ABSTRACT

Reclamation project; Complexity rating – 4 £100,000.00 – – – – – nr 12000.00 £250,000.00 – – – – – nr 26000.00 £500,000.00 – – – – – nr 45000.00 £1,000,000.00 – – – – – nr 80000.00

Housing; Complexity rating – 3 £100,000.00 – – – – – nr 11000.00 £250,000.00 – – – – – nr 23000.00 £500,000.00 – – – – – nr 40000.00 £1,000,000.00 – – – – – nr 74000.00

Labour Plant Material Unit

Excluding site overheads and profit £ hours £ £ £ rate £

C20 DEMOLITION FENCES AND GATES

Demolish existing fence; remove stakes or

grub out posts as appropriate; remove to

stock pile for removal off site; (not

included)

Mechanical demolition; clear fence line

chain link fence 1.20-1.50m high – 0.01 0.39 0.65 – m 1.04 closeboard or timber panel fence 1.80m

high – 0.03 0.97 1.19 – m 2.16 Mechanical demolition; Light shrubs or

creepers in chainlinks

chain link fence 1.20-1.50m high – 0.01 0.49 0.83 – m 1.32 closeboard or timber panel fence 1.80m

high – 0.03 1.30 1.60 – m 2.90 Mechanical demolition; heavy shrubs or

creepers bramble and the like requiring

clearance to enable removal

fence 1.20-1.50m high – 0.05 1.95 2.02 – m 3.97 closeboard or timber panel fence 1.80m

high – 0.05 1.95 2.59 – m 4.54 Demolition and site transport by hand; clear

fence lines

fence 1.20-1.50m high – 0.03 1.30 – – m 1.30 closeboard or timber panel fence 1.80m

high – 0.07 2.60 – – m 2.60 Demolition and site transport by hand; light

vegetation and creepers

fence 1.20-1.50m high – 0.05 1.95 – – m 1.95 closeboard or timber panel fence 1.80m

high – 0.13 4.88 – – m 4.88 Demolition and site transport by hand; heavy

shrubs or creepers bramble and the like

requiring clearance to enable removal

fence 1.20-1.50m high – 0.13 4.88 – – m 4.88 closeboard or timber panel fence 1.80m

high – 0.17 6.50 – – m 6.50

Demolition of Posts and straining posts

Break out straining post; grub out concrete

footings; remove to stockpile on site

single straining post by machine – 0.25 4.88 15.73 – nr 20.61 double straining post by machine – 0.30 5.85 18.37 – nr 24.22 single straining post by hand – 1.00 39.00 – – nr 39.00 double straining post by hand – 1.25 48.75 – – nr 48.75

Break out gatepost; concrete steel or timber;

girth not exceeding 150mm; grub out concrete

footings

by machine – 0.25 4.88 15.73 – nr 20.61 by hand – 1.00 19.50 – – nr 19.50

Labour Plant Material Unit

Excluding site overheads and profit £ hours £ £ £ rate £

D20 GROUND CLEARANCE BY MACHINE

Mechanical Ground clearance to large

areas; Cleartrack (Evl) Limited; Vegetation

clearance of high capacity mobile mulching

machines; 500 HP; 2.50m head width;

tracked; wheeled; skid steer and 360°

operating;

Site clearance and in situ mulching and

incorporating to soil surface to existing area of

scrub and small trees up to 150mm diameter.