The first case study highlighted the costs in time and effort to pursue a contract dispute through the courts. Some of the key aspects of the case include the following points. • With CCT, there is the potential for contract disputes. • Arbitrating and litigating contractual disputes involves much work
and money. • At Plymouth, the client and contractor took opposite interpretations
of the termination procedure, where there had been performance failure.