ABSTRACT

The state-of-practice method to produce formal,

good-quality work instructions for a particular

construction activity consists in a person or group:

(i) selecting the proper design information from the

project’s set of construction drawings or product

models; (ii) establishing the best practice (con-

struction steps and equipment and tools needed)

to perform the respective construction activity;

and finally, (iii) deciding on a format to commu-

nicate this information to the laborers and putting

the selected design and construction information

into that format. This method presents three main

challenges:

− Effort: from our observations, it takes between 1

and 2 hours to produce a good work instruction.

− Error proneness: producing good instructions