ABSTRACT

Dumper 3 tonne Thwaites self drive (28 hours/week) hr 3.90 Dumper 6 ton Thwaites self drive (28 hours/week) hr 5.00 Excavator Tracked 5 ton self drive (28 hours/week) hr 12.10 Fork lift telehandler self drive (28 hours/week) hr 10.40 Fuel charge Red diesel hr 0.95 JCB 3CX 4 × 4 Sitemaster fueled operated hr 43.00 Mini Excavator 1.5 tonne self drive hr 5.35 Mini Excavator JCB 803 Rubber tracks self drive hr 8.55 Mini Excavator JCB 803 Steel tracks self drive hr 8.55 Skip loader 1 tonne hr 3.90

HSS Access tower; alloy; 5.2m day 34.50 Cultivator; 110kg hr 7.95 Diamond blade consumable; 450mm; concrete mm 29.00 Heavy-duty breaker; 110 v; 2200 w hr 4.00 Mesh fence; (Heras fence) 2.85×2.0m high 1m/wk 0.80 Oxy-acetylene cutting kit hr 6.30 Petrol masonry saw bench; 350mm hr 5.35 Petrol poker vibrator + 50mm head hr 2.05 Post hole borer; 1man; daily rate hr 4.10 Vibrating plate compactor hr 2.80

DEMOLITION AND SITE CLEARANCE

Demolish existing surfaces by hand held electric breaker; removal by grab Break up plain concrete slab; remove to licensed tip;

150mm thick m² 10.60 200mm thick m² 13.10

Break up reinforced concrete slab and remove to licensed tip 150mm thick m² 17.90 200mm thick m² 23.00 300mm thick m² 42.50

Break out existing surface and associated 150mm thick granular base load to remove off site by grab

macadam 70mm thick m2 12.00 block paving 50mm thick m2 15.90 block paving 80mm thick m2 18.00

Demolish existing free-standing walls; grub out foundations; remove arisings to skip; backfill with imported topsoil; works by excavator, dumper and diesel breaker Brick wall; 112mm thick

300mm high m 30.00 500mm high m 42.00

£ Excluding site overheads and profit

Brick wall; 225mm thick 300mm high m 39.50 500mm high m 42.00 1.00m high m 52.00 1.20m high m 62.00 1.50m high m 66.00 1.80m high m 74.00

Demolish existing free-standing walls; grub out foundations; remove arisings to skip; backfill with imported topsoil; works by hand and diesel breaker Brick wall; 112mm thick

300mm high m 32.00 500mm high m 34.50

Brick wall; 225mm thick 300mm high m 42.00 500mm high m 46.00 1.00m high m 59.00 1.20m high m 72.00 1.50m high m 76.00 1.80m high m 86.00

Break out existing free-standing building; break out plain concrete base 150mm thick and remove to skip distance 50m; backfill with imported topsoil; all works by hand Timber buildings

shed 6.0m2 nr 320.00 shed 10.0m2 nr 710.00 shed 15.0m2 nr 970.00

Site clearance – General Clear away light fencing and gates (chain link, chestnut paling, light boarded fence or similar) and remove to licensed tip 100m 315.00 Strip turf; strip topsoil 250mm thick move to stockpile 25m

all by machine; disposal of turf of to skip 100m 800.00 by machine; disposal of turf by grab 100m 720.00 strip and stack turf for preservation by hand; strip soil by machine 100m 980.00 by hand; disposal to skip 100m 2300.00

Clear mixed shrub area; dig out roots Groundcovers and small shrubs 20%; shrubs 1.0-2.0m high 40%; shrubs 2.0-3.0m high 20%; shrubs over 3.0m high 20%

clearance only m2 31.00 disposal to skip; chipped m2 20.00 disposal to skip; unchipped m2 42.00 disposal on site; unchipped m2 4.85