ABSTRACT

Soil and waste Total Cost Item 180000.00 Cost/m² m² 7.20

Condensate Total Cost Item 34000.00 Cost/m² m² 1.35

5D Water Installations Hot and cold water services Total Cost Item 410000.00 Cost/m² m² 16.30

5F Space Heating and Air Treatment LTHW Heating system Total Cost Item 1800000.00 Cost/m² m² 72.00

Chilled water system Total Cost Item 1690000.00 Cost/m² m² 68.00

Supply and extract air conditioning system Total Cost Item 2450000.00 Cost/m² m² 98.00

Allowance for services to communications rooms Total Cost Item 225000.00 Cost/m² m² 9.05

£

5G Ventilating Services Mechanical ventilation to baggage handling and plantrooms Total Cost Item 560000.00 Cost/m² m² 22.50

Toilet extract ventilation Total Cost Item 200000.00 Cost/m² m² 8.15

Smoke extract installation Total Cost Item 225000.00 Cost/m² m² 9.05

Kitchen extract system Total Cost Item 67000.00 Cost/m² m² 2.70

5H Electrical Installation HV/LV Switchgear Total Cost Item 1500000.00 Cost/m² m² 60.00

Standby generator Total Cost Item 920000.00 Cost/m² m² 37.00

Mains and sub mains installation Total Cost Item 1040000.00 Cost/m² m² 41.50

Small power installation Total Cost Item 345000.00 Cost/m² m² 13.80

Lighting and luminaires Total Cost Item 2260000.00 Cost/m² m² 90.00

Emergency lighting installation Total Cost Item 275000.00 Cost/m² m² 11.00

Power to mechanical services Total Cost Item 160000.00 Cost/m² m² 6.45

5I Gas Installation Total Cost Item 46000.00 Cost/m² m² 1.80

£

AIRPORT TERMINAL BUILDING – cont

Cost Summary – cont

5K Protective Installation Lightning protection Total Cost Item 67000.00 Cost/m² m² 2.70

Earthing and bonding Total Cost Item 90000.00 Cost/m² m² 3.60

Sprinkler installation Total Cost Item 790000.00 Cost/m² m² 31.50

Dry riser and hosereel installations Total Cost Item 160000.00 Cost/m² m² 6.30

Fire suppression installation to communications room Total Cost Item 67000.00 Cost/m² m² 2.70

5L Communications Installations Fire and smoke detection and alarm system Total Cost Item 690000.00 Cost/m² m² 27.50

Voice/public address system Total Cost Item 460000.00 Cost/m² m² 18.40

Intruder detection Total Cost Item 230000.00 Cost/m² m² 9.20

Security, CCTV and access control Total Cost Item 810000.00 Cost/m² m² 32.00

Wireways for telephones, data and structure cable Total Cost Item 345000.00 Cost/m² m² 13.80

Structured cable installation Total Cost Item 810000.00 Cost/m² m² 32.00

Flight information display system Total Cost Item 580000.00 Cost/m² m² 23.00

£

5M Special Installations BMS Installation Total Cost Item 1240000.00 Cost/m² m² 49.50

Summary Total £ 20930000.00 Cost/m² £ 840.00

£

SHOPPING MALL (TENANT’S FIT OUT EXCLUDED)

Natural ventilation shopping mall with approximately 33,000m² two storey retail area and a 13,000m² above ground, mechanically ventilated, covered car park, situated in a town centre in South East England.