ABSTRACT
Remove existing set paving m²/hr 0.80 10 5 17 6
Break out brickwork in cement mortar: 215mm thick m²/hr 0.20 3 2 5 2
Break out concrete in areas
100mm thick m²/hr 0.90 9 5 14 5
150mm thick m²/hr 0.50 7 4 10 4
225mm thick m²/hr 0.30 4 2 6 2
300mm thick m²/hr 0.20 3 1 4 1
Break out reinforced concrete m³/hr 0.02 0.40 0.20 0.60 0.20
Break out sandstone m³/hr 0.03 0.50 0.30 0.80 0.30