ABSTRACT

Up to 5 m - 1.50 27.00 7.00 - m3 34.00 10 m - 1.50 27.00 7.70 - m3 34.70 12.5 m - 1.50 27.00 8.02 - m3 35.02 15 m - 1.50 27.00 8.41 - m3 35.41 20 m - 1.50 27.00 9.11 - m3 36.11 25 m - 1.50 27.00 9.74 - m3 36.74 30 m - 1.50 27.00 10.44 - m3 37.44

Conveyor belt width 600 mm; Mechanically loaded and removed at offload point; Conveyor length;

Up to 5 m - 1.00 18.00 5.03 - m3 23.04 10 m - 1.00 18.00 5.61 - m3 23.61 12.5 m - 1.00 18.00 5.92 - m3 23.92 15 m - 1.00 18.00 6.23 - m3 24.23 20 m - 1.00 18.00 6.86 - m3 24.86 25 m - 1.00 18.00 7.46 - m3 25.46 30 m - 1.00 18.00 8.05 - m3 26.06

Conveyor belt width 400 mm; Mechanically loaded and removed by hand at offload point; Conveyor length;

Up to 5 m - 3.19 57.43 5.25 - m3 62.68 10 m - 3.19 57.43 6.19 - m3 63.62 12.5 m - 3.19 57.43 6.60 - m3 64.03 15 m - 3.19 57.43 7.13 - m3 64.55 20 m - 3.19 57.43 8.06 - m3 65.49 25 m - 3.19 57.43 8.90 - m3 66.32 30 m - 3.19 57.43 9.83 - m3 67.26

NEW ITEMS FOR THIS EDITION

Item PC Labour Labour Plant Material Unit Total Excluding site overheads and profit £ hours £ £ £ rate £

MOVEMENT OF MATERIALS – cont’d Terranova Cranes Ltd. Crane Hire; Materials handling and lifting; Telescopic Cranes supply and management. Exclusive of roadway management or planning applications. Prices below illustrate lifts of 1 tonne at maximum crane reach; Lift cycle of 0.25 hours; Mechanical filling of material skip if appropriate 35 tonne mobile crane; Lifting capacity of 1 tonne at 25 meters; C.P.A hire (all management by hirer)

granular materials including concrete - 0.75 13.50 15.03 - tonne 28.53 palletised or packed materials - 0.50 9.00 12.03 - tonne 21.03

35 tonne mobile crane; Lifting capacity of 1 tonne at 25 meters; contract lift

granular materials or concrete - 0.25 4.50 40.31 - tonne 44.81 palletised or packed materials - - - 37.31 - tonne 37.31

50 tonne mobile crane; Lifting capacity of 1 tonne at 30 meters; C.P.A hire (all management by hirer)

granular materials including concrete - 0.75 13.50 20.19 - tonne 33.69 palletised or packed materials - 0.50 9.00 17.19 - tonne 26.19

50 tonne mobile crane; Lifting capacity of 1 tonne at 30 meters; contract lift

granular materials or concrete - 0.25 4.50 46.50 - tonne 51.00 palletised or packed materials - - - 43.50 - tonne 43.50

80 tonne mobile crane; Lifting capacity of 1 tonne at 38 meters; C.P.A hire (all management by hirer)

granular materials including concrete - 0.75 13.50 28.75 - tonne 42.25 palletised or packed materials - 0.50 9.00 25.75 - tonne 34.75

80 tonne mobile crane; Lifting capacity of 1 tonne at 38 meters; contract lift

granular materials or concrete - 0.25 4.50 56.75 - tonne 61.25 palletised or packed materials - - - 53.75 - tonne 53.75

Q25 SLAB/BRICK/SETT/COBBLE PAVINGS

Marshalls; La Linia Pavings; Fine textured exposed aggregate 80 mm thick pavings in various sizes to designed laying patterns; laid to 50 mm sharp sand bed on Type 1 base all priced separately Bonded laying patterns 300 x 300

Light Granite / Anthracite basalt 23.82 2.00 36.00 - 24.42 m2 60.42 Indian granite / Yellow - 2.00 36.00 - 26.55 m2 62.55

Random Scatter pattern incorporating 100 x 200, 200 x 200 and 300 x 200 units

Light Granite / Anthracite basalt 23.82 3.00 54.05 - 23.82 m2 77.87 Indian granite / Yellow - 3.00 54.05 - 25.90 m2 79.95

NEW ITEMS FOR THIS EDITION

Item PC Labour Labour Plant Material Unit Total Excluding site overheads and profit £ hours £ £ £ rate £

Marshalls; "La Linia Grande Paving"; as above but 140 mm thick Bonded laying patterns 300 x 300

All colours 46.54 3.00 54.05 - 46.54 m2 100.59 Random Scatter pattern incorporating 100 x 200, 200 x 200 and 300 x 200 units

Light Granite / Anthracite basalt 46.54 4.00 72.00 - 46.54 m2 118.54 Extra over to the above for incorporating inlay stones to patterns; blue, light granite or anthracite basalt

to prescribed patterns 100.89 1.50 27.00 - 100.89 m2 127.89 as individual units; triangular 200 x 200 x 282 mm

0.57 0.05 0.90 - 0.57 nr 1.47

Q31 TREE PLANTING

Greenleaf Tree Planting - Irrigation Systems; "Root Rain" tree pit irrigation systems "Metro" - "Small"; 35 mm pipe diameter 1.25 m long for specimen shrubs and standard trees

Plastic 5.09 0.25 4.50 - 5.09 nr 9.59 Plastic with chain 6.65 0.25 4.50 - 6.65 nr 11.15 Metal with chain 8.24 0.25 4.50 - 8.24 nr 12.74

"Medium" 35 mm pipe diameter 1.75 m long for s standard and selected standard trees

Plastic 5.40 0.29 5.14 - 5.40 nr 10.54 Plastic with chain 6.98 0.29 5.14 - 6.98 nr 12.12 Metal with chain 8.55 0.29 5.14 - 8.55 nr 13.69

"Large" 35 mm pipe diameter 2.50 m long for selected standards and extra heavy standards

Plastic 6.24 0.33 6.00 - 6.24 nr 12.24 Plastic with chain 7.82 0.33 6.00 - 7.82 nr 13.82 Metal with chain 10.44 0.33 6.00 - 10.44 nr 16.44

"Large" 35 mm pipe diameter 2.50 m long for selected standards and extra heavy standards

Plastic 6.24 0.33 6.00 - 6.24 nr 12.24 Plastic with chain 7.82 0.33 6.00 - 7.82 nr 13.82 Metal with chain 10.44 0.33 6.00 - 10.44 nr 16.44

"Urban" Irrigation and aeration systems; for large capacity general purpose irrigation to parkland and street verge planting

RRUrb1; 3.0 m pipe - 0.29 5.14 - 12.60 nr 17.74 RRUrb2; 5.0 m pipe 14.60 0.33 6.00 - 14.60 nr 20.60 RRUrb3; 8.0 m pipe 15.90 0.40 7.20 - 15.90 nr 23.10

"Precinct" Irrigation and aeration systems; heavy cast aluminium inlet for heavily trafficked locations

"5 m pipe" 27.50 0.33 6.00 - 27.50 nr 33.50 "8 m pipe" 30.00 0.40 7.20 - 30.00 nr 37.20

NEW ITEMS FOR THIS EDITION

Item PC Labour Labour Plant Material Unit Total Excluding site overheads and profit £ hours £ £ £ rate £

SMALL GARDENS

Notes; In calculating the costs and outputs of work in small garden, the following factors are taken into consideration.