ABSTRACT
Soil and waste Total Cost Item 180000.00 Cost/m² m² 7.20
Condensate Total Cost Item 34000.00 Cost/m² m² 1.35
5D Water Installations Hot and cold water services Total Cost Item 410000.00 Cost/m² m² 16.30
5F Space Heating and Air Treatment LTHW Heating system Total Cost Item 1800000.00 Cost/m² m² 72.00
Chilled water system Total Cost Item 1690000.00 Cost/m² m² 68.00
Supply and extract air conditioning system Total Cost Item 2450000.00 Cost/m² m² 98.00
Allowance for services to communications rooms Total Cost Item 225000.00 Cost/m² m² 9.05
£
5G Ventilating Services Mechanical ventilation to baggage handling and plantrooms Total Cost Item 560000.00 Cost/m² m² 22.50
Toilet extract ventilation Total Cost Item 200000.00 Cost/m² m² 8.15
Smoke extract installation Total Cost Item 225000.00 Cost/m² m² 9.05
Kitchen extract system Total Cost Item 67000.00 Cost/m² m² 2.70
5H Electrical Installation HV/LV Switchgear Total Cost Item 1500000.00 Cost/m² m² 60.00
Standby generator Total Cost Item 920000.00 Cost/m² m² 37.00
Mains and sub mains installation Total Cost Item 1040000.00 Cost/m² m² 41.50
Small power installation Total Cost Item 345000.00 Cost/m² m² 13.80
Lighting and luminaires Total Cost Item 2260000.00 Cost/m² m² 90.00
Emergency lighting installation Total Cost Item 275000.00 Cost/m² m² 11.00
Power to mechanical services Total Cost Item 160000.00 Cost/m² m² 6.45
5I Gas Installation Total Cost Item 46000.00 Cost/m² m² 1.80
£
AIRPORT TERMINAL BUILDING – cont
Cost Summary – cont
5K Protective Installation Lightning protection Total Cost Item 67000.00 Cost/m² m² 2.70
Earthing and bonding Total Cost Item 90000.00 Cost/m² m² 3.60
Sprinkler installation Total Cost Item 790000.00 Cost/m² m² 31.50
Dry riser and hosereel installations Total Cost Item 160000.00 Cost/m² m² 6.30
Fire suppression installation to communications room Total Cost Item 67000.00 Cost/m² m² 2.70
5L Communications Installations Fire and smoke detection and alarm system Total Cost Item 690000.00 Cost/m² m² 27.50
Voice/public address system Total Cost Item 460000.00 Cost/m² m² 18.40
Intruder detection Total Cost Item 230000.00 Cost/m² m² 9.20
Security, CCTV and access control Total Cost Item 810000.00 Cost/m² m² 32.00
Wireways for telephones, data and structure cable Total Cost Item 345000.00 Cost/m² m² 13.80
Structured cable installation Total Cost Item 810000.00 Cost/m² m² 32.00
Flight information display system Total Cost Item 580000.00 Cost/m² m² 23.00
£
5M Special Installations BMS Installation Total Cost Item 1240000.00 Cost/m² m² 49.50
Summary Total £ 20930000.00 Cost/m² £ 840.00
£
SHOPPING MALL (TENANT’S FIT OUT EXCLUDED)
Natural ventilation shopping mall with approximately 33,000m² two storey retail area and a 13,000m² above ground, mechanically ventilated, covered car park, situated in a town centre in South East England.