ABSTRACT

Galvanised steel bracket arm to BSEN40; with 5° uplift 0.5m projection, single arm 0.16 10.22 20.34 35.13 nr 65.69 1.0m projection, single arm 0.19 12.13 13.06 75.09 nr 100.28 1.5m projection, single arm 0.21 10.75 14.20 82.32 nr 107.27 2.0m projection, single arm 0.27 17.24 18.56 99.63 nr 135.43 1.0m projection, double arm 0.29 18.52 19.94 124.59 nr 163.05 2.0m projection, double arm 0.32 20.44 22.00 150.24 nr 192.68

Precast concrete bracket arm to BS EN 40; with 5° uplift 1.0m projection, single arm 0.24 15.33 16.50 145.15 nr 176.98 2.0m projection, single arm 0.32 20.44 22.00 174.16 nr 216.60 1.0m projection, double arm 0.35 22.35 24.06 168.53 nr 214.94 2.0m projection, doube arm 0.37 23.63 25.44 204.81 nr 253.88

Lantern unit with photo-electric control set to switch on at 100 lux; lamps

55W SON (P226); to suit 4m and 5m columns 0.40 25.80 20.90 284.16 nr 330.86 70W SON (P236); to suit 5m and 6m columns 0.40 25.80 20.90 287.15 nr 333.85 250W SON (P426); to suit 8m, 10m and 12m columns 0.50 32.25 26.12 430.72 nr 489.09 Sphere 70W SON; to suit 3m columns (P456) 0.50 32.25 26.12 515.98 nr 574.35 400W SON High pressure sodium; to suit 12m and 15m columns 0.50 32.25 26.12 598.21 nr 656.58

hours £ £ £ rate £

REMOVE FROM STORE AND RE-ERECT ROAD LIGHTING COLUMNS AND BRACKETS AND MASTS

Remove From Store And Re-Erect Road Lighting Columns, Brackets And Wall Mountings Re-erection of galvanized steel road lighting columns with flange plate base; including all control gear, switching, fuses and internal wiring

4.0m nominal height 0.75 38.40 19.46 18.70 nr 76.56 6.0m nominal height 0.80 40.96 20.77 24.46 nr 86.19 8.0m nominal height 0.96 49.15 24.89 30.22 nr 104.26 10.0m nominal height 1.28 65.53 33.21 35.97 nr 134.71 12.0m nominal height 1.44 73.73 37.36 41.73 nr 152.82 15.0m nominal height 1.76 90.11 45.66 50.36 nr 186.13 3.0m cast iron column (pedestrian / landscape area) 0.75 38.40 19.48 15.82 nr 73.70

Re-erection of precast concrete lighting columns with flange plate base; including all control gear, switching, fuses and internal wiring

5.0m nominal height 0.75 38.40 19.46 21.59 nr 79.45 10.0m nominal height 1.28 65.53 33.21 35.97 nr 134.71

Re-erection of galvanized steel bracket arms 0.5m projection, single arm 0.16 10.22 11.00 30.75 nr 51.97 1.0m projection, single arm 0.19 12.13 13.06 30.75 nr 55.94 1.5m projection, single arm 0.21 13.41 14.44 30.75 nr 58.60 2.0m projection, single arm 0.27 17.24 18.56 30.75 nr 66.55 1.0m projection, double arm 0.29 18.52 19.94 30.75 nr 69.21 2.0m projection, double arm 0.32 20.44 22.00 30.75 nr 73.19

Re-erection of precast concrete bracket arms 1.0m projection, single arm 0.24 15.33 16.50 30.75 nr 62.58 2.0m projection, single arm 0.32 20.44 22.00 30.75 nr 73.19 1.0m projection, double arm 0.35 22.35 24.87 30.75 nr 77.97 2.0m projection, double arm 0.37 23.63 24.06 30.75 nr 78.44

Re-installing lantern unit with photo-electric control set to switch on at 100 lux; lamps

55W SON (P226); to suit 4m and 5m columns 0.40 25.80 20.90 – nr 46.70 70W SON (P236); to suit 5m and 6m columns 0.22 14.19 20.90 – nr 35.09 250W SON (P426); to suit 8m, 10m and 12m columns 0.50 32.25 26.12 – nr 58.37 Sphere 70W SON; to suit 3m (P456) 0.50 32.25 26.12 – nr 58.37 400W SON High pressure sodium; to suit 12m and 15m columns 0.50 32.25 26.12 – nr 58.37