ABSTRACT

Hutchison J: [In Anglia Television Ltd v Reed, Lord Denning said:] ‘Anglia Television then sued Mr Reed for damages. He did not dispute his liability, but a question arose as to the damages. Anglia Television do not claim their profit. They cannot say what their profit would have been on this contract if Mr Reed had come here and performed it. So, instead of a claim for loss of profits, they claim for the wasted expenditure. They had incurred the director’s fees, the designer’s fees, the stage manager’s and assistant manager’s fees, and so on. It comes in all to £2,750. Anglia Television say that all that money was wasted because Mr Reed did not perform his contract ... It seems to me that a plaintiff in such a case as this has an election: he can either claim for loss of profits or for his wasted expenditure. But he must elect between them. He cannot claim both. If he has not suffered any loss of profits – or if he cannot prove what his profits would have been – he can claim in the alternative the expenditure which has been thrown away, that is, wasted, by, reason of the breach. That is shown by Cullinane v British ‘Rema’ Manufacturing Co Ltd [1954] 1 QB 292, pp 303 and 308. If the plaintiff claims the wasted expenditure, he is not limited to the expenditure incurred after the contract was concluded. He can claim also the expenditure incurred before the contract, provided that it was such as would reasonably be in the contemplation of the parties as likely to be wasted if the contract was broken. Applying that principle here, it is plain that, when Mr Reed entered into this contract, he must have known perfectly well that much expenditure had already been incurred on director’s fees and the like. He must have contemplated – or, at any rate, it is reasonably to be imputed to him – that if he broke his contract, all that expenditure would be wasted, whether or not it was incurred before or after the contract. He must pay damages for all the expenditure so wasted and thrown away.’