ABSTRACT

Prices generally are for beams "straight or curved exceeding 120m radius", for work to a tighter radius 50 - 120 m radius Add 15 % not exceeding 50 m radius Add 40 % Untensioned beams single sided corrugated beam 0.07 4.65 1.42 18.25 m 24.32 double sided corrugated beam 0.22 14.62 4.47 36.47 m 55.56 single sided open box beam 0.07 4.65 1.42 37.02 m 43.09 single sided double rail open box beam 0.22 14.62 4.47 74.03 m 93.12 double height open box beam 0.24 15.95 4.88 76.34 m 97.17

Tensioned beams single sided corrugated beam 0.10 6.65 2.03 19.28 m 27.96 double sided corrugated beam 0.12 7.97 2.44 39.75 m 50.17

Long driven post for single sided tensioned corrugated beam 0.06 3.65 1.12 43.22 nr 47.99 for double sided tensioned corrugated beam 0.06 3.65 1.12 43.22 nr 47.99 for single sided open box beam 0.06 3.65 1.12 43.22 nr 47.99 for double sided open box beam 0.06 3.65 1.12 43.22 nr 47.99 for double height open box beam 0.06 3.65 1.12 43.22 nr 47.99

Short post for setting in concrete or socket for single sided tensioned corrugated beam 0.06 3.99 1.22 16.66 nr 21.87 for double sided tensioned corrugated beam 0.06 3.99 1.22 16.97 nr 22.18 for single sided open box beam 0.06 3.99 1.22 20.23 nr 25.44 for double sided open box beam 0.06 3.99 1.22 24.11 nr 29.32

Mounting bracket fixed to structure for single sided open box beam 0.16 10.63 3.25 64.94 nr 78.83

Terminal section for untensioned single sided corrugated beam 0.71 47.18 14.44 467.50 nr 529.12 for untensioned double sided corrugated beam 1.25 83.07 25.42 495.00 nr 603.48 for untensioned single sided open box beam 1.01 67.12 20.54 500.50 nr 588.16 for untensioned double sided open box beam 1.78 118.29 36.19 841.50 nr 995.98 for tensioned single sided corrugated beam 0.96 63.80 19.52 326.15 nr 409.46 for tensioned double sided corrugated beam 1.70 112.97 34.56 499.13 nr 646.66

Full height anchorage for single sided tensioned corrugated beam 3.95 262.50 80.31 720.77 nr 1063.58 for double sided tensioned corrugated beam 4.35 289.08 88.44 840.40 nr 1217.92 for single sided open box beam 3.80 252.53 77.26 620.95 nr 950.73 for double sided open box beam 4.20 279.11 85.39 731.50 nr 1096.00

Expansion joint anchorage for single sided open box beam 4.52 300.37 91.90 1279.85 nr 1672.12 for double sided open box beam 5.15 342.24 104.70 1550.45 nr 1997.40

Type 048 connection to bridge parapet for single sided open box beam 0.70 46.52 14.23 171.25 nr 232.00

Connection piece for single sided open box beam to single sided corrugated beam 0.78 51.83 15.86 168.03 nr 235.72 Standard concrete foundation for post for corrugated beam 0.23 15.28 4.59 6.76 nr 26.64 for post for open box beam 0.23 15.28 4.67 8.43 nr 28.38

Concrete foundation Type 1 spanning filter drain for post for corrugated beam 0.25 16.61 5.08 11.93 nr 33.62 for post for open box beam 0.25 16.61 5.08 10.56 nr 32.25

Standard socketed foundation for post for open box beam 0.30 19.94 6.10 10.19 nr 36.23

Item Gang Labour Plant Material Unit Total hours £ £ £ rate £

CONCRETE SAFETY BARRIERS

Permanent vertical concrete safety barrier; TRL Design - DfT Approved Intermediate units Type V01 & V02; 3 m long straight or curved exceeding 50 m radius 0.16 10.63 3.25 413.30 nr 427.19 curved not exceeding 50 m radius 0.20 13.29 4.07 413.30 nr 430.66

Make up units Type V05 & V06; 1 m long straight or curved exceeding 50 m radius 0.30 19.94 6.10 522.22 nr 548.25

Termination units Type V03 & V04; 3 m long 0.50 33.23 10.17 512.58 nr 555.97 Transition to single sided open box beam unit Type V08 & V09; 1.5 m long 0.37 24.59 7.52 609.38 nr 641.49 Transition to rectangular hollow section beam unit Type V10, V11 & V12; 1.5 m long 0.37 24.59 7.52 524.68 nr 556.79 Transition to double sided open box beam; 1.5 m long unit Type V07 0.37 24.59 7.52 586.28 nr 618.39 Anchor plate sets ( normally two plates per first and last three units in any run) 0.15 9.97 6.07 40.61 nr 56.65

Temporary concrete safety barrier; TRL Design - DfT Approved Intermediate units Type V28; 3 m long straight or curved exceeding 50 m radius 0.16 10.63 3.25 368.92 nr 382.80 curved not exceeding 50 m radius 0.20 13.29 4.07 368.92 nr 386.28

Termination units Type V29; 3 m long 0.50 33.23 10.17 413.47 nr 456.86

WIRE ROPE SAFETY FENCES

Brifen wire rope safety fencing DfT approved; based on 600 m lengths; 4 rope system; posts at 2.40 m general spacings. Wire rope 0.03 1.99 0.61 13.92 m 16.52 Long driven line posts 0.05 3.32 1.02 25.70 nr 30.04 Long driven deflection posts 0.05 3.32 1.02 25.70 nr 30.04 Long driven height restraining posts 0.05 3.32 1.02 25.70 nr 30.04 Short line post for setting in concrete or socket 0.06 3.99 1.22 23.78 nr 28.99 Short deflection post for setting in concrete or socket 0.06 3.99 1.22 23.78 nr 28.99 Short height restraining post for setting in concrete or socket 0.06 3.99 1.22 23.78 nr 28.99 Fixed height surface mounted post fixed to structure or foundation 0.09 5.98 1.83 27.00 nr 34.81 Standard intermediate anchorage 2.00 132.91 40.66 312.00 nr 485.57 Standard end anchorage 2.00 132.91 40.66 112.46 nr 286.04 In situ standard concrete foundation for post 0.23 15.28 4.67 8.03 nr 27.99 In situ standard socketed foundation for post 0.33 21.93 6.71 8.03 nr 36.67 Concrete foundation Type 1 spanning filter drain for post 0.37 24.59 7.52 9.65 nr 41.76

Item Gang Labour Plant Material Unit Total hours £ £ £ rate £

VEHICLE PARAPETS

The heights of the follow parapets are in accordance with the Standard Designs and DfT requirements. The rates include for all anchorages and fixings and in the case of steel, galvanising at works and painting four coat paint system on site together with etching the galvanised surface as necessary.