are based on the use of backacter machines Excavate topsoil maximum depth ne 0.25 m 0.03 0.92 1.03 - m3 1.95 Excavate material other than topsoil, rock or artificial hard material 0.25 - 0.5 m deep 0.05 1.53 1.72 - m3 3.25 0.5 - 1.0 m deep 0.06 1.84 2.03 - m3 3.87 1.0 - 2.0 m deep 0.07 2.14 2.34 - m3 4.48 2.0 - 5.0 m deep 0.12 3.67 4.06 - m3 7.73 5.0 - 10.0 m deep 0.23 7.03 7.81 - m3 14.84 The following unit costs are based on backacter machines fitted with hydraulic breakers Excavate unreinforced concrete exposed at the commencing surface ne 0.25 m maximum depth 0.60 18.35 20.30 - m3 38.65 0.25 - 0.5 m maximum depth 0.66 20.18 22.33 - m3 42.51 0.5 - 1.0 m maximum depth 0.72 22.01 24.36 - m3 46.38 1.0 - 2.0 m maximum depth 0.80 24.46 27.11 - m3 51.57 Excavate reinforced concrete exposed at the commencing surface ne 0.25 m maximum depth 0.94 28.74 31.76 - m3 60.51 0.25 - 0.5 m maximum depth 0.98 29.96 33.20 - m3 63.17 0.5 - 1.0 m maximum depth 1.00 30.58 33.82 - m3 64.40 1.0 - 2.0 m maximum depth 1.04 31.80 35.23 - m3 67.03 Excavate tarmacadam exposed at the commencing surface ne 0.25 m maximum depth 0.30 9.17 10.15 - m3 19.32 0.25 - 0.5 m maximum depth 0.34 10.40 11.46 - m3 21.86 0.5 - 1.0 m maximum depth 0.37 11.31 12.49 - m3 23.81 1.0 - 2.0 m maximum depth 0.40 12.23 13.49 - m3 25.72 Excavate unreinforced concrete not exposed at the commencing surface ne 0.25 m maximum depth 0.70 21.40 23.64 - m3 45.05 0.25 - 0.5 m maximum depth 0.85 25.99 28.74 - m3 54.72 0.5 -1.0 m maximum depth 0.96 29.35 32.48 - m3 61.84 1.0 - 2.0 m maximum depth 1.02 31.19 34.51 - m3 65.70

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

GENERAL EXCAVATION The following unit costs are based on backacter and tractor loader machines Excavate topsoil maximum depth ne 0.25 m 0.03 1.01 1.03 - m3 2.04 Excavate material other than topsoil, rock or artificial hard material ne 0.25 m maximum depth 0.03 1.01 1.01 - m3 2.01 0.25 - 0.5 m maximum depth 0.03 1.01 1.03 - m3 2.04 0.5 - 1.0 m maximum depth 0.04 1.34 1.34 - m3 2.68 1.0 - 2.0 m maximum depth 0.06 2.01 2.03 - m3 4.04 2.0 - 5.0 m maximum depth 0.10 3.36 3.37 - m3 6.73 5.0 - 10.0 m maximum depth 0.20 6.71 6.78 - m3 13.49 10.0 - 15.0 m maximum depth 0.29 9.73 9.81 - m3 19.54 The following unit costs are based on backacter machines fitted with hydraulic breakers and tractor loader machines Excavate rock (medium hard) ne 0.25 m maximum depth 0.31 10.40 10.49 - m3 20.89 0.25 - 0.5 m maximum depth 0.43 14.43 14.55 - m3 28.98 0.5 - 1.0 m maximum depth 0.58 19.46 19.61 - m3 39.07 1.0 - 2.0 m maximum depth 0.80 26.85 27.11 - m3 53.96 Excavate unreinforced concrete exposed at the commencing surface ne 0.25 m maximum depth 0.57 19.13 19.30 - m3 38.43 0.25 - 0.5 m maximum depth 0.60 20.13 20.30 - m3 40.44 0.5 -1.0 m maximum depth 0.67 22.48 22.67 - m3 45.16 1.0 - 2.0 m maximum depth 0.70 23.49 23.67 - m3 47.16 Excavate reinforced concrete exposed at the commencing surface ne 0.25 m maximum depth 0.90 30.20 30.45 - m3 60.65 0.25 - 0.5 m maximum depth 0.90 30.20 30.45 - m3 60.65 0.5 - 1.0 m maximum depth 0.95 31.88 32.14 - m3 64.02 1.0 - 2.0 m maximum depth 1.08 36.24 36.54 - m3 72.79 Excavate unreinforced concrete not exposed at the commencing surface ne 0.25 m maximum depth 0.65 21.81 21.99 - m3 43.80 0.25 - 0.5 m maximum depth 0.67 22.48 22.67 - m3 45.16 0.5 -1.0 m maximum depth 0.69 23.15 23.36 - m3 46.52 1.0 - 2.0 m maximum depth 0.72 24.16 24.36 - m3 48.52 EXCAVATION ANCILLARIES The following unit costs are for various machines appropriate to the work Trimming topsoil; using D4H dozer horizontal 0.04 0.59 0.54 - m2 1.13 10 - 45 degrees to horizontal 0.05 0.74 0.67 - m2 1.41 Trimming material other than topsoil, rock or artificial hard material; using D4H dozer, tractor loader or motor grader average rate horizontal 0.04 0.59 0.79 - m2 1.38 10 - 45 degrees to horizontal 0.04 0.59 0.79 - m2 1.38 45 - 90 degrees to horizontal 0.06 0.89 1.18 - m2 2.07

