Note: A bid package for a lump sum contract must also include complete P&ID's, equipment and piping arrangement drawings and a complete set of project specifications

Potential bidders must be screened thoroughly to determine their technical competence as well as their organizational capability and/or willingness to .meet project specific requirements, size fit, construction approach, etc. Contractors should not be placed on the bidders slate unless they are considered fully capable of performing quality work within the criteria established in the project execution plan. The criteria are the responsibility of the Project Manager, who must consider, as a minimum, the following factors:

• Relevant Process Experience

- Organic/inorganic/solids. - Developmental/first of a kind. - Specialized process design programs.