ABSTRACT

Progress Activity Frac. Frac. Gauging Main structure 0.10 0.015 Eyeballing Roofing 0.15 0.022 ft. 2 Siding 0.15 0.023 ft.2 Doors & windows 0.10 0.015 Unit Lighting 0.20 0.030 Milestones HVAC 0.20 0.030 See note Finish 0.10 0.015 Eyeballing

TOTAL 1.00 0.150

Note: HVAC work could be broken down by power supply, equipment installation, or ducts installation.