ABSTRACT

The following unit costs for ‘excavation in material other than topsoil, rock or artificial hard material’ are based on excavation in firm sand and gravel soils.

For alternative types of soil, multiply the following rates by:

Scrapers Stiff clay 1.5 Chalk 2.5 Soft rock 3.5 Broken rock

3.7

Tractor dozers and loaders

Stiff clay 2.0 Chalk 3.0 Soft rock 2.5 Broken rock

2.5

Backacter (minimum bucket size 0.5 m3)

Stiff clay 1.7 Chalk 2.0

rock

Basis of disposal rates

All pricing and estimating for disposal is based on the volume of solid material excavated and rates for disposal should be adjusted by the following factors for bulkage. Multiply the rates by:

Sand bulkage

1.10

Gravel bulkage

1.20

Compacted soil bulkage

1.30

Compacted sub-base, suitable

fill etc. bulkage

1.30

Stiff clay bulkage

1.20

See also Part 13: Tables and Memoranda

Basis of rates generally

To provide an overall cost comparison, rates, prices and outputs have been based on a medium sized Civil Engineering project of £5-6 million, location

excessively remote, with no abnormal ground conditions that would affect the stated output and consistency of work produced. The rates are optimum rates and assume continuous output with no delays caused by other operations or works.