ABSTRACT
RESOURCESLABOUR
Fencing/barrier gang 1 ganger/chargehand (skill rate 4)—50% of time
5.33
1 skilled operative (skill rate 4)—50% of time
5.08
1 unskilled operative (general)
9.52
1 plant operator (skill rate 4)
11.08
Total Gang Rate/Hour £ 31.01
1 skilled operative (skill rate 4)
10.16
1 unskilled operative (general)
9.52
Total Gang Rate/Hour £ 19.68 RESOURCESPLANT
Fencing/Barriers agricultural type tractor; fencing auger
11.74
gas oil for ditto 1.29 drop sided trailer, two axles
0.27
power tools etc. (fencing)
2.50
Total Gang Rate/Hour £ 15.79 RESOURCESMATERIALS
All rates for materials are based on the most economically available materials with a minimum waste allowance of 2.5% and supplier’s discount of 15%.