IRON PIPES – cont’d Cast iron pipes to BS 437 plain ended pipe with "Timesaver" mechanical coupling joints; excavation and supports, backfilling – cont’d 100 mm pipes; in trenches, depth not in trenches 0.13 5.90 0.24 28.85 m 34.99 ne 1.50 m deep 0.21 14.64 10.24 28.85 m 53.73 1.50 - 2.00 m deep 0.23 16.04 11.30 28.85 m 56.19 2.00 - 2.50 m deep 0.30 20.92 14.81 28.85 m 64.58 2.50 - 3.00 m deep 0.37 25.80 18.41 28.85 m 73.06 3.00 - 3.50 m deep 0.48 33.47 24.07 28.85 m 86.39 3.50 - 4.00 m deep 0.60 41.84 30.37 28.85 m 101.05 4.00 - 4.50 m deep 0.75 52.30 38.38 28.85 m 119.53 4.50 - 5.00 m deep 0.95 66.24 49.50 28.85 m 144.59 5.00 - 5.50 m deep 1.22 85.07 65.51 28.85 m 179.42 Extra for bend; 87.5 degree 0.38 26.50 1.75 74.65 nr 102.89 Extra for bend; 45 degree 0.38 26.50 1.75 49.06 nr 77.30 Extra for bend; long radius 0.38 26.50 1.75 74.65 nr 102.89 Extra for single junction; equal 0.59 41.14 2.88 105.43 nr 149.44 Extra for double junction; equal 0.80 55.78 4.59 137.36 nr 197.73 Extra for taper reducer 0.40 27.89 2.88 63.38 nr 94.15 150 mm pipes; in trenches, depth not in trenches 0.14 6.35 0.24 49.48 m 56.07 ne 1.50 m deep 0.24 16.73 11.69 49.48 m 77.91 1.50 - 2.00 m deep 0.28 19.52 13.77 49.48 m 82.77 2.00 - 2.50 m deep 0.34 23.71 16.79 49.48 m 89.98 2.50 - 3.00 m deep 0.40 27.89 19.89 49.48 m 97.26 3.00 - 3.50 m deep 0.54 37.65 27.09 49.48 m 114.22 3.50 - 4.00 m deep 0.61 42.53 30.88 49.48 m 122.89 4.00 - 4.50 m deep 0.79 55.08 40.43 49.48 m 144.99 4.50 - 5.00 m deep 1.05 73.21 54.72 49.48 m 177.41 5.00 - 5.50 m deep 1.32 92.04 70.86 49.48 m 212.38 Extra for bend; 87.5 degree 0.56 39.05 2.30 106.03 nr 147.37 Extra for bend; 45 degree 0.56 39.05 2.30 66.55 nr 107.89 Extra for bend; long radius 0.56 39.05 2.30 136.46 nr 177.80 Extra for single junction; equal 0.88 61.36 4.59 205.77 nr 271.72 Extra for taper reducer 0.56 39.05 4.59 125.01 nr 168.64 225 mm pipes; in trenches, depth not in trenches 0.15 6.81 0.24 142.90 m 149.95 ne 1.50 m deep 0.25 17.43 12.19 142.90 m 172.52 1.50 - 2.00 m deep 0.30 20.92 14.77 142.90 m 178.58 2.00 - 2.50 m deep 0.35 24.40 17.26 142.90 m 184.56 2.50 - 3.00 m deep 0.41 28.59 20.40 142.90 m 191.88 3.00 - 3.50 m deep 0.54 37.65 27.09 142.90 m 207.64 3.50 - 4.00 m deep 0.61 42.53 30.88 142.90 m 216.31 4.00 - 4.50 m deep 0.77 53.69 39.42 142.90 m 236.01 4.50 - 5.00 m deep 1.02 71.12 53.17 142.90 m 267.19 5.00 - 5.50 m deep 1.30 90.64 69.80 142.90 m 303.34 Extra for bend; 87.5 degree 0.77 53.69 2.30 288.61 nr 344.59 Extra for bend; 45 degree 0.77 53.69 2.30 288.61 nr 344.59 Extra for single junction; equal 1.21 84.37 5.17 485.56 nr 575.10 Extra for taper reducer 0.77 53.69 5.17 197.41 nr 256.27

