ABSTRACT

The so called rule in Hadley v Baxendale was stated as follows: Where two parties have made a contract, which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, that is, according to the usual course of things, from such breach of contract itself or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it – where the plaintiffs, the owners of a flour mill, sent a broken iron shaft to an office of the defendants, who were common carriers, to be conveyed by them, and the defendants’ clerk, who attended at the office, was told that the mill was stopped, that the shaft must be delivered immediately, and that a special entry, if necessary, must be made to hasten its delivery; and the delivery of the broken shaft to the consignee, to whom it had been sent by the plaintiffs as a pattern, by which to make a new shaft, was delayed for an unreasonable time; in consequence of which, the plaintiffs did not receive the new shaft for some days after the time they ought to have received it, and they were consequently unable to work their mill from want of the new shaft, and thereby incurred a loss of profits – held, that, under the circumstances, such loss could not be recovered in an action against the defendants as common carriers.