Equip erection 6,300 55.0 346 12,600 11.5 145 Field erect. tanks 2,000 (I) 4,000 6.50 (I) Piping 31,000 50.0 1,550 62,000 6.50 403 Instrumentation 9,200 48.0 442 18,400 4.50 83 Electrical 10,100 48.0 486 20,200 4.50 91 Site preparation 1,100 (1) 2,200 1.50 (1) Fire protection 1,500 (I) 3,000 1.50 (I) Concrete 10,000 (I) 20,000 1.50 (I) Structural steel 4,000 52.0 208 8,000 8.50 68 Buildings 4,100 (I) 8,200 1.50 (1) Insulation 5,300 (I) 10,600 1.50 (I) Paint 500 (1) 1,000 1.50 (1)

Total Labor Subcont. 85,100 3,032 172,000 790

Note (I) Cost of labor included in subcontract in N.5.