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Ductile iron pipes to BS 4772, Tyton joints; excavation and supports, backfilling 100 mm pipes; in trenches, depth not in trenches 0.10 4.54 0.24 32.35 m 37.13 ne 1.50 m deep 0.19 13.25 8.79 32.35 m 54.39 1.50 - 2.00 m deep 0.20 13.95 9.83 32.35 m 56.13 2.00 - 2.50 m deep 0.26 18.13 12.84 32.35 m 63.32 2.50 - 3.00 m deep 0.32 22.31 15.91 32.35 m 70.58 3.00 - 3.50 m deep 0.42 29.29 21.07 32.35 m 82.71 3.50 - 4.00 m deep 0.53 36.96 26.83 32.35 m 96.13 4.00 - 4.50 m deep 0.66 46.02 33.80 32.35 m 112.16 4.50 - 5.00 m deep 0.84 58.57 43.77 32.35 m 134.69 5.00 - 5.50 m deep 1.08 75.30 57.98 32.35 m 165.63 Extra for bend; 90 degree 0.38 26.50 13.17 71.44 nr 111.11 Extra for single junction; equal 0.60 41.84 3.46 106.39 nr 151.69 150 mm pipes; in trenches, depth not in trenches 0.11 4.99 0.24 40.71 m 45.94 ne 1.50 m deep 0.21 14.64 10.24 40.71 m 65.59 1.50 - 2.00 m deep 0.25 17.43 12.30 40.71 m 70.44 2.00 - 2.50 m deep 0.30 20.92 14.81 40.71 m 76.44 2.50 - 3.00 m deep 0.37 25.80 18.41 40.71 m 84.92 3.00 - 3.50 m deep 0.49 34.17 24.58 40.71 m 99.45 3.50 - 4.00 m deep 0.55 38.35 27.83 40.71 m 106.89 4.00 - 4.50 m deep 0.72 50.20 36.85 40.71 m 127.77 4.50 - 5.00 m deep 0.94 65.54 49.00 40.71 m 155.25 5.00 - 5.50 m deep 1.19 82.97 63.87 40.71 m 187.56 Extra for bend; 90 degree 0.57 39.74 2.30 154.03 nr 196.07 Extra for single junction; equal 0.88 61.36 4.59 212.52 nr 278.47 250 mm pipes; in trenches, depth not in trenches 0.16 7.26 0.24 72.23 m 79.73 ne 1.50 m deep 0.24 16.73 11.69 72.23 m 100.66 1.50 - 2.00 m deep 0.30 20.92 14.77 72.23 m 107.91 2.00 - 2.50 m deep 0.35 24.40 17.27 72.23 m 113.90 2.50 - 3.00 m deep 0.42 29.29 20.90 72.23 m 122.41 3.00 - 3.50 m deep 0.56 39.05 28.08 72.23 m 139.35 3.50 - 4.00 m deep 0.64 44.63 32.39 72.23 m 149.24 4.00 - 4.50 m deep 0.81 56.48 41.47 72.23 m 170.17 4.50 - 5.00 m deep 1.02 71.12 53.17 72.23 m 196.52 5.00 - 5.50 m deep 1.27 88.55 68.17 72.23 m 228.95 Extra for bend; 90 degree 0.96 66.94 3.46 444.65 nr 515.05 Extra for single junction; equal 1.32 92.04 5.75 586.47 nr 684.27 400 mm pipes; in trenches, depth not in trenches 0.24 10.89 0.52 135.37 m 146.78 ne 1.50 m deep 0.33 23.01 16.09 135.37 m 174.47 1.50 - 2.00 m deep 0.43 29.98 21.14 135.37 m 186.49 2.00 - 2.50 m deep 0.48 33.47 23.68 135.37 m 192.52 2.50 - 3.00 m deep 0.57 39.74 28.36 135.37 m 203.47 3.00 - 3.50 m deep 0.71 49.51 35.59 135.37 m 220.47 3.50 - 4.00 m deep 0.91 63.45 46.05 135.37 m 244.87 4.00 - 4.50 m deep 1.16 80.88 59.38 135.37 m 275.63 4.50 - 5.00 m deep 1.47 102.50 76.59 135.37 m 314.47 5.00 - 5.50 m deep 1.77 123.42 95.02 135.37 m 353.81

