ABSTRACT

Held there was an innominate term (not a condition) that the ship would be delivered seaworthy. Whether a breach of that term allowed the innocent party to terminate depended on the seriousness of the breach: did it go to the root of the contract? Here, the charterers still had 17 months of use. They could recover damages for the other period, but they could not terminate the contract.