ABSTRACT

Total Gang Rate/Hour 1.00 69.14 – – - 69.14 Bracket erection gang

1 ganger/chargehand (skill rate 4) 2.00 17.72 – – - 17.72 1 skilled operative (skill rate 4) 1.00 16.70 – – - 16.70 1 plant operator (skill rate 4) 1.00 20.02 – – - 20.02 1 plant operator (craftsman) 1.00 38.26 – – - 38.26

Total Gang Rate/Hour 1.00 92.70 – – - 92.70 Lanterns gang

1 skilled operative (skill rate 3) 1.00 18.55 – – - 18.55 1 skilled operative (skill rate 4) 1.00 16.70 – – - 16.70 1 plant operator (skill rate 4) 1.00 20.02 – – - 20.02 1 plant operator (craftsman) 1.00 38.26 – – - 38.26

Total Gang Rate/Hour 1.00 93.54 – – - 93.54

RESOURCES – PLANT Columns and bracket arms

15 t mobile crane – 50% of time – – 44.85 – - 44.85 125 cfm compressor – 50% of time – – 5.82 – - 5.82 compressor tools: 2 single head scabbler – 50% of time – – 1.58 – - 1.58 2 t dumper – 50% of time – – 4.00 – - 4.00

Total Rate/Hour – – 56.24 – - 56.24 Bracket arms

15 t mobile crane – – 89.71 – - 89.71 access platform, Simon hoist (50 ft) – – 22.02 – - 22.02

Total Rate/Hour – – 111.73 – - 111.73

hours £ £ £ rate £

RESOURCES – PLANT – cont Lanterns

15 t mobile crane – – 89.71 – - 89.71 access platform, Simon hoist (50 ft) – – 22.02 – - 22.02

Total Rate/Hour – – 111.73 – - 111.73

ROAD LIGHTING COLUMNS, BRACKETS, WALL MOUNTINGS, CCTV MASTS AND CANTILEVER MASTS Galvanised steel road lighting columns to BS EN 40 with flange plate base (including all control gear, switching, fuses and internal wiring)

4.0m nominal height 0.75 51.85 42.19 128.77 nr 222.81 6.0m nominal height 0.80 55.31 60.16 352.72 nr 468.19 8.0m nominal height 0.96 66.37 72.19 447.89 nr 586.45 10.0m nominal height 1.28 88.50 96.26 559.87 nr 744.63 12.0m nominal height 1.44 99.56 108.29 862.19 nr 1070.04 15.0m nominal height 1.76 121.69 132.35 1343.68 nr 1597.72 3.0m cast iron column (pedestrian/landscape area) 0.75 51.85 56.41 1567.62 nr 1675.88

Precast concrete lighting columns to BS EN 40 with flange plate base (including all control gear, switching, fuses and internal wiring)

5.0m nominal height 0.75 51.85 56.41 256.28 nr 364.54 10.0m nominal height 1.28 88.50 96.29 651.84 nr 836.63

Galvanised steel bracket arm to BS EN 40; with 5° uplift

0.5m projection, single arm 0.16 14.83 43.12 278.56 nr 336.51 1.0m projection, single arm 0.19 17.61 21.23 389.99 nr 428.83 1.5m projection, single arm 0.21 14.52 23.30 445.70 nr 483.52 2.0m projection, single arm 0.27 25.03 30.17 501.40 nr 556.60 1.0m projection, double arm 0.29 26.88 32.40 501.40 nr 560.68 2.0m projection, double arm 0.32 29.67 35.75 557.12 nr 622.54

Precast concrete bracket arm to BS EN 40; with 5° uplift

1.0m projection, single arm 0.24 22.25 26.82 152.94 nr 202.01 2.0m projection, single arm 0.32 29.67 35.75 180.24 nr 245.66 1.0m projection, double arm 0.35 32.45 39.11 218.48 nr 290.04 2.0m projection, doube arm 0.37 34.30 41.34 273.10 nr 348.74

Lantern unit with photo-electric control set to switch on at 100 lux; lamps

55W SON (P226); to suit 4m and 5m columns 0.40 37.41 26.75 278.56 nr 342.72 70W SON (P236); to suit 5m and 6m columns 0.40 37.41 26.75 295.28 nr 359.44 250W SON (P426); to suit 8m, 10m and 12m columns 0.50 46.77 33.44 434.56 nr 514.77 Sphere 70W SON; to suit 3m columns (P456) 0.50 46.77 33.44 518.13 nr 598.34 400W SON High pressure sodium; to suit 12m and 15m columns 0.50 46.77 33.44 518.13 nr 598.34

hours £ £ £ rate £

REMOVE FROM STORE AND RE-ERECT ROAD LIGHTING COLUMNS AND BRACKETS AND MASTS Re-erection of galvanised steel road lighting columns with flange plate base; including all control gear, switching, fuses and internal wiring

4.0m nominal height 0.75 51.85 42.20 20.89 nr 114.94 6.0m nominal height 0.80 55.31 45.03 27.30 nr 127.64 8.0m nominal height 0.96 66.37 53.99 33.70 nr 154.06 10.0m nominal height 1.28 88.50 72.02 40.11 nr 200.63 12.0m nominal height 1.44 99.56 81.02 45.86 nr 226.44 15.0m nominal height 1.76 121.69 99.02 51.53 nr 272.24 3.0m cast iron column (pedestrian/landscape area) 0.75 51.85 42.22 17.55 nr 111.62

Re-erection of precast concrete lighting columns with flange plate base; including all control gear, switching, fuses and internal wiring

5.0m nominal height 0.75 51.85 42.20 24.24 nr 118.29 10.0m nominal height 1.28 88.50 72.02 40.11 nr 200.63

Re-erection of galvanised steel bracket arms 0.5m projection, single arm 0.16 14.83 17.88 33.43 nr 66.14 1.0m projection, single arm 0.19 17.61 21.23 33.43 nr 72.27 1.5m projection, single arm 0.21 19.47 23.46 33.43 nr 76.36 2.0m projection, single arm 0.27 25.03 30.17 33.43 nr 88.63 1.0m projection, double arm 0.29 26.88 32.40 33.43 nr 92.71 2.0m projection, double arm 0.32 29.67 35.75 33.43 nr 98.85

Re-erection of precast concrete bracket arms 1.0m projection, single arm 0.24 22.25 26.82 33.43 nr 82.50 2.0m projection, single arm 0.32 29.67 35.75 33.43 nr 98.85 1.0m projection, double arm 0.35 32.45 39.66 33.43 nr 105.54 2.0m projection, double arm 0.37 34.30 39.11 33.43 nr 106.84

Re-installing lantern unit with photo-electric control set to switch on at 100 lux; lamps

55W SON (P226); to suit 4m and 5m columns 0.40 37.41 26.75 – nr 64.16 70W SON (P236); to suit 5m and 6m columns 0.22 20.58 26.75 – nr 47.33 250W SON (P426); to suit 8m, 10m and 12m columns 0.50 46.77 33.44 – nr 80.21 Sphere 70W SON; to suit 3m (P456) 0.50 46.77 33.44 – nr 80.21 400W SON High pressure sodium; to suit 12m and 15m columns 0.50 46.77 33.44 – nr 80.21