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Trimming rock; using D6E dozer horizontal 0.08 1.18 17.88 - m2 19.06 10 - 45 degrees to horizontal 0.80 11.80 17.88 - m2 29.69 45 - 90 degrees to horizontal 1.06 15.64 23.69 - m2 39.33 vertical 1.06 15.64 23.69 - m2 39.33 Preparation of topsoil; using D4H dozer, tractor loader or motor grader average rate horizontal 0.06 0.89 0.95 - m2 1.84 10 - 45 degrees to horizontal 0.06 0.89 0.95 - m2 1.84 Preparation of material other than rock or artificial hard material; using D6E dozer, tractor loader or motor grader average rate horizontal 0.06 0.89 1.36 - m2 2.24 10 - 45 degrees to horizontal 0.06 0.89 1.36 - m2 2.24 45 - 90 degrees to horizontal 0.06 0.89 1.36 - m2 2.24 Preparation of rock; using D6E dozer horizontal 0.80 11.80 17.88 - m2 29.69 10 - 45 degrees to horizontal 0.60 8.85 13.41 - m2 22.26 45 - 90 degrees to horizontal 0.60 8.85 13.41 - m2 22.26 The following unit costs for disposal are based on using a 22.5 tonne ADT for site work and 20 tonne tipper for off-site work. The distances used in the calculation are quoted to assist estimating, although this goes beyond the specific requirements of CESMM3 Disposal of excavated topsoil storage on site; 100 m maximum distance 0.05 0.90 2.53 - m3 3.43 removal; 5 km distance 0.11 1.99 5.75 - m3 7.74 removal; 15 km distance 0.21 3.79 10.99 - m3 14.78 Disposal of excavated earth other than rock or artificial hard material storage on site; 100 m maximum distance; using 22.5 tonne ADT 0.05 0.90 2.53 - m3 3.43 removal; 5 km distance; using 20 tonne tipper 0.12 2.17 6.28 - m3 8.44 removal; 15 km distance; using 20 tonne tipper 0.22 3.97 11.51 - m3 15.48 Disposal of excavated rock or artificial hard material storage on site; 100 m maximum distance; using 22.5 tonne ADT 0.06 1.08 3.03 - m3 4.12 removal; 5 km distance; using 20 tonne tipper 0.13 2.35 6.80 - m3 9.15 removal; 15 km distance; using 20 tonne tipper 0.23 4.15 12.03 - m3 16.18 Add to the above rates where tipping charges apply: non-hazardous waste - - - - m3 29.62 hazardous waste - - - - m3 74.25 special waste - - - - m3 90.75 contaminated liquid - - - - m3 94.88 contaminated sludge - - - - m3 123.75 Add to the above rates where Landfill Tax applies: exempted material - - - - m3 - inactive or inert material - - - - m3 3.75 other material - - - - m3 48.00

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

EXCAVATION ANCILLARIES – cont’d The following unit costs for double handling are based on using a 1.5 m3 tractor loader and 22.5 tonne ADT. A range of distances is listed to assist in estimating, although this goes beyond the specific requirements of CESMM3. Double handling of excavated topsoil; using 1.5 m3 tractor loader and 22.5 tonne ADT 300 m average distance moved 0.08 1.44 3.49 - m3 4.93 600 m average distance moved 0.10 1.80 4.36 - m3 6.17 1000 m average distance moved 0.12 2.17 5.23 - m3 7.40 Double handling of excavated earth other than rock or artificial hard material; using 1.5 m3 tractor loader and 22.5 tonne ADT 300 m average distance moved 0.08 1.44 3.49 - m3 4.93 600 m average distance moved 0.10 1.80 4.36 - m3 6.17 1000 m average distance moved 0.12 2.17 5.23 - m3 7.40 Double handling of rock or artificial hard material; using 1.5 m3 tractor loader and 22.5 tonne ADT 300 m average distance moved 0.16 2.89 6.98 - m3 9.87 600 m average distance moved 0.18 3.25 7.85 - m3 11.10 1000 m average distance moved 0.20 3.61 8.72 - m3 12.33 The following unit rates for excavation below Final Surface are based on using a 16 tonne backacter machine Excavation of material below the Final Surface and replacement of with: granular fill 1.20 17.18 19.00 19.58 m3 55.75 concrete Grade C7.5P 0.60 8.59 9.50 83.67 m3 101.75 Timber supports left in 0.32 6.03 - 7.59 m2 13.62 Metal supports left in 0.89 16.40 - 34.34 m2 50.75 FILLING Excavated topsoil; DfT specified type 5A Filling to structures 0.07 2.82 3.65 - m3 6.48 embankments 0.03 0.99 1.28 - m3 2.26 general 0.02 0.83 1.07 - m3 1.90 150 mm thick 0.01 0.28 0.36 - m2 0.63 250 mm thick 0.01 0.47 0.61 - m2 1.09 400 mm thick 0.02 0.67 0.87 - m2 1.54 600 mm thick 0.02 0.95 1.23 - m2 2.17 Imported topsoil DfT specified type 5B; Filling embankments 0.03 0.99 1.28 21.82 m3 24.09 general 0.02 0.83 1.07 21.82 m3 23.72 150 mm thick 0.01 0.28 0.36 3.27 m2 3.91 250 mm thick 0.01 0.47 0.61 5.46 m2 6.54 400 mm thick 0.02 0.67 0.87 8.73 m2 10.27 600 mm thick 0.02 0.95 1.23 13.09 m2 15.27

