ABSTRACT

The second phase of the construction project of JLRD Company is to design and plan a transmission manufacture assembly line with a production capacity of double shifts of 150,000 sets based on the optimization of the data of technological process and standard hours of the first phase in the condition of original factory building area and technological process. Consider the operation rest interval to be 10%, the Takt time is 87 s. During the planning stage, people need to analyze the standard labor time and design the layout of the workstations and corresponding distribution route.