ABSTRACT

The scheduling methods discussed in Chapter 6 assume that activity times are known and fixed, even though in reality they are estimated and variable. This chapter discusses the implications of variable activity times on project schedules and the methods for handling uncertainty in project completion dates, namely PERT and Critical Chain. It also covers methods for reducing the project duration, starting with CPM.