ABSTRACT

The Employer shall give the Contractor right of access to, and possession of, all parts of the Site within the time stated in the Contract Data. Giving access to the Contractor of the Site in a timely and cooperative manner is the key to a successful execution of the Works. The Employer’s arrangements for financing the Employer’s obligations under the Contract shall be detailed in the Contract Data. If the Employer intends to make any material change to these financial arrangements, or has to do so because of changes in the Employer’s financial situation, the Employer shall immediately give a Notice to the Contractor with detailed supporting particulars. The Employer shall have made available to the Contractor for information, before the Base Date, all relevant data in the Employer’s possession on the topography of the Site and on sub-surface, hydrological, climatic and environmental conditions at the Site.