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Non-selected excavated material other than topsoil or rock Filling to structures 0.04 1.42 1.84 - m3 3.26 embankments 0.02 0.59 0.77 - m3 1.36 general 0.01 0.43 0.56 - m3 1.00 150 mm thick - 0.16 0.20 - m2 0.36 250 mm thick 0.01 0.24 0.31 - m2 0.54 400 mm thick 0.01 0.36 0.46 - m2 0.82 600 mm thick 0.01 0.47 0.61 - m2 1.09 Selected excavated material other than topsoil or rock Filling to structures 0.04 1.62 2.09 - m3 3.71 embankments 0.01 0.55 0.72 - m3 1.27 general 0.01 0.47 0.61 - m3 1.09 150 mm thick - 0.16 0.20 - m2 0.36 250 mm thick 0.01 0.28 0.36 - m2 0.63 400 mm thick 0.01 0.39 0.51 - m2 0.91 600 mm thick 0.01 0.51 0.66 - m2 1.18 Imported natural material other than topsoil or rock; subsoil Filling to structures 0.04 1.42 1.84 20.32 m3 23.58 embankments 0.02 0.59 0.77 20.32 m3 21.68 general 0.02 0.59 0.77 20.32 m3 21.68 150 mm thick 0.01 0.36 0.46 3.05 m2 3.86 250 mm thick 0.01 0.51 0.66 5.08 m2 6.26 400 mm thick 0.02 0.59 0.77 8.13 m2 9.49 600 mm thick 0.02 0.67 0.87 12.19 m2 13.73 Imported natural material other than topsoil or rock; granular graded material Filling to structures 0.04 1.42 1.84 22.21 m3 25.47 embankments 0.02 0.67 0.87 22.21 m3 23.75 general 0.02 0.67 0.87 22.21 m3 23.75 150 mm thick 0.01 0.47 0.61 3.33 m2 4.42 250 mm thick 0.02 0.67 0.87 5.55 m2 7.09 400 mm thick 0.02 0.79 1.02 8.88 m2 10.70 600 mm thick 0.02 0.87 1.12 13.33 m2 15.32 Imported natural material other than topsoil or rock; granular selected material Filling to structures 0.04 1.42 1.84 20.68 m3 23.94 embankments 0.02 0.67 0.87 20.68 m3 22.22 general 0.02 0.67 0.87 20.68 m3 22.22 150 mm thick 0.01 0.47 0.61 3.10 m2 4.19 250 mm thick 0.02 0.67 0.87 5.17 m2 6.71 400 mm thick 0.02 0.79 1.02 8.27 m2 10.08 600 mm thick 0.02 0.87 1.12 12.41 m2 14.40

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

FILLING – cont’d Excavated rock Filling to structures 0.04 1.58 2.04 - m3 3.62 embankments 0.05 1.97 2.55 - m3 4.53 general 0.05 1.97 2.55 - m3 4.53 150 mm thick 0.02 0.67 0.87 - m2 1.54 250 mm thick 0.03 1.03 1.33 - m2 2.35 400 mm thick 0.04 1.58 2.04 - m2 3.62 600 mm thick 0.06 2.17 2.81 - m2 4.98 Imported rock Filling to structures 0.04 1.58 2.04 44.88 m3 48.50 embankments 0.02 0.95 1.23 44.88 m3 47.05 general 0.02 0.79 1.02 44.88 m3 46.69 150 mm thick 0.01 0.47 0.61 6.73 m2 7.82 250 mm thick 0.02 0.79 1.02 11.22 m2 13.03 400 mm thick 0.03 1.18 1.53 17.95 m2 20.67 600 mm thick 0.03 1.18 1.53 26.93 m2 29.65 FILLING ANCILLARIES Trimming of filled surfaces Topsoil horizontal 0.02 0.38 0.83 - m2 1.21 inclined at an angle of 10 - 45 degrees to horizontal 0.02 0.38 0.83 - m2 1.21 inclined at an angle of 45 - 90 degrees to horizontal 0.03 0.49 1.07 - m2 1.56 Material other than topsoil, rock or artificial hard material horizontal 0.02 0.38 0.83 - m2 1.21 inclined at an angle of 10 - 45 degrees to horizontal 0.02 0.38 0.83 - m2 1.21 inclined at an angle of 45 - 90 degrees to horizontal 0.03 0.49 1.07 - m2 1.56 Rock horizontal 0.51 9.22 20.18 - m2 29.41 inclined at an angle of 10 - 45 degrees to horizontal 0.52 9.40 20.58 - m2 29.98 inclined at an angle of 45 - 90 degrees to horizontal 0.70 12.66 27.70 - m2 40.36 Preparation of filled surfaces Topsoil horizontal 0.03 0.54 1.19 - m2 1.73 inclined at an angle of 10 - 45 degrees to horizontal 0.03 0.54 1.19 - m2 1.73 inclined at an angle of 45 - 90 degrees to horizontal 0.04 0.67 1.46 - m2 2.13

