ABSTRACT

ABSTRACT: This article discusses the challenges faced by the design team of two under river crossings of electric transmission feeders in an urban area. The under river crossing of a 138 kV transmission feeder was successfully completed through HDD. A second under river crossing of a 345 kV feeder, was initially designed as HDD, but was redesigned as a utility tunnel because of site constraints on both sides of the river.