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

IRON PIPES – cont’d Ductile iron pipes to BS 4772, Tyton joints; excavation and supports, backfilling – cont’d 600 mm pipes; in trenches, depth not in trenches 0.34 15.43 0.71 243.32 m 259.46 ne 1.50 m deep 0.47 32.77 22.89 243.32 m 298.98 1.50 - 2.00 m deep 0.55 38.35 27.04 243.32 m 308.70 2.00 - 2.50 m deep 0.66 46.02 32.57 243.32 m 321.91 2.50 - 3.00 m deep 0.78 54.39 38.81 243.32 m 336.51 3.00 - 3.50 m deep 0.89 62.06 44.63 243.32 m 350.01 3.50 - 4.00 m deep 1.09 76.00 55.17 243.32 m 374.49 4.00 - 4.50 m deep 1.37 95.53 70.13 243.32 m 408.98 4.50 - 5.00 m deep 1.70 118.54 88.60 243.32 m 450.46 5.00 - 5.50 m deep 2.03 141.55 108.97 243.32 m 493.83 STEEL PIPES Carbon steel pipes to BS EN 10126; welded joints; (for protection and lining refer to manufacturer); excavation and supports, backfilling 100 mm pipes; in trenches, depth not in trenches 0.07 3.18 0.33 26.88 m 30.38 ne 1.50 m deep 0.15 10.46 7.30 26.88 m 44.64 1.50 - 2.00 m deep 0.17 11.85 8.37 26.88 m 47.10 2.00 - 2.50 m deep 0.22 15.34 10.87 26.88 m 53.08 2.50 - 3.00 m deep 0.27 18.83 13.42 26.88 m 59.12 3.00 - 3.50 m deep 0.35 24.40 17.54 26.88 m 68.82 3.50 - 4.00 m deep 0.44 30.68 22.27 26.88 m 79.82 4.00 - 4.50 m deep 0.55 38.35 28.14 26.88 m 93.37 4.50 - 5.00 m deep 0.70 48.81 40.04 26.88 m 115.73 5.00 - 5.50 m deep 0.87 60.66 46.70 26.88 m 134.23 Extra for bend; 45 degrees 0.07 4.88 1.71 11.20 nr 17.79 Extra for bend; 90 degrees 0.07 4.88 1.71 14.15 nr 20.74 Extra for single junction; equal 0.11 7.67 2.88 33.25 nr 43.80 150 mm pipes; in trenches, depth not in trenches 0.07 3.18 0.33 41.41 m 44.91 ne 1.50 m deep 0.17 11.85 8.29 41.41 m 61.55 1.50 - 2.00 m deep 0.20 13.95 9.83 41.41 m 65.19 2.00 - 2.50 m deep 0.24 16.73 11.84 41.41 m 69.98 2.50 - 3.00 m deep 0.29 20.22 14.43 41.41 m 76.06 3.00 - 3.50 m deep 0.39 27.19 19.55 41.41 m 88.15 3.50 - 4.00 m deep 0.44 30.68 22.27 41.41 m 94.36 4.00 - 4.50 m deep 0.57 39.74 29.18 41.41 m 110.34 4.50 - 5.00 m deep 0.72 50.20 41.17 41.41 m 132.78 5.00 - 5.50 m deep 0.90 62.75 48.33 41.41 m 152.49 Extra for bend; 45 degrees 0.09 6.28 2.30 23.53 nr 32.10 Extra for bend; 90 degrees 0.09 6.28 2.30 31.68 nr 40.25 Extra for single junction; equal 0.16 11.16 4.59 58.85 nr 74.60