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Material other than topsoil, rock or artificial hard material horizontal 0.03 0.54 1.19 - m2 1.73 inclined at an angle of 10 - 45 degrees to horizontal 0.03 0.54 1.19 - m2 1.73 inclined at an angle of 45 - 90 degrees to horizontal 0.04 0.67 1.46 - m2 2.13 Rock horizontal 0.33 5.96 13.06 - m2 19.02 inclined at an angle of 10 - 45 degrees to horizontal 0.33 5.96 13.06 - m2 19.02 inclined at an angle of 45 - 90 degrees to horizontal 0.52 9.39 20.58 - m2 29.97 GEOTEXTILES NOTES The geotextile products mentioned below are not specifically confined to the individual uses stated but are examples of one of many scenarios to which they may be applied. Conversely, the scenarios are not limited to the geotextile used as an example. Geotextiles; stabilisation applications for reinforcement of granular sub-bases, capping layers and railway ballast placed over weak and variable soils For use over weak soils with moderate traffic intensities e.g. car parks, light access roads; Tensar SS20 Polypropylene Geogrid horizontal 0.04 1.17 - 1.78 m² 2.94 inclined at an angle of 10 to 45 degrees to the horizontal 0.05 1.47 - 1.78 m² 3.25 For use over weak soils with high traffic intensities and/or high axle loadings; Tensar SS30 Polypropylene Geogrid horizontal 0.05 1.81 - 2.59 m² 4.40 inclined at an angle of 10 to 45 degrees to the horizontal 0.06 2.25 - 2.59 m² 4.84 For use over very weak soils e.g. alluvium, marsh or peat or firmer soil subject to exceptionally high axle loadings; Tensar SS40 Polypropylene Geogrid horizontal 0.05 1.98 1.65 4.00 m² 7.63 inclined at an angle of 10 to 45 degrees to the horizontal 0.06 2.46 2.05 4.00 m² 8.52 For trafficked areas where fill comprises aggregate exceeding 100mm; Tensar SSLA20 Polypropylene Geogrid horizontal 0.04 1.17 - 2.20 m² 3.37 inclined at an angle 10 - 45 degrees to the horizontal 0.05 1.47 - 2.20 m² 3.67

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

GEOTEXTILES – cont’d Geotextiles; stabilisation applications for reinforcement of granular sub-bases, capping layers and railway ballast placed over weak and variable soils – cont’d Stabilisation and separation of granular fill from soft sub grade to prevent intermixing: Terram 1000 horizontal 0.05 2.05 - 0.49 m² 2.54 inclined at an angle of 10 to 45 degrees to the horizontal 0.06 2.57 - 0.49 m² 3.07 Stabilisation and separation of granular fill from soft sub grade to prevent intermixing: Terram 2000 horizontal 0.04 1.85 1.54 1.41 m² 4.80 inclined at an angle of 10 to 45 degrees to the horizontal 0.05 2.33 1.94 1.41 m² 5.69 Geotextiles; reinforcement applications for asphalt pavements For roads, hardstandings and airfield pavements; Tensar AR-G composite comprising Tensar AR-1 grid bonded to a geotextile, laid within asphalt horizontal 0.05 1.81 - 3.44 m² 5.25 inclined at an angle of 10 to 45 degrees to the horizontal 0.06 2.25 - 3.44 m² 5.69 Geotextiles; slope reinforcement and embankment support; for use where soils can only withstand limited shear stresses, therefore steep slopes require external support Paragrid 30/155; 330g/m² horizontal 0.04 1.17 - 2.13 m² 3.30 inclined at an angle of 10-45 degrees to the horizontal 0.05 1.47 - 2.13 m² 3.60 Paragrid 100/255; 330g/m² horizontal 0.04 1.17 - 2.90 m² 4.07 inclined at an angle of 10-45 degrees to the horizontal 0.05 1.47 - 2.90 m² 4.37 Paralink 200s; 1120g/m2 horizontal 0.05 2.38 1.98 5.70 m² 10.06 inclined at an angle of 10-45 degrees to the horizontal 0.07 2.99 2.49 5.70 m² 11.19 Paralink 600s; 2040g/m2 horizontal 0.06 2.77 2.31 12.04 m² 17.12 inclined at an angle of 10-45 degrees to the horizontal 0.08 3.48 2.90 12.04 m² 18.41 Terram grid 30/30 horizontal 0.06 2.51 2.09 0.01 m² 4.61 inclined at an angle of 10-45 degrees to the horizontal 0.07 3.12 2.60 0.01 m² 5.74

