ABSTRACT

Excavate and form ditch and bank with 45° sides in light to medium soils; all widths taken at bottom of ditch 300mm wide×600mm deep 100m 105.00 600mm wide×900mm deep 100m 120.00 1.20m wide×900mm deep 100m 920.00 1.50m wide×1.20m deep 100m 1550.00

Clear and bottom existing ditch average 1.50m deep, trim back vegetation and remove debris to licensed tip not exceeding 13 km, lay jointed concrete pipes; including bedding, haunching and topping with 150mm concrete; 11.50N/mm2 – 40mm aggregate; backfill with approved spoil from site Pipes 300mm diameter 100m 6300.00 Pipes 450mm diameter 100m 8000.00 Pipes 600mm diameter 100m 10500.00

SUBSOIL DRAINAGE – BY MACHINE

Main drain; remove 150mm topsoil and deposit alongside trench, excavate drain trench by machine and lay flexible perforated drain; lay bed of gravel rejects 100mm; backfill with gravel rejects or similar to within 150mm of finished ground level; complete fill with topsoil; remove surplus spoil to approved dump on site Main drain 160mm supplied in 35m lengths

450mm deep 100m 690.00 600mm deep 100m 810.00 900mm deep 100m 1375.00

Extra for couplings each 2.00 As above but with 100mm main drain supplied in 100m lengths

450mm deep 100m 1050.00 600mm deep 100m 1375.00 900mm deep 100m 2275.00

Extra for couplings each 1.65

Laterals to mains above; herringbone pattern; excavation and backfilling as above; inclusive of connecting lateral to main drain 160mm pipe to 450mm deep trench

laterals at 1.0m centres 100m² 690.00 laterals at 2.0m centres 100m² 345.00 laterals at 3.0m centres 100m² 230.00 laterals at 5.0m centres 100m² 140.00 laterals at 10.0m centres 100m² 69.00

160mm pipe to 600mm deep trench laterals at 1.0m centres 100m² 810.00 laterals at 2.0m centres 100m² 405.00 laterals at 3.0m centres 100m² 270.00 laterals at 5.0m centres 100m² 160.00 laterals at 10.0m centres 100m² 81.00

£ Excluding site overheads and profit

160mm pipe to 900mm deep trench laterals at 1.0m centres 100m² 1375.00 laterals at 2.0m centres 100m² 700.00 laterals at 3.0m centres 100m² 460.00 laterals at 5.0m centres 100m² 280.00 laterals at 10.0m centres 100m² 140.00

Extra for 160/160mm couplings connecting laterals to main drain laterals at 1.0m centres 10m 79.00 laterals at 2.0m centres 10m 39.00 laterals at 3.0m centres 10m 26.00 laterals at 5.0m centres 10m 15.70 laterals at 10.0m centres 10m 7.85

100mm pipe to 450mm deep trench laterals at 1.0m centres 100m² 1050.00 laterals at 2.0m centres 100m² 530.00 laterals at 3.0m centres 100m² 350.00 laterals at 5.0m centres 100m² 210.00 laterals at 10.0m centres 100m² 105.00

100mm pipe to 600mm deep trench laterals at 1.0m centres 100m² 1375.00 laterals at 2.0m centres 100m² 700.00 laterals at 3.0m centres 100m² 460.00 laterals at 5.0m centres 100m² 280.00 laterals at 10.0m centres 100m² 140.00

100mm pipe to 900mm deep trench laterals at 1.0m centres 100m² 2275.00 laterals at 2.0m centres 100m² 1125.00 laterals at 3.0m centres 100m² 750.00 laterals at 5.0m centres 100m² 450.00 laterals at 10.0m centres 100m² 225.00

80mm pipe to 450mm deep trench laterals at 1.0m centres 100m² 1025.00 laterals at 2.0m centres 100m² 510.00 laterals at 3.0m centres 100m² 335.00 laterals at 5.0m centres 100m² 205.00 laterals at 10.0m centres 100m² 100.00

80mm pipe to 600mm deep trench laterals at 1.0m centres 100m² 1350.00 laterals at 2.0m centres 100m² 680.00 laterals at 3.0m centres 100m² 450.00 laterals at 5.0m centres 100m² 270.00 laterals at 10.0m centres 100m² 135.00

80mm pipe to 900mm deep trench laterals at 1.0m centres 100m² 2225.00 laterals at 2.0m centres 100m² 1125.00 laterals at 3.0m centres 100m² 740.00 laterals at 5.0m centres 100m² 445.00 laterals at 10.0m centres 100m² 220.00

£ Excluding site overheads and profit

SUBSOIL DRAINAGE – BY MACHINE – CONT

Laterals to mains above – cont Extra for 100/80mm junctions connecting laterals to main drain

laterals at 1.0m centres 10m 37.00 laterals at 2.0m centres 10m 18.60 laterals at 3.0m centres 10m 12.40 laterals at 5.0m centres 10m 7.45 laterals at 10.0m centres 10m 3.70

Clay land drain Excavate trench by excavator to 450mm deep; lay 100mm vitrified clay drain with butt joints, bedding Class B; backfill with excavated material screened to remove stones over 40mm; backfill to be laid in layers not exceeding 150mm; top with 150mm topsoil remove surplus material to approved dump on site not exceeding 100m; final level of fill to allow for settlement 100m 1550.00

