ABSTRACT

Throughout this playbook, I have discussed the Lean concepts that can help reduce the time associated with setup and help you develop quick changeover concepts. Now, that those topics have been discussed, let us return to your original time studies and spaghetti diagram to evaluate which concept can be applied. https://s3-euw1-ap-pe-df-pch-content-public-p.s3.eu-west-1.amazonaws.com/9780429255120/bf35e5aa-64e0-4387-865d-1fdc9cc2744b/content/page45_1.jpg"/> 46

Work Description: Engine Frame Setup

Step

Work Content

I

E

AVG

Improvement

1

Remove Part from Machine with Allen Wrench

X

0

Perform External with One-Turn Method and Intermediate Process

2

Place on Cart and Move into Inventory

X

0

Perform While Machine is Running (External)

3

Reset Computer and Machine to Start Position

X

0

Perform While Machine is Running (External)

4

Retrieve Engine Frame Fixture

X

0

Move Fixture Closer: 5S

5

Retrieve Procedure and Tools

X

0

Work Instructions in Work Area Posted Shadow Board: 5S

6

Retrieve Material

X

0

Move Fixture Closer: 5S

7

Remove Fixture from Last Part

X

0

Perform External with One-Turn Method and Intermediate Process

8

Place new Fixture in Machine

X

0

Perform External with One-Turn Method and Intermediate Process

9

Tighten Down Fixture

X

0

Perform External with One-Turn Method and Intermediate Process

10

Place Material in Fixture

X

0

Perform External with One-Turn Method and Intermediate Process

11

Close Doors and Run Verification Test

X

0.634

12

Open Doors and Adjust Position as Needed

X

0.47

13

Close Doors and Run Final Test

X

0.626

14

Turn to Machine RUN

X

0.15

15

Machine Cut Material

X

6.55

Total Time

8.43