ABSTRACT

General groundworks team Generally a three man team is used in this section; The column Labour hours reports team hours. The column Labour £ reports the total cost of the team for the unit of work shown

3man team – 1.00 71.25 – – hr 71.25 2man team – 1.00 47.50 – – hr 47.50

BOREHOLES

Borehole drilling; Agripower Ltd Drilling operations to average 100m depth; lining with 150mm diameter sieve

drilling to 100m – – – – – nr 12720.00 rate per m over 100m – – – – – m 127.20 pump, rising main, cable and kiosk – – – – – nr 5300.00

COLD WATER

Blue MDPE polythene pipes; type 50; for cold water services; with compression fittings; bedding on 100mm DOT type 1granular fill material Pipes

20mm diameter 0.48 0.08 1.90 – 4.93 m 6.83 25mm diameter 1.10 0.08 1.90 – 5.56 m 7.46 32mm diameter 1.35 0.08 1.90 – 5.80 m 7.70 50mm diameter 2.22 0.10 2.38 – 6.67 m 9.05 60mm diameter 3.55 0.10 2.38 – 8.01 m 10.39

Hose union bib taps; including fixing to wall; making good surfaces

15mm 13.77 0.75 17.81 – 14.17 nr 31.98 22mm 18.44 0.75 17.81 – 19.04 nr 36.85

Stopcocks; including fixing to wall; making good surfaces

15mm 8.06 0.75 17.81 – 8.46 nr 26.27 22mm 12.09 0.75 17.81 – 12.49 nr 30.30

Standpipes; to existing 25mm water mains

1.00m high – – – – – nr 225.00

PC Labour Labour Plant Excluding site overheads and profit £ hours £ £ £ rate £

COLD WATER – cont

Blue MDPE polythene pipes – cont Hose junction bib taps; to standpipes

19mm – – – – – nr 80.00

RAINWATER HARVESTING

Rainwater harvesting tanks Note: Rainwater harvesting tanks must be installed on granular or concrete bases. If installed below ground the tanks may require construction of drained underground chambers to support them. Please see the appropriate sections in this book for excavation, disposal, bases, retaining walls and drainage.