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

200 mm pipes; in trenches, depth not in trenches 0.09 4.08 7.70 43.79 m 55.57 ne 1.50 m deep 0.18 12.55 8.79 43.79 m 65.12 1.50 - 2.00 m deep 0.21 14.64 10.33 43.79 m 68.76 2.00 - 2.50 m deep 0.25 17.43 12.35 43.79 m 73.56 2.50 - 3.00 m deep 0.30 20.92 14.93 43.79 m 79.64 3.00 - 3.50 m deep 0.40 27.89 20.06 43.79 m 91.73 3.50 - 4.00 m deep 0.46 32.07 23.29 43.79 m 99.16 4.00 - 4.50 m deep 0.59 41.14 30.19 43.79 m 115.12 4.50 - 5.00 m deep 0.74 51.60 38.58 43.79 m 133.96 5.00 - 5.50 m deep 0.92 64.15 49.39 43.79 m 157.32 Extra for bend; 45 degrees 0.12 8.37 2.30 49.73 nr 60.39 Extra for bend; 90 degrees 0.12 8.37 2.30 64.90 nr 75.56 Extra for single junction; equal 0.21 14.64 4.56 113.04 nr 132.24 250 mm pipes; in trenches, depth not in trenches 0.10 4.54 0.49 55.05 m 60.08 ne 1.50 m deep 0.18 12.55 10.34 55.05 m 77.95 1.50 - 2.00 m deep 0.22 15.34 12.60 55.05 m 82.99 2.00 - 2.50 m deep 0.26 18.13 14.76 55.05 m 87.95 2.50 - 3.00 m deep 0.31 21.62 17.77 55.05 m 94.44 3.00 - 3.50 m deep 0.41 28.59 23.52 55.05 m 107.17 3.50 - 4.00 m deep 0.47 32.77 26.92 55.05 m 114.75 4.00 - 4.50 m deep 0.60 41.84 34.22 55.05 m 131.11 4.50 - 5.00 m deep 0.75 52.30 42.88 55.05 m 150.23 5.00 - 5.50 m deep 0.94 65.54 53.76 55.05 m 174.36 Extra for bend; 45 degrees 0.13 9.06 2.30 87.47 nr 98.83 Extra for bend; 90 degrees 0.13 9.06 2.30 115.05 nr 126.41 Extra for single junction; equal 0.23 16.04 4.59 210.73 nr 231.35 300 mm pipes; in trenches, depth not in trenches 0.11 4.99 0.52 63.12 m 68.63 ne 1.50 m deep 0.20 13.95 9.75 63.12 m 86.81 1.50 - 2.00 m deep 0.25 17.43 12.30 63.12 m 92.85 2.00 - 2.50 m deep 0.28 19.52 13.81 63.12 m 96.45 2.50 - 3.00 m deep 0.34 23.71 16.92 63.12 m 103.75 3.00 - 3.50 m deep 0.44 30.68 22.06 63.12 m 115.86 3.50 - 4.00 m deep 0.53 36.96 26.83 63.12 m 126.91 4.00 - 4.50 m deep 0.68 47.41 34.81 63.12 m 145.34 4.50 - 5.00 m deep 0.86 59.97 44.83 63.12 m 167.91 5.00 - 5.50 m deep 1.06 73.91 56.92 63.12 m 193.95 Extra for bend; 45 degrees 0.14 9.76 3.46 116.94 nr 130.16 Extra for bend; 90 degrees 0.14 9.76 3.46 157.44 nr 170.66 Extra for single junction; equal 0.25 17.43 7.47 325.39 nr 350.29

