Congestion charging London only week 40.00

£ Excluding site overheads and profit

Site Setup and Site Establishment

Site fencing; supply and erect temporary protective fencing and remove at completion of works Cleft chestnut paling

1.20m high 75mm larch posts at 3m centres 100m 930.00 1.50m high 75mm larch posts at 3m centres 100m 1075.00

Heras fencing 2 week hire period 100m 970.00 4 week hire period 100m 1475.00 8 week hire period 100m 2450.00 12 week hire period 100m 3450.00 16 week hire period 100m 4450.00 24 week hire period 100m 6400.00

Site compounds Establish site administration area on reduced compacted Type 1 base; 150mm thick; allow for initial setup of site office and welfare facilities for site manager and maximum 8site operatives

temporary base or hard standing; 20× 10m 200m2 2450.00

To hardstanding area above; erect office and welfare accommodation; allow for furniture, telephone connection, and power; restrict access using temporary safety fencing to the perimeter of the site administration area Establishment; delivery and collectioncosts only

site office and chemical toilet; 20m of site fencing nr 850.00 site office and chemical toilet; 40m of site fencing nr 920.00 site office and chemical toilet; 60m of site fencing nr 980.00

Weekly hire rates of site compound equipment site office 2.4 × 3.6m; chemical toilet; 20m of site fencing week 115.00 site office 4.8 × 2.4m; chemical toilet; 20m of site fencing; armoured store 2.4 × 3.6m week 130.00 site office 2.4 × 3.6m; chemical toilet; 40m of site fencing week 165.00 site office 2.4 × 3.6m; chemical toilet; 60m of site fencing week 215.00

Removal of site compound Remove base; fill with topsoil and reinstate to turf on completion of site works 200m2 1675.00

Surveying and setting out Note: In all instances a quotation should be obtained from a surveyor. The following cost projections are based on the costs of a surveyor using EDM (electronic distance measuring equipment) where an average of 400 different points on site are recorded in a day. The surveyed points are drawn in a CAD application and the assumption used that there is one day of drawing up for each day of on-site surveying.