ABSTRACT

Time is one of the fundamental variables in every construction project, and perhaps the one that the parties have the least control over. This chapter is concerned with the Contractor's time obligations under the FIDIC forms. The programme will set out the anticipated order, timing and duration of the different tasks or activities which, if adhered to, will result in the Works completed within the time for completion and the other obligations of the Contractor fulfilled. A contractor's obligation to complete the work which they have agreed to carry out within the time required by the contract is one of the most important obligations under almost every construction contract. The instruction to accelerate is effected through an instruction to the Contractor to submit a revised programme and supporting report describing the revised methods he proposes to adopt to “expedite progress and to complete within the time for completion”.