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

POLYVINYL CHLORIDE PIPES Unplasticised pvc perforated pipes; ring seal sockets; excavation and supports, backfilling; 6 m pipe lengths unless stated otherwise 82 mm pipes; in trench, depth not in trenches; 3.00 m pipe lengths 0.06 2.72 0.15 9.22 m 12.09 ne 1.50 m deep; 3.00 m pipe lengths 0.10 6.97 2.83 9.22 m 19.03 1.50 - 2.00 m deep 0.13 9.06 3.74 9.22 m 22.02 2.00 - 2.50 m deep 0.16 11.16 4.62 9.22 m 25.00 2.50 - 3.00 m deep 0.19 13.25 5.56 9.22 m 28.03 3.00 - 3.50 m deep 0.22 15.34 6.54 9.22 m 31.10 3.50 - 4.00 m deep 0.25 17.43 7.54 9.22 m 34.20 4.00 - 4.50 m deep 0.28 19.52 8.61 9.22 m 37.35 4.50 - 5.00 m deep 0.32 22.31 10.13 9.22 m 41.66 5.00 - 5.50 m deep 0.35 24.40 11.63 9.22 m 45.25 110 mm pipes; in trench, depth not in trenches 0.06 2.72 0.07 8.99 m 11.78 ne 1.50 m deep 0.10 6.97 2.83 8.99 m 18.79 1.50 - 2.00 m deep 0.13 9.06 3.74 8.99 m 21.79 2.00 - 2.50 m deep 0.16 11.16 4.62 8.99 m 24.76 2.50 - 3.00 m deep 0.19 13.25 5.56 8.99 m 27.80 3.00 - 3.50 m deep 0.22 15.34 6.54 8.99 m 30.87 3.50 - 4.00 m deep 0.25 17.43 7.54 8.99 m 33.96 4.00 - 4.50 m deep 0.28 19.52 8.61 8.99 m 37.12 4.50 - 5.00 m deep 0.32 22.31 10.13 8.99 m 41.43 5.00 - 5.50 m deep 0.36 25.10 11.97 8.99 m 46.05 160 mm pipes; in trench, depth not in trenches 0.06 2.72 0.15 16.92 m 19.79 ne 1.50 m deep 0.11 7.67 3.11 16.92 m 27.70 1.50 - 2.00 m deep 0.14 9.76 4.03 16.92 m 30.71 2.00 - 2.50 m deep 0.18 12.55 5.20 16.92 m 34.68 2.50 - 3.00 m deep 0.22 15.34 6.45 16.92 m 38.71 3.00 - 3.50 m deep 0.23 16.04 6.83 16.92 m 39.79 3.50 - 4.00 m deep 0.26 18.13 7.85 16.92 m 42.90 4.00 - 4.50 m deep 0.30 20.92 9.23 16.92 m 47.07 4.50 - 5.00 m deep 0.35 24.40 11.08 16.92 m 52.41 5.00 - 5.50 m deep 0.40 27.89 13.29 16.92 m 58.11 Unplasticised pvc pipes; ring seal sockets; excavation and supports, backfilling; 6 m pipe lengths unless stated otherwise 82 mm pipes; in trenches, depth not in trenches; 3.00 m pipe lengths 0.06 2.72 0.30 10.68 m 13.70 ne 1.50 m deep; 3.00 m pipe lengths 0.10 6.97 4.78 10.68 m 22.43 1.50 - 2.00 m deep 0.13 9.06 6.40 10.68 m 26.15 2.00 - 2.50 m deep 0.16 11.16 7.89 10.68 m 29.73 2.50 - 3.00 m deep 0.19 13.25 9.44 10.68 m 33.37 3.00 - 3.50 m deep 0.22 15.34 11.05 10.68 m 37.07 3.50 - 4.00 m deep 0.25 17.43 12.66 10.68 m 40.77 4.00 - 4.50 m deep 0.28 19.52 14.33 10.68 m 44.54 4.50 - 5.00 m deep 0.32 22.31 16.68 10.68 m 49.67 5.00 - 5.50 m deep 0.35 24.40 18.78 10.68 m 53.87 Extra for bend; short radius (socket/spigot) 0.05 3.49 - 14.79 nr 18.27 Extra for branches; equal (socket/spigot) 0.07 4.88 - 22.49 nr 27.37

