FORM OF PROGRESS REPORT 1 Scheduling Methods
1.1 Contractor will maintain the project master schedule. The master schedule will be of sufficient detail as to allow any user of <<insert program name>> program to easily identify the single “CRITICAL PATH” and overall project “PERCENTAGES COMPLETE” for main areas of effort and the entire project.