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Geotextiles; scour and erosion protection For use where erosion protection is required to the surface of a slope once its geotechnical stability has been achieved, and to allow grass establishment; Tensar 'Mat' Polyethelene mesh; fixed with Tensar pegs horizontal 0.04 1.65 - 3.76 m² 5.41 inclined at an angle of 10-45 degrees to the horizontal 0.05 2.05 - 3.76 m² 5.82 For use where hydraulic action exists, such as coastline protection from pressures exerted by waves, currents and tides; Typar SF56 horizontal 0.05 2.24 1.87 0.56 m² 4.68 inclined at an angle of 10-45 degrees to the horizontal 0.06 2.82 2.35 0.56 m² 5.72 For protection against puncturing to reservoir liner; Typar SF563 horizontal 0.05 2.24 1.87 0.56 m² 4.68 inclined at an angle of 10-45 degrees to the horizontal 0.06 2.82 2.35 0.56 m² 5.72 Geotextiles; temporary parking areas For reinforcement of grassed areas subject to wear from excessive pedestrian and light motor vehicle traffic; Netlon CE131 high density polyethelyene geogrid horizontal 0.04 1.22 - 3.77 m² 4.99 Geotextiles; landscaping applications For prevention of weed growth in planted areas by incorporating a geotextile over top soil and below mulch or gravel; Typar SF20 horizontal 0.08 3.02 - 0.33 m² 3.35 inclined at an angle of 10-45 degrees to the horizontal 0.09 3.78 - 0.33 m² 4.12 For root growth control-Prevention of lateral spread of roots and mixing of road base and humus; Typar SF20 horizontal 0.08 3.02 - 0.33 m² 3.35 inclined at an angle of 10-45 degrees to the horizontal 0.09 3.78 - 0.33 m² 4.12 Geotextiles; drainage applications For clean installation of pipe support material and to prevent siliting of the drainage pipe and minimising differential settlement; Typar SF10 horizontal 0.04 1.65 - 0.37 m² 2.02 inclined at an angle of 10-45 degrees to the horizontal 0.05 2.05 - 0.37 m² 2.42 For wrapping to prevent clogging of drainage pipes surrounded by fine soil; Typar SF10 sheeting 0.08 3.22 - 0.72 m² 3.94 For wrapping to prevent clogging of drainage pipes surrounded by fine soil; Terram 1000 sheeting 0.08 3.22 - 0.53 m² 3.75

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

GEOTEXTILES – cont’d Geotextiles; drainage applications – cont’d For vertical structure drainage to sub-surface walls, roofs and foundations; Filtram 1B1 sheeting 0.08 3.22 - 8.20 m² 11.42 For waterproofing to tunnels, buried structures, etc. where the membrane is buried, forming part of the drainage system; Filtram 1BZ sheeting 0.08 3.22 - 7.87 m² 11.09 Geotextiles; roofing insulation and protection Protection of waterproofing membrane from physical damage and puncturing; Typar SF56 sheeting 0.05 2.24 1.87 0.56 m² 4.68 Internal reinforcement of in situ spread waterproof bitumen emulsion; Typar SF10 sheeting 0.07 2.65 - 0.37 m² 3.02 LANDSCAPING Preparatory operations prior to landscaping Supply and apply granular cultivation treatments by hand 35 grammes/m2 0.50 12.89 - 5.18 100 m2 18.07 50 grammes/ m2 0.65 16.76 - 7.40 100 m2 24.16 75 grammes/ m2 0.85 21.91 - 11.10 100 m2 33.02 100 grammes/ m2 1.00 25.78 - 14.80 100 m2 40.58 Supply and apply granular cultivation treatments by machine in suitable economically large areas 100 grammes/m2 0.25 3.64 1.03 14.80 100 m2 19.48 Supply and incorporate cultivation additives into top 150 mm of topsoil by hand 1 m3 / 10 m2 20.00 515.58 - 12.34 100 m2 527.92 1 m3 / 13 m2 20.00 515.58 - 9.49 100 m2 525.07 1 m3 / 20 m2 19.00 489.80 - 6.17 100 m2 495.97 1 m3 / 40 m2 17.00 438.25 - 3.08 100 m2 441.33 Supply and incorporate cultivation additives into top 150 mm of topsoil by machine in suitable economically large areas 1 m3 / 10 m2 - - 153.52 12.34 100 m2 165.86 1 m3 / 13 m2 - - 141.71 9.49 100 m2 151.19 1 m3 / 20 m2 - - 125.97 6.17 100 m2 132.14 1 m3 / 40 m2 - - 116.12 3.08 100 m2 119.21 Turfing Turfing horizontal 0.12 3.09 - 3.08 m2 6.17 10 - 45 degress to horizontal 0.17 4.38 - 3.08 m2 7.46 45 - 90 degrees to horizontal; pegging down 0.19 4.90 - 3.08 m2 7.97