SUBSOIL DRAINAGE – BY HAND

Main drain; remove 150mm topsoil and deposit alongside trench; excavate drain trench by machine and lay flexible perforated drain; lay bed of gravel rejects 100mm; backfill with gravel rejects or similar to within 150mm of finished ground level; complete fill with topsoil; remove surplus spoil to approved dump on site Main drain 160mm in supplied in 35m lengths

450mm deep 100m 2000.00 600mm deep 100m 2500.00 900mm deep 100m 3400.00

Extra for couplings each 2.00 As above but with 100mm main drain supplied in 100m lengths

450mm deep 100m 1325.00 600mm deep 100m 1675.00 900mm deep 100m 2350.00

Extra for couplings each 1.65

Laterals to mains above; herringbone pattern; excavation and backfilling as above; inclusive of connecting lateral to main drain 160mm pipe to 450mm deep trench

laterals at 1.0m centres 100m² 2000.00 laterals at 2.0m centres 100m² 1000.00 laterals at 3.0m centres 100m² 660.00 laterals at 5.0m centres 100m² 400.00 laterals at 10.0m centres 100m² 200.00

160mm pipe to 600mm deep trench laterals at 1.0m centres 100m² 2500.00 laterals at 2.0m centres 100m² 1250.00 laterals at 3.0m centres 100m² 830.00 laterals at 5.0m centres 100m² 500.00 laterals at 10.0m centres 100m² 250.00

£ Excluding site overheads and profit

160mm pipe to 900mm deep trench laterals at 1.0m centres 100m² 3400.00 laterals at 2.0m centres 100m² 1675.00 laterals at 3.0m centres 100m² 1100.00 laterals at 5.0m centres 100m² 670.00 laterals at 10.0m centres 100m² 340.00

Extra for 160/160mm couplings connecting laterals to main drain laterals at 1.0m centres 10m 79.00 laterals at 2.0m centres 10m 39.00 laterals at 3.0m centres 10m 26.00 laterals at 5.0m centres 10m 15.70 laterals at 10.0m centres 10m 7.85

100mm pipe to 450mm deep trench laterals at 1.0m centres 100m² 1325.00 laterals at 2.0m centres 100m² 660.00 laterals at 3.0m centres 100m² 430.00 laterals at 5.0m centres 100m² 260.00 laterals at 10m centres 100m² 130.00

100mm pipe to 600mm deep trench laterals at 1.0m centres 100m² 1675.00 laterals at 2.0m centres 100m² 840.00 laterals at 3.0m centres 100m² 550.00 laterals at 5.0m centres 100m² 335.00 laterals at 10.0m centres 100m² 170.00

100mm pipe to 900mm deep trench laterals at 1.0m centres 100m² 2350.00 laterals at 2.0m centres 100m² 1175.00 laterals at 3.0m centres 100m² 770.00 laterals at 5.0m centres 100m² 470.00 laterals at 10.0m centres 100m² 230.00

80mm pipe to 450mm deep trench laterals at 1.0m centres 100m² 1275.00 laterals at 2.0m centres 100m² 640.00 laterals at 3.0m centres 100m² 420.00 laterals at 5.0m centres 100m² 255.00 laterals at 10.0m centres 100m² 130.00

80mm pipe to 600mm deep trench laterals at 1.0m centres 100m² 1650.00 laterals at 2.0m centres 100m² 820.00 laterals at 3.0m centres 100m² 540.00 laterals at 5.0m centres 100m² 330.00 laterals at 10.0m centres 100m² 160.00

80mm pipe to 900mm deep trench laterals at 1.0m centres 100m² 2300.00 laterals at 2.0m centres 100m² 1150.00 laterals at 3.0m centres 100m² 760.00 laterals at 5.0m centres 100m² 460.00 laterals at 10.0m centres 100m² 230.00

£ Excluding site overheads and profit

SUBSOIL DRAINAGE – BY HAND – CONT

Laterals to mains above – cont Extra for 100/80mm couplings connecting laterals to main drain

laterals at 1.0m centres 10m 37.00 laterals at 2.0m centres 10m 18.60 laterals at 3.0m centres 10m 12.40 laterals at 5.0m centres 10m 7.45 laterals at 10.0m centres 10m 3.70

SOAKAWAYS

Construct soakaway from perforated concrete rings; excavation, casting in situ concrete ring beam base; filling with gravel 250mm deep; placing perforated concrete rings; surrounding with geofabric and backfilling to external surround of soakaway with 250mm wide granular surround and excavated material; step irons and cover slab; inclusive of all earthwork retention and disposal off site of surplus material 900mm diameter

1.00m deep nr 590.00 2.00m deep nr 960.00

1200mm diameter 1.00m deep nr 780.00 2.00m deep nr 1275.00

2400mm diameter 1.00m deep nr 2225.00 2.00m deep nr 3600.00

Aquacell Infiltration unit soakaway; 1.00m×500×400mm; 200 litre volume each in trench Excavate for new soakaway; grade bottom of excavation; Lay bedding layer of 100mm sharp sand; Install geotextile to line excavation and bedding; Install Aquacell units in bonded formation; wrap entire installation in geotextile; back filling to surround in MOT Type 2 150mm thick. Place sharp sand over infiltration units; inclusive of connection only of in-flow pipework; Cover over 500 deep with Type 2granular material.