ABSTRACT

The surface of plastic is one of the most critical steps of land reclamation. Due to rock mining stripping a large number of soil and expansion factors, the dump which stacked artificial is made up of steeper, longer slopes and flat panel. And the drainage system in a situation of disorder, can easily result in an unstable slope sites and aggravate soil erosion. According to the actual situation of Yuanbaoshan open pit coal mine, design requirements of the South Dump terrain are as follows:

1. Landscape of the Dump to be harmonized with the surrounding area;

2. Prevent soil erosion; 3. Meet demand biological reclamation; 4. Venues plastic should use bulldozers to build

cars road transport system, the transport system must take into account the biological reclamation and land-use process using the long-term future.