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Hydraulic mulch grass seeding Grass seeding horizontal 0.01 0.13 - 0.24 m2 0.37 10 - 45 degrees to horizontal 0.01 0.18 - 0.24 m2 0.42 45 - 90 degrees to horizontal 0.01 0.23 - 0.24 m2 0.47 Selected grass seeding Grass seeding; sowing at the rate of 0.050 kg/m2 in two operations horizontal 0.01 0.26 - 0.22 m2 0.48 10 - 45 degrees to horizontal 0.02 0.39 - 0.22 m2 0.61 45 - 90 degrees to horizontal 0.02 0.52 - 0.22 m2 0.74 Plants Form planting hole in previously cultivated area, supply and plant specified herbaceous plants and backfill with excavated material 5 plants/ m2 0.01 0.26 - 3.77 m2 4.03 10 plants/ m2 0.02 0.57 - 13.81 m2 14.38 25 plants/ m2 0.05 1.29 - 32.16 m2 33.45 35 plants/ m2 0.07 1.80 - 45.02 m2 46.82 50 plants/ m2 0.10 2.58 - 64.32 m2 66.89 Supply and fix plant support netting on 50 mm diameter stakes 750 mm long driven into the ground at 1.5 m centres 1.15 m high green extruded plastic mesh, 125 mm square mesh 0.06 1.55 - 1.82 m2 3.37 Form planting hole in previously cultivated area; supply and plant bulbs and backfill with excavated material small 0.01 0.26 - 0.17 each 0.43 medium 0.01 0.26 - 0.27 each 0.53 large 0.01 0.26 - 0.32 each 0.58 Supply and plant bulbs in grassed area using bulb planter and backfill with screened topsoil or peat and cut turf plug small 0.01 0.26 - 0.17 each 0.43 medium 0.01 0.26 - 0.27 each 0.53 large 0.01 0.26 - 0.32 each 0.58 Shrubs Form planting hole in previously cultivated area, supply and plant specified shrub and backfill with excavated material shrub 300 mm high 0.01 0.26 - 2.60 each 2.86 shrub 600 mm high 0.01 0.26 - 3.74 each 4.00 shrub 900 mm high 0.01 0.26 - 4.47 each 4.73 shrub 1 m high and over 0.01 0.26 - 5.97 each 6.23 Supply and fix shrub stake including two ties one stake; 1.5 m long, 75 mm diameter 0.12 3.09 - 5.52 each 8.62

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

LANDSCAPING – cont’d Trees The cost of planting semi-mature trees will depend on the size and species, and on the access to the site for tree handling machines. Prices should be obtained for individual trees and planting. Break up subsoil to a depth of 200 mm in tree pit 0.05 1.29 - - each 1.29 Supply and plant tree in prepared pit; backfill with excavated topsoil minimum 600 mm deep light standard tree 0.25 6.44 - 10.71 each 17.15 standard tree 0.45 11.60 - 16.07 each 27.67 selected standard tree 0.75 19.33 - 21.42 each 40.75 heavy standard tree 0.85 21.91 - 37.48 each 59.40 extra heavy standard tree 1.50 38.67 - 66.94 each 105.61 Extra for filling with topsoil from spoil heap ne 100 m distant 0.15 3.87 - - m3 3.87 Extra for filling with imported topsoil 0.08 2.06 - 19.30 m3 21.37 Supply tree stake and drive 500 mm into firm ground and trim to approved height, including two tree ties to approved pattern one stake; 2.4 m long, 100 mm diameter 0.16 4.12 - 6.89 each 11.02 one stake; 3.0 m long, 100 mm diameter 0.20 5.16 - 8.69 each 13.84 two stakes; 2.4 m long, 100 mm diameter 0.24 6.19 - 13.79 each 19.98 two stakes; 3.0 m long, 100 mm diameter 0.30 7.73 - 17.38 each 25.11 Supply and fit tree support comprising three collars and wire guys; including pickets galvanised steel 50 x 600 mm 1.50 38.67 - 28.89 each 67.56 hardwood 75 x 600 mm 1.50 38.67 - 29.55 each 68.22 Supply and fix standard steel tree guard 0.30 7.73 - 24.14 each 31.87 Hedges Excavate trench by hand for hedge and deposit soil alongside trench 300 wide x 300 mm deep 0.10 2.58 - - m 2.58 450 wide x 300 mm deep 0.13 3.35 - - m 3.35 Excavate trench by machine for hedge and deposit soil alongside trench 300 wide x 300 mm deep 0.02 0.52 - - m 0.52 450 wide x 300 mm deep 0.02 0.52 - - m 0.52 Set out, nick out and excavate trench and break up subsoil to minimum depth of 300 mm 400 mm minimum deep 0.28 7.19 - - m 7.19 Supply and plant hedging plants, backfill with excavated topsoil single row; plants at 200 mm centres 0.25 6.44 - 3.28 m 9.73 single row; plants at 300 mm centres 0.17 4.38 - 2.19 m 6.57 single row; plants at 400 mm centres 0.13 3.22 - 1.64 m 4.86 single row; plants at 500 mm centres 0.10 2.58 - 1.31 m 3.89 single row; plants at 600 mm centres 0.08 2.06 - 1.09 m 3.15 double row; plants at 200 mm centres 0.50 12.89 - 6.56 m 19.45 double row; plants at 300 mm centres 0.34 8.76 - 4.37 m 13.14 double row; plants at 400 mm centres 0.25 6.44 - 3.28 m 9.73 double row; plants at 500 mm centres 0.20 5.16 - 2.63 m 7.78 Extra for incorporating manure at the rate of 1m3 per 30 m of trench 0.12 3.09 - 0.11 m 3.21

