ABSTRACT

The objective of the subordination phase is to coordinate the activity of all other resources within the factory to ensure that the schedule established for the constraint is protected, that shipping is completed on time, and that raw material is released to the floor in synchronization with the way in which it will be consumed. It is an extremely important step in the process.