ABSTRACT

By the first (1st) Day of the <<fourth (4th)>> calendar month after the Combined Cycle Notice to Commence, the Contractor shall notify the Sponsor in writing of the schedule of dates in which the above mentioned Existing Plant Shutdown Hours will be executed, for each generating unit, required for Contractor to perform the Work.