ABSTRACT

The article presents the results of solving the engineering and geotechnical problem of ensuring the safety of the building of the architectural monument, which is located in the immediate vicinity of the site of production work on the construction of a pit with a depth of excavation of more than 2.5 meters below the mark of laying the foundations of the existing building. The solution is presented through the implementation of a number of compensatory measures using modern injection technologies and an integrated approach to support design and construction through physical and mathematical modeling, geotechnical monitoring, and scientific and technical support.