ABSTRACT

Health and safety Produce health and safety file including preliminary meeting and subsequent progress meetings with external planning officer in connection with health and safety; project value £35,000 - 8.00 244.00 - - nr 244.00 £75,000 - 12.00 366.00 - - nr 366.00 £100,000 - 16.00 488.00 - - nr 488.00 £200,000 to £500,000 - 40.00 1220.00 - - nr 1220.00

Maintain health and safety file for project duration; project value £35,000 - 4.00 122.00 - - week 122.00 £75,000 - 4.00 122.00 - - week 122.00 £100,000 - 8.00 244.00 - - week 244.00 £200,000 to £500,000 - 8.00 244.00 - - week 244.00

Produce written risk assessments on all areas of operations within the scope of works of the contract; project value £35,000 - 2.00 61.00 - - week 61.00 £75,000 - 3.00 91.50 - - week 91.50 £100,000 - 5.00 152.50 - - week 152.50 £200,000 to £500,000 - 8.00 244.00 - - week 244.00

Produce COSHH assessments on all substances to be used in connection with the contract; project value £35,000 - 1.50 45.75 - - nr 45.75 £75,000 - 2.00 61.00 - - nr 61.00 £100,000 - 3.00 91.50 - - nr 91.50 £200,000 to £500,000 - 3.00 91.50 - - nr 91.50

Method statements Provide detailed method statements on all aspects of the works; project value £30,000 - 2.50 76.25 - - nr 76.25 £50,000 - 3.50 106.75 - - nr 106.75 £75,000 - 4.00 122.00 - - nr 122.00 £100,000 - 5.00 152.50 - - nr 152.50 £200,000 - 6.00 183.00 - - nr 183.00

PC Labour Labour Plant Material Excluding site overheads and profit £ hours £ £ £ rate £

A30 EMPLOYERS REQUIREMENTS: TENDERING/SUBLETTING/SUPPLY

Tendering costs for an employed estimator for the acquisition of a landscape main or subcontract; inclusive of measurement, sourcing of materials, and suppliers, cost and area calculations, pre and post tender meetings, bid compliance method statements and submission documents Remeasureable contract from prepared bills; contract value £25,000 - - - - - nr 180.00 £50,000 - - - - - nr 300.00 £100,000 - - - - - nr 720.00 £200,000 - - - - - nr 1200.00 £500,000 - - - - - nr 1560.00 £1,000,000 - - - - - nr 2400.00

Lump sum contract from specifications and drawings only; contract value £25,000 - - - - - nr 480.00 £50,000 - - - - - nr 600.00 £100,000 - - - - - nr 1200.00 £200,000 - - - - - nr 2160.00 £500,000 - - - - - nr 3000.00 £1,000,000 - - - - - nr 4800.00

Material costs for tendering Drawing and plan printing and distribution costs; plans issued by employer on CD; project value £30,000 - - - - 19.00 nr - £30,000 to £80,000 - - - - 47.50 nr - £80,000 to £150,000 - - - - 95.00 nr - £150,000 to £300,000 - - - - 133.00 nr - £300,000 to £1,000,000 - - - - 228.00 nr -

A32 EMPLOYERS REQUIREMENTS: MANAGEMENT OF THE WORKS

Programmes Allow for production of works programmes prior to the start of the works; project value £30,000 - 3.00 91.50 - - nr 91.50 £50,000 - 6.00 183.00 - - nr 183.00 £75,000 - 8.00 244.00 - - nr 244.00 £100,000 - 10.00 305.00 - - nr 305.00 £200,000 - 14.00 427.00 - - nr 427.00

Allow for updating the works programme during the course of the works; project value £30,000 - 1.00 30.50 - - nr 30.50 £50,000 - 1.50 45.75 - - nr 45.75 £75,000 - 2.00 61.00 - - nr 61.00 £100,000 - 3.00 91.50 - - nr 91.50 £200,000 - 5.00 152.50 - - nr 152.50

PC Labour Labour Plant Material Excluding site overheads and profit £ hours £ £ £ rate £

A32 EMPLOYERS REQUIREMENTS: MANAGEMENT OF THE WORKS - cont'd

Setting out Setting out for external works operations comprising hard and soft works elements; placing of pegs and string lines to Landscape Architect's drawings; surveying levels and placing level pegs; obtaining approval from the Landscape Architect to commence works; areas of entire site 1,000 m2 - 5.00 91.25 - 6.00 nr 97.25 2,500 m2 - 8.00 146.00 - 12.00 nr 158.00 5,000 m2 - 8.00 146.00 - 12.00 nr 158.00 10,000 m2 - 32.00 584.00 - 30.00 nr 614.00

A34 SECURITY/SAFETY/PROTECTION

Temorary security fence; HSS Hire; mesh framed unclimbable fencing; including precast concrete supports and couplings Weekly hire; 2.85 x 2.00 m high weekly hire rate - - - 1.28 - m 1.28 erection of fencing; labour only - 0.10 1.82 - - m 1.82 removal of fencing loading to collection vehicle - 0.07 1.22 - - m 1.22 delivery charge - - - 0.80 - m 0.80 return haulage charge - - - 0.60 - m 0.60

A41 CONTRACTORS GENERAL COST ITEMS: SITE ACCOMODATION

General The following items are instances of the commonly found preliminary costs associated with external works contracts. The assumption is made that the external works contractor is subcontracted to a main contractor.