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

110 mm pipes; in trenches, depth not in trenches 0.06 2.72 0.30 7.43 m 10.44 ne 1.50 m deep 0.10 6.97 4.89 7.43 m 19.29 1.50 - 2.00 m deep 0.13 9.06 6.40 7.43 m 22.89 2.00 - 2.50 m deep 0.16 11.16 7.87 7.43 m 26.45 2.50 - 3.00 m deep 0.19 13.25 9.44 7.43 m 30.12 3.00 - 3.50 m deep 0.22 15.34 11.05 7.43 m 33.81 3.50 - 4.00 m deep 0.25 17.43 12.66 7.43 m 37.52 4.00 - 4.50 m deep 0.28 19.52 14.33 7.43 m 41.28 4.50 - 5.00 m deep 0.32 22.31 16.68 7.43 m 46.41 5.00 - 5.50 m deep 0.36 25.10 19.33 7.43 m 51.85 Extra for bend; short radius (socket/spigot) 0.05 3.49 - 14.96 nr 18.44 Extra for bend; adjustable (socket/spigot) 0.05 3.49 - 28.24 nr 31.73 Extra for reducer 0.05 3.49 - 5.11 nr 8.60 Extra for branches; equal (socket/spigot) 0.07 4.88 - 22.17 nr 27.05 160 mm pipes; in trenches, depth not in trenches 0.06 2.72 0.30 18.30 m 21.31 ne 1.50 m deep 0.11 7.67 5.35 18.30 m 31.32 1.50 - 2.00 m deep 0.14 9.76 6.90 18.30 m 34.96 2.00 - 2.50 m deep 0.18 12.55 8.90 18.30 m 39.75 2.50 - 3.00 m deep 0.22 15.34 10.96 18.30 m 44.59 3.00 - 3.50 m deep 0.23 16.04 11.53 18.30 m 45.86 3.50 - 4.00 m deep 0.26 18.13 13.17 18.30 m 49.60 4.00 - 4.50 m deep 0.30 20.92 15.37 18.30 m 54.58 4.50 - 5.00 m deep 0.35 24.40 18.23 18.30 m 60.93 5.00 - 5.50 m deep 0.40 27.89 21.47 18.30 m 67.66 Extra for bend; short radius (socket/spigot) 0.05 3.49 - 38.37 nr 41.85 Extra for branches; equal (socket/spigot) 0.07 4.88 - 43.23 nr 48.11 225 mm pipes; in trenches, depth not in trenches 0.07 3.18 0.33 16.21 m 19.71 ne 1.50 m deep 0.12 8.37 5.85 16.21 m 30.42 1.50 - 2.00 m deep 0.15 10.46 7.37 16.21 m 34.04 2.00 - 2.50 m deep 0.20 13.95 9.87 16.21 m 40.02 2.50 - 3.00 m deep 0.23 16.04 11.43 16.21 m 43.68 3.00 - 3.50 m deep 0.24 16.73 12.03 16.21 m 44.98 3.50 - 4.00 m deep 0.27 18.83 13.66 16.21 m 48.69 4.00 - 4.50 m deep 0.32 22.31 16.38 16.21 m 54.90 4.50 - 5.00 m deep 0.36 25.10 18.76 16.21 m 60.07 5.00 - 5.50 m deep 0.45 31.38 24.16 16.21 m 71.75 Extra for bend; short radius 45° (double socket) 0.07 4.88 - 58.70 nr 63.58 Extra for branches; equal (all socket) 0.09 6.28 - 137.86 nr 144.14 300 mm pipes; in trenches, depth not in trenches 0.08 3.63 0.38 24.65 m 28.66 ne 1.50 m deep 0.13 9.06 6.34 24.65 m 40.06 1.50 - 2.00 m deep 0.16 11.16 7.87 24.65 m 43.67 2.00 - 2.50 m deep 0.21 14.64 10.37 24.65 m 49.66 2.50 - 3.00 m deep 0.23 16.04 11.43 24.65 m 52.12 3.00 - 3.50 m deep 0.25 17.43 12.54 24.65 m 54.63 3.50 - 4.00 m deep 0.28 19.52 14.17 24.65 m 58.34 4.00 - 4.50 m deep 0.34 23.71 17.42 24.65 m 65.78 4.50 - 5.00 m deep 0.38 26.50 19.82 24.65 m 70.96 5.00 - 5.50 m deep 0.47 32.77 25.22 24.65 m 82.65 Extra for bend; short radius 45° (double socket) 0.07 4.88 - 109.16 nr 114.04 Extra for branches; unequal (all socket) 0.09 6.28 - 318.85 nr 325.13

