Goods lifts hoist nr 9690.00 to 34520.00

Electric heavy duty goods lifts 500 kg 2 - 3 levels nr 3750.00 to 51680.00 1000 kg; 2 - 3 levels nr 47670.00 to 64825.00 1500 kg; 3 levels nr 112500.00 to 134000.00 2000 kg; 2 levels nr 112500.00 to 134100.00 2000 kg; 3 levels nr 134100.00 to 155700.00 3000 kg; 2 levels nr 121000.00 to 144800.00 3000 kg; 3 levels nr 151000.00 to 178430.00

Oil hydraulic heavy duty goods lifts 500 kg; 3 levels nr 112500.00 to 134100.00 1000 kg; 3 levels nr 118500.00 to 140340.00 2000 kg; 3 levels nr 138100.00 to 159500.00

Dock levellers dock levellers nr 11850.00 to 28400.00 dock levellers and canopy nr 17050.00 to 39200.00

PROTECTIVE, COMMUNICATION AND SPECIAL INSTALLATIONS

Based upon gross internal area serviced Fire fighting/protective installations smoke detectors, alarms and controls m2 4.10 to 10.25 hosereels, dry risers and extinguishers m2 6.35 to 15.25

Sprinkler installations single level sprinkler systems, alarms and smoke detectors; low hazard m2 15.04 to 22.84 single level sprinkler systems, alarms and smoke detectors; ordinary hazard m2 21.61 to 30.07 double level sprinkler systems, alarms and smoke detectors; high hazard m2 32.30 to 41.21

Lightning protection m2 0.81 to 3.19 Security/communication installations security alarm system m2 2.27 to 3.29 telephone system m2 1.24 to 2.72 public address, television ariel and clocks m2 3.19 to 5.46 closed-circuit television and public address system m2 5.01 to 6.02

BUILDERS' WORK IN CONNECTION WITH SERVICES

General builders work to mains supplies; lighting and power to landlords areas m2 2.34 to 6.59 central heating and electrical installation m2 4.68 to 17.42 central heating; electrical and lift installations m2 6.73 to 19.32 air-conditioning m2 17.28 to 26.79 air-conditioning and electrical installation m2 19.32 to 28.40 air-conditioning; electrical and lift installations m2 21.67 to 31.77

General builders work; including allowance for plant rooms; to central heating and electrical installations m2 30.60 to 38.65 central heating, electrical and lift installations m2 38.65 to 47.87 air-conditioning m2 54.61 to 63.54 air-conditioning and electrical installation m2 70.13 to 76.86 air-conditioning; electrical and lift installations m2 86.38 to 86.38