Sub-base laying gang 1 ganger/chargehand (skill rate 4) - 14.28 - - - - 1 skilled operative (skill rate 4) - 13.32 - - - - 2 unskilled operatives (general) - 24.88 - - - - 1 plant operator (skill rate 2) - 18.05 - - - - 1 plant operator (skill rate 3) - 16.19 - - - - Total Gang Rate / Hour £ 86.72 - - - -

Flexible paving gang 1 ganger/chargehand (skill rate 4) - 14.28 - - - - 2 skilled operatives (skill rate 4) - 26.64 - - - - 4 unskilled operatives (general) - 49.76 - - - - 4 plant operators (skill rate 3) - 64.76 - - - - Total Gang Rate / Hour £ 155.44 - - - -

Concrete paving gang 1 ganger/chargehand (skill rate 4) - 14.28 - - - - 2 skilled operatives (skill rate 4) - 26.64 - - - - 4 unskilled operatives (general) - 49.76 - - - - 1 plant operator (skill rate 2) - 18.05 - - - - 1 plant operator (skill rate 3) - 16.19 - - - - Total Rate / Hour £ 124.92 - - - -

Road surface spraying gang 1 plant operator (skill rate 3) - 16.19 - - - - Total Gang Cost / Hour £ 16.19 - - - -

Road chippings gang 1 ganger/chargehand (skill rate 4) - 50% of time - 7.14 - - - - 1 skilled operative (skill rate 4) - 13.32 - - - - 2 unskilled operatives (general) - 24.88 - - - - 3 plant operators (skill rate 3) - 48.57 - - - - Total Gang Rate / Hour £ 93.91 - - - -

Cutting slabs gang 1 unskilled operative (general) - 12.44 - - - - Total Gang Rate / Hour £ 12.44 - - - -

Concrete filled joints gang 1 ganger/chargehand - 50% of time - 7.14 - - - - 1 skilled operative (skill rate 4) - 13.32 - - - - 2 unskilled operatives (general) - 24.88 - - - - Total Gang Rate / Hour £ 45.34 - - - -

Milling gang 1 ganger/chargehand (skill rate 4) 2.00 14.28 - - - - 2 skilled operatives (skill rate 4) 2.00 26.64 - - - - 4 unskilled operatives (general) 4.00 49.76 - - - - 1 plant operator (skill rate 2) 1.00 18.05 - - - - 1 plant operator (skill rate 3) 1.00 16.19 - - - - Total Gang Rate / Hour 10.00 124.92 - - - -

Item Gang Labour Plant Material Unit Total hours £ £ £ rate £

RESOURCES - LABOUR - cont'd

Rake and compact planed material gang 1 ganger/chargehand (skill rate 4) - 14.28 - - - - 1 skilled operative (skill rate 4) - 13.32 - - - - 3 unskilled operatives (general) - 37.32 - - - - 1 plant operator (skill rate 4) - 14.56 - - - - 1 plant operator (skill rate 3) - 16.19 - - - - Total Gang Rate / Hour £ 95.67 - - - -

RESOURCES - PLANT

Sub-base laying 93 kW motor grader - - 28.84 - - - 0.8 m3 tractor loader - - 23.05 - - - 6 t towed vibratory roller - - 11.51 - - - Total Gang Rate / Hour - £ 63.40 - - -

Flexible paving 2 asphalt pavers, 35 kW, 4.0 m - - 95.59 - - - 2 deadweight rollers, 3 point, 10 t - £ 36.90 - - - tractor with front bucket and integral 2 tool compressor - - 20.02 - - - compressor tools : rammer - - 0.44 - - - compressor tools : poker vibrator - - 1.52 - - - compressor tools : extra 15 m hose - - 0.33 - - - tar sprayer, 100 litre - - 7.69 - - - self propelled chip spreader - - 10.73 - - - channel (heat) iron - - 1.19 - - - Total Gang Rate / Hour - £ 174.40 - - -

Concrete paving wheeled loader, 2.60 m3 - - 59.98 - - - concrete paver, 6.0 m - - 78.69 - - - concrete slipform finisher - - 19.50 - - - Total Gang Rate / Hour - £ 158.17 - - -

Road surface spraying tar sprayer; 100 litre - - 7.69 - - - Total Gang Rate / Hour - £ 7.69 - - -

Road chippings deadweight roller, 3 point, 10 t - - 18.45 - - - tar sprayer, 100 litre - - 7.69 - - - self propelled chip spreader - - 10.73 - - - channel (heat) iron - - 1.19 - - - Total Gang Rate / Hour - £ 38.05 - - -

Cutting slabs compressor, 65 cfm - - 4.88 - - - 12" disc cutter - - 1.41 3.52 - - Total Gang Rate / Hour - £ 6.28 3.52 - -

Cold milling cold planer, 2.10 m - - 56.13 - - - wheeled loader, 2.60 m3 - - 59.98 - - - Total Gang Rate / Hour - £ 116.11 - - -

Item Gang Labour Plant Material Unit Total hours £ £ £ rate £

Heat planing heat planer, 4.5 m - - 80.81 - - - wheeled loader, 2.60 m3 - - 59.98 - - - Total Gang Rate / Hour - £ 140.80 - - -

Rake and compact planed material deadweight roller, 3 point, 10 t - - 18.45 - - - tractor with front bucket and integral 2 tool compressor - - 20.02 - - - channel (heat) iron - - 1.19 - - - Total Gang Rate / Hour - £ 39.66 - - -

SUB-BASE

The following unit costs are generally based on the Highways Agency Specification for Highway Works and reference is made throughout this Section to clauses within that specification.