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

POLYVINYL CHLORIDE PIPES – cont’d Unplasticised pvc pipes; polypropylene couplings; excavation and supports, backfilling; 6 m pipe lengths unless stated otherwise 110 mm pipes; in trenches, depth not in trenches 0.06 2.72 0.30 6.82 m 9.84 ne 1.50 m deep 0.10 6.97 4.89 6.82 m 18.68 1.50 - 2.00 m deep 0.13 9.06 6.40 6.82 m 22.28 2.00 - 2.50 m deep 0.16 11.16 7.89 6.82 m 25.87 2.50 - 3.00 m deep 0.19 13.25 9.44 6.82 m 29.51 3.00 - 3.50 m deep 0.22 15.34 11.05 6.82 m 33.21 3.50 - 4.00 m deep 0.25 17.43 12.66 6.82 m 36.91 4.00 - 4.50 m deep 0.28 19.52 14.33 6.82 m 40.68 4.50 - 5.00 m deep 0.32 22.31 16.68 6.82 m 45.81 5.00 - 5.50 m deep 0.36 25.10 19.33 6.82 m 51.25 160 mm pipes; in trenches, depth not in trenches 0.06 2.72 0.30 22.05 m 25.08 ne 1.50 m deep 0.11 7.67 5.35 22.05 m 35.07 1.50 - 2.00 m deep 0.14 9.76 6.90 22.05 m 38.71 2.00 - 2.50 m deep 0.18 12.55 8.90 22.05 m 43.50 2.50 - 3.00 m deep 0.22 15.34 10.96 22.05 m 48.35 3.00 - 3.50 m deep 0.23 16.04 11.53 22.05 m 49.61 3.50 - 4.00 m deep 0.26 18.13 13.17 22.05 m 53.35 4.00 - 4.50 m deep 0.30 20.92 15.37 22.05 m 58.34 4.50 - 5.00 m deep 0.35 24.40 18.23 22.05 m 64.69 5.00 - 5.50 m deep 0.40 27.89 21.47 22.05 m 71.41 225 mm pipes; in trenches, depth not in trenches 0.07 3.18 0.33 24.10 m 27.60 ne 1.50 m deep 0.12 8.37 5.85 24.10 m 38.31 1.50 - 2.00 m deep 0.15 10.46 7.37 24.10 m 41.92 2.00 - 2.50 m deep 0.20 13.95 9.87 24.10 m 47.91 2.50 - 3.00 m deep 0.23 16.04 11.43 24.10 m 51.56 3.00 - 3.50 m deep 0.24 16.73 12.03 24.10 m 52.86 3.50 - 4.00 m deep 0.27 18.83 13.66 24.10 m 56.58 4.00 - 4.50 m deep 0.32 22.31 16.38 24.10 m 62.79 4.50 - 5.00 m deep 0.36 25.10 18.76 24.10 m 67.96 5.00 - 5.50 m deep 0.45 31.38 24.16 24.10 m 79.64 300 mm pipes; in trenches, depth not in trenches 0.08 3.63 0.38 46.80 m 50.81 ne 1.50 m deep 0.13 9.06 6.34 46.80 m 62.20 1.50 - 2.00 m deep 0.16 11.16 7.87 46.80 m 65.82 2.00 - 2.50 m deep 0.21 14.64 10.37 46.80 m 71.80 2.50 - 3.00 m deep 0.23 16.04 11.43 46.80 m 74.26 3.00 - 3.50 m deep 0.25 17.43 12.54 46.80 m 76.77 3.50 - 4.00 m deep 0.28 19.52 14.17 46.80 m 80.49 4.00 - 4.50 m deep 0.34 23.71 17.42 46.80 m 87.92 4.50 - 5.00 m deep 0.38 26.50 19.82 46.80 m 93.11 5.00 - 5.50 m deep 0.47 32.77 25.22 46.80 m 104.79