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

COMPARATIVE COSTS - EARTH MOVING Notes The cost of earth moving and other associated works is dependent on matching the overall quantities and production rate called for by the programme of works with the most appropriate plant and assessing the most suitable version of that plant which will: * deal with the site conditions (e.g. type of ground, type of excavation, length of haul, prevailing weather, etc.) * comply with the specification requirements (e.g. compaction, separation of materials, surface tolerances, etc.) * complete the work economically (e.g. provide surface tolerances which will avoid undue expense of imported materials) Labour costs are based on a plant operative skill rate 3 unless otherwise stated Comparative costs of excavation equipment The following are comparative costs using various types of excavation equipment and include loading into transport. All costs assume 50 minutes productive work in every hour and adequate disposal transport being available to obviate any delay. Dragline (for excavations requiring a long reach and long discharge, mainly in clearing streams and rivers) bucket capacity ne 1.15 m3 0.06 1.08 2.41 - m3 3.49 bucket capacity ne 2.00 m3 0.03 0.54 2.78 - m3 3.32 bucket capacity ne 3.00 m3 0.02 0.36 2.68 - m3 3.04 Hydraulic backacter (for all types of excavation and loading, including trenches, breaking hard ground, etc.) bucket capacity ne 0.40 m3 0.05 0.81 1.22 - m3 2.03 bucket capacity ne 1.00 m3 0.02 0.36 0.85 - m3 1.21 bucket capacity ne 1.60 m3 0.01 0.18 1.06 - m3 1.24 Hydraulic face shovel (predominantly for excavating cuttings and embankments over 2 m high requiring high output) bucket capacity ne 1.50 m3 0.04 0.72 2.99 - m3 3.71 bucket capacity ne 2.60 m3 0.02 0.36 2.01 - m3 2.37 bucket capacity ne 3.40 m3 0.01 0.18 1.24 - m3 1.42 Tractor loader (for loading, carrying, placing materials, spreading and levelling, some site clearance operations and reducing levels) bucket capacity ne 0.80 m3 0.02 0.36 0.46 - m3 0.82 bucket capacity ne 1.50 m3 0.01 0.18 0.37 - m3 0.55 bucket capacity ne 3.00 m3 0.01 0.13 0.54 - m3 0.66 Multipurpose wheeled loader / backhoe (versatile machine for small to medium excavations, trenches, loading, carrying and back filling) bucket capacity ne 0.76 m3 0.08 1.44 1.50 - m3 2.94 bucket capacity ne 1.00 m3 0.06 1.08 1.15 - m3 2.23

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

COMPARATIVE COSTS - EARTH MOVING - cont’d Comparative costs of transportation equipment The following are comparative costs for using various types of transportation equipment to transport excavated loose material. The capacity of the transport must be suitable for the output of the loading machine. The cost will vary depending on the number of transport units required to meet the output of the loading unit and the distance to be travelled. Loading loose material into transport by wheeled loader ne 2.1 m3 capacity 0.02 0.36 0.84 - m3 1.20 ne 5.4 m3 capacity 0.01 0.18 1.63 - m3 1.82 ne 10.5 m3 capacity 0.01 0.13 0.96 - m3 1.09 Transport material within site by dump truck (rear dump) ne 24 m3 heaped capacity, distance travelled ne 0.5 Km 0.03 0.54 2.39 - m3 2.93 Add per 0.5 Km additional distance 0.01 0.18 0.80 - m3 0.98 ne 57 m3 heaped capacity, distance travelled ne 0.5 Km 0.03 0.59 2.68 - m3 3.27 Add per 0.5 Km additional distance 0.03 0.59 1.34 - m3 1.93 Transport material within site by dump truck (articulated) ne 32 t payload, distance travelled ne 0.5 Km 0.04 0.78 2.76 - m3 3.54 Add per 0.5 Km additional distance 0.02 0.39 1.38 - m3 1.77 Transport material within or off site by tipping lorry ne 10 t payload, distance travelled ne 1 Km 0.05 0.81 1.51 - m3 2.32 Add per 1 Km additional distance 0.03 0.40 0.76 - m3 1.16 10 - 15 t payload, distance travelled ne 1 Km 0.04 0.65 1.31 - m3 1.95 Add per 1 Km additional distance 0.02 0.32 0.65 - m3 0.98 15 - 25 t payload, distance travelled ne 1 Km 0.03 0.54 1.32 - m3 1.86 Add per 1 Km additional distance 0.02 0.27 0.66 - m3 0.93 Comparative costs of earth moving equipment The following are comparative costs using various types of earth moving equipment to include excavation, transport, spreading and levelling. Bulldozer up to 74 KW (CAT D4H sized machine used for site strip, reducing levels or grading and spreading materials over smaller sites) average push one way 10 m 0.03 0.49 0.80 - m3 1.29 average push one way 30 m 0.08 1.30 2.15 - m3 3.44 average push one way 50 m 0.14 2.27 3.76 - m3 6.02 average push one way 100 m 0.29 4.70 7.78 - m3 12.48 Bulldozer up to 104 KW (CAT D6E sized machine for reducing levels, excavating to greater depths at steeper inclines, grading surfaces, small cut and fill operations; maximum push 100 m) average push one way 10 m 0.03 0.54 1.34 - m3 1.88 average push one way 30 m 0.07 1.26 3.13 - m3 4.39 average push one way 50 m 0.09 1.62 4.02 - m3 5.65 average push one way 100 m 0.19 3.43 8.49 - m3 11.92

