ABSTRACT
RESOURCESLABOUR
Concreting gang 1 ganger/chargehand (skill rate 4)
10.66
2 skilled operatives (skill rate 4)
20.32
4 unskilled operatives (general)
38.08
1 plant operator (skill rate 3)— 25% of time
3.10
Total Gang Rate/Hour
£ 72.16
Formwork gang 1 foreman (craftsman)
15.46
2 joiners 29.42
operative (general)
1 plant operator (craftsman)—25% of time
3.96
Total Gang Rate/Hour
£ 58.36
Reinforcement gang
1 foreman (craftsman)
15.46
4 steel fixers (craftsman)
58.84
1 unskilled operative (general)
9.52
1 plant operator (craftsman)—25% of time
3.96
Total Gang Rate/Hour
£ 87.78
RESOURCESPLANT
Concreting 22RB crane-25% of time
5.03
gas oil for ditto 0.09 0.76 m3 concrete skip-25% of time
0.20
11.3 m3/min compressor, 4 tool
8.19
gas oil for ditto 2.42 4 poker vibrators P5475 mm or less in thickness
4.50
Total Gang Rate/Hour
£ 20.43
Formwork 20 t crawler crane-25% of time
4.85
gas oil for ditto 0.11 22″ saw bench 1.05 gas oil for ditto 0.14 small power tools (formwork)
1.11
Total Gang Rate/Hour
£ 7.26
crane-25% of time
gas oil for ditto 0.11 bar cropper 1.69 small power tools (reinforcement)
0.61
tirfors, kentledge etc.