ABSTRACT

Removing tree stumps girth 600mm-1.50m – 2.00 39.50 82.50 – nr 122.00 girth 1.50-3.00m – 7.00 138.25 78.20 – nr 216.45 girth over 3.00m – 12.00 237.00 134.06 – nr 371.06

Stump grinding; disposing to spoil heaps girth 600mm-1.50m – 2.00 39.50 32.20 – nr 71.70 girth 1.50-3.00m – 2.50 49.38 64.41 – nr 113.79 girth over 3.00m – 4.00 79.00 56.35 – nr 135.35

Clearing site vegetation mechanical clearance – 0.25 4.94 13.59 – 100m2 18.53 hand clearance – 2.00 39.50 – – 100m2 39.50

Lifting turf for preservation sod cutter machine lift and stack – 0.75 14.81 9.96 – 100m2 24.77 hand lift and stack – 8.33 164.58 – – 100m2 164.58

Lifting turf for disposal (disposal not included)

by excavator; 5 tonne – – – 40.52 – 100m2 40.52 by excavator; 7 tonne – – – 30.99 – 100m2 30.99 by excavator; 7 tonne; working with two dumpers – – – 29.19 – 100m2 29.19 by excavator; 7 tonne; working with two dumpers – – – 24.96 – 100m2 24.96 hand lift and stack – 8.33 164.58 – – 100m2 164.58

Site clearance; by machine; clear site of mature shrubs from existing cultivated beds; dig out roots by machine Mixed shrubs in beds; planting centres 500mm average

height less than 1m – 0.03 0.49 0.79 – m2 1.28 1.00-1.50m – 0.04 0.79 1.26 – m2 2.05 1.50-2.00m; pruning to ground level by hand – 0.10 1.98 3.15 – m2 5.13 2.00-3.00m; pruning to ground level by hand – 0.10 1.98 6.29 – m2 8.27 3.00-4.00m; pruning to ground level by hand – 0.20 3.95 10.48 – m2 14.43

Material Excluding site overheads and profit £ hours £ £ £ rate £

SITE PREPARATION AND CLEARANCE – cont

Site clearance; by hand; clear site of mature shrubs from existing cultivated beds; dig out roots Mixed shrubs in beds; planting centres 500mm average

height less than 1m – 0.33 6.58 – – m2 6.58 1.00-1.50m – 0.50 9.88 – – m2 9.88 1.50-2.00m – 1.00 19.75 – – m2 19.75 2.00-3.00m – 2.00 39.50 – – m2 39.50 3.00-4.00m – 3.00 59.26 – – m2 59.26

Mechanical ground clearance to large areas; Cleartrack (Evl) Limited; vegetation clearance of high capacity mobile mulching machines; 500 HP; 2.50m head width; tracked; wheeled; skid steer and 360 degree operating Site clearance and in situ mulching and incorporating to soil surface to existing area of scrub and small trees up to 150mm dia.; cleared mulched material left on surface for clearance to stockpile (not included)

Areas of existing grass, bramble and weed; average height not exceeding 1.00m – – – – – 100m2 10.25 Areas of existing small shrubs and weed; average height not exceeding 1.80m – – – – – 100m2 15.38 Areas of existing grass, bramble, weed and regular shrubs; varying heights to 3.00m; max stem dia. 100mm – – – – – 100m2 21.52 Areas of existing grass, bramble, weed, regular shrubs and small trees; varying heights up and over 3.00m; max stem dia. 150mm – – – – – 100m2 55.35

Spraying of vegetation; Glyphosate at 5l/ ha by tractor drawn spray equipment – – – – – 100m2 2.56

Excavated material; on site In spoil heaps

average 25m distance – – – 2.80 – m3 2.80 average 50m distance – – – 3.23 – m3 3.23 average 100m distance (1 dumper) – – – 4.05 – m3 4.05 average 100m distance (2 dumpers) – – – 4.18 – m3 4.18 average 200m distance – – – 4.89 – m3 4.89 average 200m distance (2 dumpers) – – – 5.02 – m3 5.02

Material Excluding site overheads and profit £ hours £ £ £ rate £

EXCAVATING

Market prices of topsoil; prices shown include for 20% settlement Multiple source screened topsoil – – – – 33.60 m3 33.60 Single source topsoil; British Sugar PLC – – – – 33.60 m3 33.60 High grade topsoil for planting – – – – 52.80 m3 52.80

Note: The figures in this section relate to the machine capacities shown earlier in this section. The figures below however allow for dig efficiency based on depth. A banksman is allowed for in all excavation build and disposal costs shown. Bulkages of 25% allowed; adjustments should be made for different soil types.