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Bull or Angle Dozer up to 212 KW (CAT D8N sized machine for high output, ripping and excavating by reducing levels at steeper inclines or in harder material than with D6E, larger cut and fill operations used in conjunction with towed or S.P. scrapers. Spreading and grading over large areas; maximum push 100 m) average push one way 10 m 0.03 0.54 3.01 - m3 3.55 average push one way 30 m 0.06 1.08 6.02 - m3 7.11 average push one way 50 m 0.07 1.26 7.03 - m3 8.29 average push one way 100 m 0.11 1.99 11.04 - m3 13.03 Motorised scraper, 15 m3 capacity (for excavating larger volumes over large haul lengths, excavating to reduce levels and also levelling ground, grading large sites, moving and tipping material including hard material - used in open cast sites) average haul one way 500 m - 0.07 0.39 - m3 0.47 average haul one way 1,000 m 0.01 0.11 0.59 - m3 0.70 average haul one way 2,000 m 0.01 0.14 0.79 - m3 0.93 average haul one way 3,000 m 0.01 0.18 0.99 - m3 1.17 Twin engined motorised scraper, 16 m3 capacity average haul one way 500 m - 0.05 0.37 - m3 0.43 average haul one way 1,000 m - 0.07 0.50 - m3 0.57 average haul one way 2,000 m 0.01 0.09 0.62 - m3 0.72 average haul one way 3,000 m 0.01 0.13 0.87 - m3 1.00 Twin engined motorised scraper, 34 m3 capacity average haul one way 500 m - 0.04 0.52 - m3 0.56 average haul one way 1,000 m - 0.05 0.78 - m3 0.84 average haul one way 2,000 m - 0.05 0.78 - m3 0.84 average haul one way 3,000 m - 0.07 1.05 - m3 1.12 Excavation by hand Desirable for work around live services or in areas of highly restricted access. Excavate and load into skip or dumper bucket loose material 2.02 25.13 - - m3 25.13 compacted soil or clay 3.15 39.19 - - m3 39.19 mass concrete or sandstone 3.00 37.32 - - m3 37.32 broken rock 2.95 36.70 - - m3 36.70 existing sub-base or pipe surrounds 3.12 38.81 - - m3 38.81 Excavate by hand using pneumatic equipment Excavate below ground using 1.80 m3/min single tool compressor and pneumatic breaker and load material into skip or dumper bucket rock (medium drill) 2.12 26.37 14.21 - m3 40.58 brickwork or mass concrete 2.76 34.33 15.15 - m3 49.48 reinforced concrete 3.87 48.14 24.31 - m3 72.45 asphalt in carriageways 1.15 14.31 6.88 - m3 21.18

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

COMPARATIVE COSTS - EARTH MOVING - cont’d Comparative prices for ancillary equipment Excavate using 6 tonne to break out (JCB 3CX and Montalbert 125 breaker) medium hard rock 0.43 6.96 10.42 - m3 17.38 brickwork or mass concrete 0.54 8.74 13.08 - m3 21.82 reinforced concrete 0.64 10.36 15.50 - m3 25.86 Load material into skip or dumper Load material into skip or dumper bucket using a 11.5 tonne crawler backacter with 0.80 m3 rock bucket medium hard rock 0.07 1.13 1.92 - m3 3.05 brickwork or mass concrete 0.08 1.30 2.19 - m3 3.48 reinforced concrete 0.09 1.46 2.47 - m3 3.92 DRILLING AND BLASTING IN ROCK The cost of blasting is controlled by the number of holes and the length of drilling required to achieve the tolerances and degree of shatter required, e.g. line drilling to trenches, depth of drilling to control horizontal overbreak. Drilling with rotary percussion drills 105 - 110 mm diameter; hard rock - - - - m 13.90 105 - 110 mm diameter; sandstone - - - - m 7.03 125 mm diameter; hard rock - - - - m 11.04 125 mm diameter; sandstone - - - - m 9.92 165 mm diameter; hard rock - - - - m 12.65 165 mm diameter; sandstone - - - - m 12.65 Drilling and blasting in open cut for bulk excavation excluding cost of excavation or trimming hard rock - - - - m 3.20 sandstone - - - - m 4.32 Drilling and blasting for quarry operations with face height exceeding 10 m hard rock - - - - m 3.06 sandstone - - - - m 3.06 Drilling and blasting in trenches excluding cost of excavation or trimming trench width ne 1.0 m - - - - m 24.01 trench width 1.0 - 1.5 m - - - - m 20.82 trench width over 1.5 m - - - - m 17.63 Secondary blasting to boulders pop shooting - - - - m 7.52 plaster shooting - - - - m 4.01

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

DEWATERING The following unit costs are for dewatering pervious ground only and are for sets of equipment comprising: 1 nr diesel driven pump (WP 150/60 or similar) complete with allowance of £50 for fuel - - - - day 101.10 50 m of 150 mm diameter header pipe - - - - day 19.48 35 nr of disposable well points - - - - buy 298.86 18 m of delivery pipe - - - - day 7.68 1 nr diesel driven standby pump - - - - day 35.62 1 nr jetting pump with hoses (for installation of wellpoints only) - - - - - 62.33 attendant labour and plant (2 hrs per day) inclusive of small dumper and bowser - - - - - 99.71 Costs are based on 10 hr shifts with attendant labour and plant (specialist advice) Guide price for single set of equipment comprising pump, 150 mm diameter header pipe, 35 nr well points, delivery pipes and attendant labour and plant Bring to site equipment and remove upon completion - - - - sum 2310.00 Installation costs hire of jetting pump with hoses; 1 day - - - - sum 62.33 purchase of well points; 35 Nr - - - - sum 298.86 labour and plant; 10 hours - - - - sum 997.09 Operating costs hire of pump, header pipe, delivery pipe and standby pump complete with fuel etc. and 2 hours attendant labour and plant - - - - day 363.30