ABSTRACT
Reclamation project; Complexity rating – 4 £100,000.00 – – – – – nr 12000.00 £250,000.00 – – – – – nr 26000.00 £500,000.00 – – – – – nr 45000.00 £1,000,000.00 – – – – – nr 80000.00
Housing; Complexity rating – 3 £100,000.00 – – – – – nr 11000.00 £250,000.00 – – – – – nr 23000.00 £500,000.00 – – – – – nr 40000.00 £1,000,000.00 – – – – – nr 74000.00
Labour Plant Material Unit
Excluding site overheads and profit £ hours £ £ £ rate £
C20 DEMOLITION FENCES AND GATES
Demolish existing fence; remove stakes or
grub out posts as appropriate; remove to
stock pile for removal off site; (not
included)
Mechanical demolition; clear fence line
chain link fence 1.20-1.50m high – 0.01 0.39 0.65 – m 1.04 closeboard or timber panel fence 1.80m
high – 0.03 0.97 1.19 – m 2.16 Mechanical demolition; Light shrubs or
creepers in chainlinks
chain link fence 1.20-1.50m high – 0.01 0.49 0.83 – m 1.32 closeboard or timber panel fence 1.80m
high – 0.03 1.30 1.60 – m 2.90 Mechanical demolition; heavy shrubs or
creepers bramble and the like requiring
clearance to enable removal
fence 1.20-1.50m high – 0.05 1.95 2.02 – m 3.97 closeboard or timber panel fence 1.80m
high – 0.05 1.95 2.59 – m 4.54 Demolition and site transport by hand; clear
fence lines
fence 1.20-1.50m high – 0.03 1.30 – – m 1.30 closeboard or timber panel fence 1.80m
high – 0.07 2.60 – – m 2.60 Demolition and site transport by hand; light
vegetation and creepers
fence 1.20-1.50m high – 0.05 1.95 – – m 1.95 closeboard or timber panel fence 1.80m
high – 0.13 4.88 – – m 4.88 Demolition and site transport by hand; heavy
shrubs or creepers bramble and the like
requiring clearance to enable removal
fence 1.20-1.50m high – 0.13 4.88 – – m 4.88 closeboard or timber panel fence 1.80m
high – 0.17 6.50 – – m 6.50
Demolition of Posts and straining posts
Break out straining post; grub out concrete
footings; remove to stockpile on site
single straining post by machine – 0.25 4.88 15.73 – nr 20.61 double straining post by machine – 0.30 5.85 18.37 – nr 24.22 single straining post by hand – 1.00 39.00 – – nr 39.00 double straining post by hand – 1.25 48.75 – – nr 48.75
Break out gatepost; concrete steel or timber;
girth not exceeding 150mm; grub out concrete
footings
by machine – 0.25 4.88 15.73 – nr 20.61 by hand – 1.00 19.50 – – nr 19.50
Labour Plant Material Unit
Excluding site overheads and profit £ hours £ £ £ rate £
D20 GROUND CLEARANCE BY MACHINE
Mechanical Ground clearance to large
areas; Cleartrack (Evl) Limited; Vegetation
clearance of high capacity mobile mulching
machines; 500 HP; 2.50m head width;
tracked; wheeled; skid steer and 360°
operating;
Site clearance and in situ mulching and
incorporating to soil surface to existing area of
scrub and small trees up to 150mm diameter.