ABSTRACT
In successive project studies and financing plans, the project costs escalated and targets moved in the following manner. https://www.niso.org/standards/z39-96/ns/oasis-exchange/table">
Year of Study
Project
Project Capital Cost $ million
Maximum Funding $ million
Jun 72
Lonrho’s feasibility study
125
125
Aug 73
First revision of Lonrho’s feasibility study
142
142
Jun 74
Second revision of Lonrho’s feasibility study
177
183
May 76
Project report by Lonrho
276
340
Aug 76
Project report by Lonrho
350
420
Nov 76
Project study by Alexander & Baldwin Agribusiness of Hawaii (appointed by KFTCIC)
450
535
Oct 77
Project report and financing plan by ABA of Hawaii
530
599
Dec 78
– ditto –
571
599
May 79
– ditto –
571
614
Aug 79
– ditto –
586
643
Sept 79
– ditto –
586
688