Item

Gang hours

Labour £

Plant £

Material £ Unit

Total rate £

Ultrarib unplasticised pvc pipes; ring seal joints; excavation and supports, backfilling 150 mm pipes; in trenches, depth not in trenches 0.13 5.90 0.62 23.67 m 30.20 ne 1.50 m deep 0.16 11.16 7.80 23.67 m 42.63 1.50 - 2.00 m deep 0.19 13.25 9.34 23.67 m 46.26 2.00 - 2.50 m deep 0.22 15.34 10.87 23.67 m 49.89 2.50 - 3.00 m deep 0.24 16.73 11.94 23.67 m 52.34 3.00 - 3.50 m deep 0.24 16.73 12.03 23.67 m 52.44 3.50 - 4.00 m deep 0.27 18.83 13.66 23.67 m 56.16 4.00 - 4.50 m deep 0.32 22.31 16.38 23.67 m 62.37 4.50 - 5.00 m deep 0.36 25.10 18.76 23.67 m 67.54 5.00 - 5.50 m deep 0.45 31.38 24.16 23.67 m 79.22 Extra for bends; short radius (socket/spigot) 0.05 3.49 - 20.97 nr 24.46 Extra for branches; equal (socket/spigot) 0.09 6.28 - 50.71 nr 56.98 225 mm pipes; in trenches, depth not in trenches 0.08 3.63 0.38 26.48 m 30.49 ne 1.50 m deep 0.13 9.06 6.34 26.48 m 41.89 1.50 - 2.00 m deep 0.16 11.16 7.87 26.48 m 45.50 2.00 - 2.50 m deep 0.21 14.64 10.37 26.48 m 51.49 2.50 - 3.00 m deep 0.23 16.04 11.43 26.48 m 53.95 3.00 - 3.50 m deep 0.25 17.43 12.54 26.48 m 56.45 3.50 - 4.00 m deep 0.28 19.52 14.17 26.48 m 60.17 4.00 - 4.50 m deep 0.34 23.71 17.42 26.48 m 67.60 4.50 - 5.00 m deep 0.38 26.50 19.82 26.48 m 72.79 5.00 - 5.50 m deep 0.47 32.77 25.22 26.48 m 84.47 Extra for bends; short radius (socket/spigot) 0.05 3.49 - 84.38 nr 87.87 Extra for branches; equal (socket/spigot) 0.09 6.28 - 168.27 nr 174.54 300 mm pipes; in trenches, depth not in trenches 0.08 3.63 0.38 42.58 m 46.59 ne 1.50 m deep 0.13 9.06 6.34 42.58 m 57.98 1.50 - 2.00 m deep 0.16 11.16 7.87 42.58 m 61.60 2.00 - 2.50 m deep 0.21 14.64 10.37 42.58 m 67.59 2.50 - 3.00 m deep 0.23 16.04 11.43 42.58 m 70.05 3.00 - 3.50 m deep 0.25 17.43 12.54 42.58 m 72.55 3.50 - 4.00 m deep 0.28 19.52 14.17 42.58 m 76.27 4.00 - 4.50 m deep 0.34 23.71 17.42 42.58 m 83.70 4.50 - 5.00 m deep 0.38 26.50 19.82 42.58 m 88.89 5.00 - 5.50 m deep 0.47 32.77 25.22 42.58 m 100.57 EXtra for bends; short radius (socket/spigot) 0.07 4.88 - 153.23 nr 158.11 Extra for branches; equal (socket/spigot) 0.09 6.28 - 288.67 nr 294.94